PUNJAB STATE ELECTRICITY BOARD
(O/O C.E/Commercial) (Tariff
Regulation Directorate)
PSEB, Patiala
Commercial Circular No. 57/2004
Dated 9/12/2004
Sub: Revision of Tariff w.e.f. 1.10.2004
In compliance to the Punjab State
Electricity Regulatory Commission orders dated 30.11.2004 with reference to
PSEB petition No. 12 of 2004 relating to filing of ARR/Tariff Application for
2004-05, the tariff rates of power supply to various categories of consumers
as per tariff order issued by PSERC are revised as under:-
| Sl.No.(i) |
Category of consumers (ii) |
Energy Rates (P/ Kwh) (iii) |
MMC Rs/KW or part thereof
(iv) |
A) PERMANENT
SUPPLY
|
|
1) |
Domestic supply |
|
a) Upto 100 units |
200 |
Rs.
27
without rounding of load |
|
b) 101 to 300 units |
334 |
|
c) Above 300 units |
353 |
2) |
Non-Residential |
384 |
Rs. 99
without rounding of load |
3) |
Public lighting |
384 |
As per 8 hrs./day |
4) |
Irrigation tubewells |
i) Without Govt. subsidy
194 Ps / kwh
or Rs. 205/ BHP / Month.
ii) With Govt. subsidy 57 Ps/ kwh or Rs. 60 / BHP/ Month. |
N.A. |
5) |
Industrial supply |
|
|
|
a) Small power |
306 |
81 |
|
b) Medium supply |
337 |
108 |
|
c) Large supply |
|
|
|
i) General industry |
337 |
108 |
|
ii) PIU |
337 |
297 |
|
iii) Arc Furnace |
337 |
283 |
6) |
Bulk supply |
|
|
|
HT |
346 |
162/KVA |
|
LT |
368 |
162/KW |
7) |
Railway traction |
402 |
162/KVA |
8) |
Outside State |
248 |
N.A. |
B) SEASONAL INDUSTRY:
COTTON GINNING, PRESSING & BAILING PLANT, RICE SHELLERS/HULLER
MILLS, RICE BRAN STABILIZATION UNITS (WITHOUT T.G. SETS) S.P., MS &
LS |
| |
a) During season (1st Sept.
to 31st May) next year
SP
MS
LS |
Relevant industrial
tariff as per A (5) |
297
297
297 |
| |
b) Off season
SP
MS
LS |
363
391
388 |
N.A.
N.A.
N.A. |
| C)
ICE FACTORY & ICE CANDIES AND COLD STORAGE |
| |
a) Season (April to July)
SP
MS
LS |
306
337
337 |
405
(April to July) |
| |
b) Off season
SP
MS
LS |
-do- |
81
81
81 |
|
D) GOLDEN
TEMPLE, AMRITSAR AND DURGIANA TEMPLE, AMRITSAR. |
|
|
Golden Temple, Amritsar |
|
|
|
| |
a) First 2000 units |
Free |
N.A. |
|
| |
b) Beyond 2000 units |
273 |
N.A. |
|
| |
Durgiana Temple, Amritsar |
|
|
|
| |
a) First 2000 units |
As
per the pattern applicable for Golden Temple, Amritsar. |
|
| |
b) Beyond 2000 units |
|
| E) TEMPORARY SUPPLY |
|
| |
i) Domestic |
601 |
Rs.500 or
Rs.100/ kW whichever is higher |
|
| |
ii) NRS |
601 |
Rs.1000 or Rs.250/kW
whichever is higher |
|
| |
iii) Industrial
(SP,MS
& LS) |
As per tariff approved at A (5) above for
permanent supply + 100% |
Rs.400/kW of sanctioned load |
|
| |
iv) Wheat thrasher |
-do- |
-do- |
|
| |
v) Fairs, Exhibition & Melas
Congregations |
Bulk Supply tariff as at A (6) +50% |
Rs.4000 per service |
|
| |
vi) Touring Cinemas
a) Lights and fans
b) Motive load |
601
Rate for industrial permanent supply as at A(5)+ 100% |
For (a) & (b)
Rs.1000 or Rs.250/KW of Sanctioned load whichever is higher. |
|
NOTE:-
1. The tariff rates are applicable with
effect from 1.10.2004 and shall remain operative till fresh determination of
tariff by PSERC.
2.
The excess recoveries made by the Board from 1.4.2004 to 30.9.2004 will be kept
with the Board as Regulatory Reserve.
3.
The excess amount received from consumers on account of revised rates from 1.10.2004
will be adjusted in the future bills within the current financial year.
4. Domestic consumers
belonging to SC category, with connected load upto 300 Watts
will be given 50 units of free power per month in view of Government subsidy.
5.
The domestic consumers located in the rural area will be allowed 10% rebate
in tariff on consumption of electricity. For this purpose the definition of
rural area will be as followed by the State Govt.
6.
DS & NRS consumers to be charged MMC on the basis of actual sanctioned load
and no rounding off needs to be carried out for computing MMC.
7.
Checking of connected load by Board for only DS consumers suspended till further
orders.
8.
High Voltage Rebate:
High Voltage rebate allowed to all categories of consumers except Railway
Traction at the following rates:
i) Supply
voltage 33/66 KV
3% of energy
charges.
ii) Supply voltage
132/220 KV
5% of energy charges.
9.
THE EXISTING SURCHARGE FOR 11 KV ARC/INDUCTION FURNACE TO CONTINUE AS PER THE
EXISTING RATES.
10.
AGRICULTURAL PUMP SETS FOR IRRIGATION PURPOSE
(a)
AP tubewell consumers getting supply from rural feeders to be charged A.P. flat
rate / A.P. metered tariff.
(b)
AP tubewell consumers getting supply from urban / city / urban pattern supply
feeder to be charged AP metered tariff.
(c)
Farmers of Kandi Area, PAU Ludhiana, PSTC tubewells, lift irrigation & other
connections of tubewell released under SP/MS category who had applied connections
after 31.3.1990 to be charged as under:-
(i)
AP flat rate on rural feeder / AP metered rate on Urban Feeder.
(ii)
AP metered rate where M.S. tariff is being charged at present.
(d) AP consumers located within
Municipal limits will be covered under AP metered rate as before.
11.
The revised rates are exclusive of E.D., Octroi charges, and other taxes. E.D.
is not applicable for Agriculture consumption.
12.
All others charges / surcharge i.e. power factor surcharge, PLEC charges, late
payment surcharge, parallel operation charges including rentals and deposits
etc. which were being collected by the Board as per Sales Regulation for supply
of energy before the issue of this order will be continued to be charged at
the existing rates. Any provision not covered in this order shall continue to
be applicable as before.
13.
NOTICE FOR INTIMATION TO CONSUMERS
A notice of not less than 6 months to the consumers be served for revision
in the threshold limit of power factor to be maintained by them and Power Factor
incentive shall be as detailed below:-
(a)
THRESHOLD LIMIT
To be raised from 0.88 to 0.90 in respect of MS, LS and Railway Traction consumers
w.e.f. 1.7.2005.
(b) POWER FACTOR QUANTUM AND
INCENTIVE
(i) QUANTUM
The incentive for higher power factor will be @ 0.25% on consumption charges
for each 0.01 improvement in power factor beyond threshold limit given below
w.e.f.1.7.2005.
(ii) ELIGIBILITY OF INCENTIVE.
(a) For MS and LS (General Industry)
above 0.90
(b) PIUs, Arc Furnaces and Railway
Traction above 0.95
14.
A copy of above tariff rates may be displayed on notice Board of all the sub-divisions
/divisions/circles for wide publicity and for information of all the public.
The above instructions be brought to the notice of all concerned for compliance.
Director/Tariff Regulation,
for C.E./Commercial,
PSEB, Patiala.
|