| 1) |
Name of the Project |
Guru Hargobind Thermal Plant Stage-II |
| 2) |
Location |
Lehra Mohabbat, Distt. Bhatinda |
| 3) |
Installed Capacity unitwise |
2 x 250 = 500 MW |
| 4) |
Type of Fuel |
Coal |
| 5) |
Executing Agency |
BHEL |
| 6) |
Clearances Status |
Cleared by CEA, New Delhi. Investment approved by Planning
Commission.All clearance obtained. |
| 7) |
Total estimated Cost |
Rs. 2123 Crores.(approx.) |
| 8) |
Synchronization dates |
Unit-3 Commercial Operation date (COD)16-10-08
Unit-4 COD expected on dated 31-01-09 |
| 9) |
Annual Generation at 68.5% load factor |
3000 MU 2715 MU Net |
| 10) |
Coal consumption / year |
1860000 Ton |
| 11) |
Cost of Generation |
Rs. 3.17 ( at Bus Bar). |
| 12) |
Latest Status |
Order is placed on turnkey/ EPC basis on BHEL on 31.03.04. Unit-3 COD 16-10-08 and Unit-4 COD expected on dt-31-01-09. |