1) Name of the Project Guru Hargobind Thermal Plant Stage-II
2) Location Lehra Mohabbat, Distt. Bhatinda
3) Installed Capacity unitwise 2 x 250 = 500 MW
4) Type of Fuel Coal
5) Executing Agency BHEL
6) Clearances Status Cleared by CEA, New Delhi. Investment approved by Planning Commission.All clearance obtained.
7) Total estimated Cost Rs. 2123 Crores.(approx.)
8) Synchronization dates

Unit-3 Commercial Operation date (COD)16-10-08

Unit-4 COD expected on dated 31-01-09

9) Annual Generation at 68.5% load factor 3000 MU 2715 MU Net
10) Coal consumption / year 1860000 Ton
11) Cost of Generation Rs. 3.17 ( at Bus Bar).
12) Latest Status Order is placed on turnkey/ EPC basis on BHEL on 31.03.04. Unit-3 COD 16-10-08 and Unit-4 COD expected on dt-31-01-09.