TARGET AND ACHIEVEMENT UNDER TRW CIRCLE PSEB LUDHIANA DURING THE YEAR 2006-07
YEARLY TARGET 4176 T/F'S - 6480 UNITS


SR.
NO.

MONTH /
YEAR

CAPACITY WISE T/F's REPAIRED

T/F'S REPAIRED

UNITS REPAIRED

PERCENTAGE OF PROGRESS

REMARKS

 

 

25
KVA

63
KVA

100
KVA

200
KVA

300
KVA

500 / 1000
KVA

During
the month

Progressive

During
the month

Progressive

T/F'S

UNITS

 

1

Apr-06

123

148

70

8

0

0

349

349

517.0

517.0

100.29

100.29

95.74

95.74

 

2

May-06

131

98

169

14

0

0

412

761

672.0

1189.0

118.39

109.34

124.44

110.09

 

3

Jun-06

151

65

134

14

0

0

364

1125

572.5

1761.5

104.60

107.76

106.02

108.73

 

4

Jul-06

45

135

105

14

1

0

300

1425

518.0

2279.5

86.21

102.37

95.93

105.53

 

5

Aug-06

28

101

119

26

1

0

275

1700

526.5

2806.0

79.02

97.70

97.50

103.93

 

6

Sep-06

29

82

135

23

2

0

271

1971

524.0

3330.0

77.87

94.40

97.04

102.78

 

7

Oct-06

30

110

130

20

1

0

291

2262

540.0

3870.0

83.62

92.86

100.00

102.38

 

8

Nov-06

86

171

147

5

0

0

409

2671

656.5

4526.5

117.53

95.94

121.57

104.78

 

9

Dec-06

41

162

187

9

0

0

399

3070

694.0

5220.5

114.66

98.02

128.52

107.42

 

10

Jan-07

39

228

149

17

1

0

434

3504

752.0

5972.5

124.71

100.69

139.26

110.60

 

11

Feb-07

37

243

140

11

0

1

432

3936

735.5

6708.0

124.14

102.82

136.20

112.93

 

12

Mar-07

17

196

171

27

1

0

412

4348

766.0

7474.0

118.39

104.12

141.85

115.34

 