Technical Audit and Inspection Wing in PSEB is responsible not only for quality
control of the material being inspected by the Inspectors, but also motivates
the field officers for exercising quality control for improving the quality
of works being executed by PSEB by way of regular checking. The TA&I Organization
also ensures proper use of material for execution of works. To achieve the purpose
three units headed by Dy.CE/Director/SE have been created under CE/Tech. Audit
& Insp. These units are:-
1. Inspection Unit Material Services presently headed by SE/MS
2. Technical Audit Unit(Electrical Wing) presently headed by Dir./TA(Elecl.)
3. Technical Audit Unit(Civil Wing) presently headed by Dir./TA(Civil)
1) Inspection Unit – Material Services
Under inspection wing, the material is got inspected immediately after the receipt
of inspection requisition against the orders placed by EIC/MM, CE/Workshops,
CE/Metering, CE/RE&APDRP by deputing Addl.SEs/Sr.Xens(Inspection). The inspection
of the material is done in accordance with provisions in Indian Standard/PSEB
Specifications and purchase order. The Inspection reports are scrutinized and
where after the despatches are allowed by the Competent Authority. Transformers
repaired by various Transformer Repair Workshops of PSEB are also checked/tested
by Sr.Xen/TRT who are part of the inspection wing. Jobs done during Financial
year 2005-06 and financial year 2006-07(upto 10.12.2006) are as under:-
| Sr.No. |
Description |
Financial year 2005-06 |
Financial year 2006-07(Upto 31.12.2006) |
| 1. |
Total No.of Inspection conducted. (Nos) |
2742 |
2002 |
| 2. |
Total length of conductor inspected (Kms) |
53277 |
36125 |
| 3. |
Total No.of transformers inspected. (Nos) |
60258 |
53589 |
| 4. |
Total No. of Meters inspected. (Nos) |
587883 |
384929 |
| 5. |
Total No .of Poles inspected. (Nos) |
372697 |
163111 |
| 6. |
Total length of Cable inspected (Kms) |
11207 |
7737 |
Apart from above the inspection of other Misc. items of material like G.O.Switches,
various types of Insulators, DPC wires & strips, Nut & Bolts, Structure
steel, T/F oil, Air Conditioners, Vehicles and Stationery etc. have also been
conducted. While conducting the inspection, material such as conductor, cables,
T/Fs and other items have been rejected in 155 number cases.
Regular meeting of all the Officers of Inspection Wing are held for technical
interaction, improvement in working discussing, suggestions and monitoring the
progress. Instructions/guidelines are issued from time to time to bring improvement
in the quality control system.
The job of works appraisal of the firms who participate for the first time
in PSEB for the supply of any item of material required for distribution system
is being done by SE/MS for evaluating the technical and financial suitability
of the firm towards supply of material, by actually visiting the firm premises.
2)Technical Audit Unit (Electrical)
This unit investigates the complaints received directly from the public or
forwarded by the higher authorities and submits the report to the competent
authority for decision. Further more, this unit conducts the checking of following
works on monthly basis:-
- Physical verification of material drawn from stores and used at site. '
- Petty purchase expenditure by the Sub-divisions.
- Physical verification of material received in various stores.
- Checking the compliance of computerized key exception reports, job orders,
ME-I and ME-II registers, compliance of Board’s instructions and other
misc. works.
- Checking of quality and calibration of energy meters.
The progress achieved during financial year 2005-06 and financial year 2006-07(
Upto 31.12.2006)is given as under:-
| |
During financial year 2005-06 |
During financial year 2006-07 (Upto 31.12.2006) |
| No. of inspections done. |
510 |
329 |
| No. of officers/officials penalized. |
127 |
77 |
| No.of complaints dealt. |
108 |
114 |
Further more, on checking the quality of material received in stores, in cases
where defects are found in material viz. cables, insulators, G.O.Switches &
ACSR, etc., the defective material is not accepted and the firms are suitably
penalized by sending strong signal of ‘No compromise in quality of material
by PSEB’.
Checking of works by Technical Audit unit is done in such a manner that some
of the area in every division is covered so that fear of existence of surprise
check persists for all the field officers/officials of the PSEB.
Depending upon work load some of the works appraisals are also assigned to
Director/Tech. Audit for evaluating the technical and financial suitability
to the firms who participated for the first time in PSEB for supply of material.
3) Technical Audit Unit (Civil)
Thel completions of Civil Works of all the electrical Sub-stations in the field
are checked by the Technical Audit Unit. Deficiencies, if any, are pointed out
which are got removed towards final settlement. During financial year 2005-06,
36 Nos. completion of works and during financial year 2006-07( upto 31.1.07)
8 No. completion of works have been checked by Tech. Audit.
Civil Works already done are selected at random and their quality of execution
and maintenance is checked as per rules and regulations. Deficiency, if any,
is intimated to the Competent Authority and accordingly administrative action
is taken against the officers/officials. In this regard, 32 no. divisions during
financial year 2005-06 and 9 No. during financial year 2006-07( uo to 31-1-07)
pertaining to P&M , Distribution Organization and TLSChave been checked
and 42 no. officers/officials have been penalized.
Physical verification of coal lying at the three no. Thermal Plants is done
quarterly and report sent to Competent Authority for further action.
Some of the firm’s works appraisals relating to civil material are also
assigned to Director/Technical Audit (Civil).
Further more, complaints regarding civil works are investigated thoroughly
by Technical Audit (Civil) and reports are put up to the Competent Authority.
In this regard 5 no. complaints have been investigated during financial year
2005-06 and 5 No. during financial year2006-07 (up to 31.1.2007). Special checking
of works of Mukerian Hydel Channel and Anandpur Sahib Hydel Channel have also
been conducted by Technical Audit and reports submitted to the Competent Authority
where suggestions have been made for further improvement in the method of execution
of works.
It is pertinent to add further that Technical Audit(Civil) also hold meetings
with field officers in routine for technical inspection and sounding the field
officers regarding maintaining of quality of the works so that field officers
may remain cautious and alert.
|