UBDC PROJECT STAGE - III

1)

Location

UBDC Hydel Channel Stage-III will take off at RD 65000 (left) of UBDC Main & will our fall into River Beas Down Stream Shally Pattan

2)

Main Features:

 
  1. Generation of Stage-I & II shall increased.
  2. Two Power Houses shall be set up giving additional Installed Capacity of 75 MUs.

3)

No. of Power Houses.

2

4)

No. of Units:

For PH-I = 3 Units

For PH-II = 2 Units

5)

Total generating capacity

3x15 + 2x15 = 75 MW

6)

Gross Head:

For PH -I = 17.03 M

For PH-II = 23.195 M

7)

Design Discharge:

For Phase -1

  • UBDC Stage Escape Channel =9325 cusecs
  • Carrier Channel =6888 cusecs
For Phase II:
  • Alternative Irrigation Channel =272 Cusecs to 43.76
For Phase III:
  • UBDC Hydel Channel Stage-III = 13245 Cusecs

 

8)

Type of Development

Run off River

9)

Commissioning:

2007-08

10)

Cost of Project:

Rs. 670 Crore (5/2000)

11)

Total Energy Contribution Annually

472.47 Mus.

12)

Cost per unit:

Rs. 2.94

13)

Cost of the Project:

Rs. 670 Crore (5/2000)