Dy Director/ Administration: attached with Chief Engineer/
SO&C, Patiala. Supervises the work of establishment section and other official
matters of the offices under the control of Chief Engineer/ SO&C.
There are four Directors and one SE under the control of Chief Engineer/SO&C
Director/ Power Regulation & Control:
This directorate is responsible for the load management in the state of Punjab
by balancing Supply of Electric Power against Demand of Electric Power. Management
of Supply side involves scheduling own generation, drawl of power from common
pool and central sector generation stations as well as banking arrangement with
other states & purchase of power through traders. On the other hand Management
of demand side involves scheduling of electric power supply to various categories
of consumers through restrictions on the timings for supply, Peak Load restrictions
on industry as well as load shedding activity. State of the art EMS/ SCADA system
is a tool available with this office for online monitoring of the power system
in Punjab as well as whole of the Northern Region of India.
Besides this, whole of power data for the state of Punjab is being compiled
and maintained. Industries which are continuous process in nature are declared
after due process involved. Exemptions from Peak Load restrictions for industry
are also processed by this Directorate.
Special Requirement of Additional Web Pages for Displaying Data/ P.R.
Circulars related to this Directorate:
- As per CERC & PSERC directives State Load Dispatch Center is to maintain
some information about Open Access transactions. As such pages may be reserved
to account for this requirement. Necessary data for these pages will be provided
subsequently.
- Webspace for Power Regulation Circulars which are issued by this office
from time to time are required to be displayed on the web site under “Regulations”
category. Data/ text may be taken from the existing web site of PSEB (www.psebindia.org)
Director/ SLDC:
Main functions & Activities of SLDC Directorate :
- SLDC Directorate has been instrumental in implementing/commissioning of
the Unified Load Despatch & Communication (ULD&C) scheme in PSEB which
is functional since July 2002. This scheme comprises of SCADA/ EMS (Supervisory
Control & Data Acquisition/ Energy Management System) system provided
by ALSTOM and provides on-line data of integrated power system network at
the Control centers located at SLDC Patiala and two Area Load Despatch Centers
(ALDCs) at Lalton Kalan (Ludhiana) and Jamsher (Jallandhar). Wide band MW
Communication network has been provided on main trunk route which is further
linked with NRLDC New Delhi from where central sector power projects and energy
drawl data is received.
- SCADA system for 66KV Ring Main System at Ludhiana :
There is a proposal to provide SCADA system for 66KV ring main system
at Ludhiana covering about 44 No substations. On line data from these stations
shall be available at a centrally located Distribution control center to be
located at Mini Sectt. , Ludhiana
Status:
• M/S Tata Consulting Services appointed as consultants for the project
• Feasibility study cum Basic study report approved by the Board
• DPR prepared by the Consultants under approval of the Board.
- Intra-state boundary Metering for ABT amongst Discoms, transco & Genco
There is a proposal to implement intra-state/ ABT Boundary metering for post
unbundling structure of PSEB amongst three DISCOMs, Transco and Genco.
Status:
• M/S Power Grid Corporation of India has been appointed as consultants
for implementation of the boundary Metering scheme in PSEB and providing necessary
software
• NIT has been floated for design, supply, erection, testing & commissioning
of SEMs (Special Energy meters), data communication, hardware/ software for
ABT etc.
• The scheme involves installation of SEMs at specified locations, collection
of metering data on weekly basis and preparation of energy account, bill generation,
etc on weekly basis.
• Open access consumer requirements shall also be covered under above
metering scheme.
2) Achievements of SLDC Dte. :
- State Load Despatch Center, using state of the art technology (i.e. computers,
modern communication media etc.) has been established in SLDC building at
220KV Grid Sub-Station, Ablowal, Patiala for collection of on-line data from
Punjab’s Generating stations, 220KV & 132 KV Sub-Stations. SCADA
scheme had been implemented in PSEB in two phases namely Interim SCADA Scheme
and Unified SCADA scheme.
- SCADA scheme for the 1st time in PSEB was introduced as Interim SCADA scheme
in the year 1999 covering most important Generating stations and 220KV &
132KV sub-stations. The scheme was integrated with Unified SCADA scheme in
the year 2002.
- Unified SCADA/EMS scheme under Unified Load Despatch & Communication
Project had been commissioned in the year 2002 through Power Grid Corporation
of India Ltd. (PGCIL) for all the Northern Region constituents’ viz.
HVPNL, DTL, PSEB, HPSEB, RRVPNL, UPPCL, PDD Jammu and central sector including
BBMB.
- Total 49 Nos. important stations (220KV & 132KV only) including all
Gen. Stations have been covered under Unified SCADA/ EMS scheme.
Director/ Communication Design:
Design Directorate Communication is responsible for Design/Procurement of the
following Communication equipment required for new communication links and for
replacement of existing defective/out lived equipment and the same is made available
to the SE/Communication 'Op.', Circle, PSEB, Jallandhar for Installation/ Commissioning
at various Sub-stations of P.S.E.B.:-
1) Power Line Carrier Communication : Single / Twin Channel Terminals for Speech
and Data transmission
2) Wave Traps : 1mH, 1250A, 220KV 0.5mH, 800A, 66KV & 132KV
3) Coupling Capacitors : 8800pf, 66KV/132KV/220KV
4) Telephone Cable : Single pair/Multi pair (Armoured/ Un-armoured)
5) H.F Cable : 150 ohm balanced (armoured)
6) Coupling Devices : 100W, 200W & 650W Phase to Ground, Phase to Phase
7) 48V DC Battery Chargers : 20A, 40A, 60A & 80A rated
8) 48V DC Batteries : 2V, 24Nos. Tubular/VRLA-MF Cells (60AH, 100AH, 200AH,
300AH & 400AH Capacity)
9) Telephone Sets : Basic and 1 + 1 Plan sets (extension sets)
10) Telephone Exchanges : (PLCC / Non-PLCC Version)
11) Microwave System
12) Data Modems
Besides above, Communication options like Optical Fiber System, Lease Line
and Low cost Microwave system are also explored for speech/data transmission
among the various Sub-Stations of PSEB.
Director/ ISB:
Inter state Billing Directorate is entrusted with the work of purchase /sale
of electrical energy from various Central Sector Generating Station i.e. NTPC,
NHPC, NPCIL, PTC etc., Co Gen projects, IPP Projects and other Electricity Boards
as well. For the purchase of energy from Co Generators, job of signing of PPAs/
MOUs and execution thereof is entrusted to this Directorate. Annual payments
against energy bills to the tune to Rs 2000 crore per annum is being made by
this office.
2. Achievements supported with statistical data, tables, graphs etc.
Energy bills relating to all Central Projects and projects under NRSE Policy
etc. are being verified and the payments released during the last 5 years is
as under:-
2001-02 |
2002-03 |
2003-04 |
2004-05 |
2005-06 |
(Rs In Cr)
1203
|
(Rs In Cr)
1508
|
(Rs In Cr)
1595
|
(Rs In Cr)
2281
|
(Rs In Cr)
2405 |
SE/ Communication Operation Circle, Jallandhar:
1. Communication (Operation) Circle, Jallandhar takes care of the speech/ data
through wireless, microwave and Power Line Carrier Communication system in whole
of Punjab and some parts of the adjoining States e.g. J&K, H.P also.
2. Statistical Data:
Number of PLCC terminal - 1657
Number of wireless sets - 200
Number of telephone exchanges - 80
Number of MW connected speech stations - 52
Number of Data stations - 49
3. Important activities:
- Communication Circle plays an important role in the Power Management by
keeping communication links for SCADA system functional.
- Construction as well as operation of PLCC links for the purpose of speech
as well as data transfer.
- Installation, testing, commissioning and upkeep of protection couplers
for carrier inter-tripping on various important link stations.
- Testing and commissioning of PLCC equipment.
- Operation and maintenance of inter communication in head offices and mini
secretariats of PSEB.
- Repairing of the sophisticated modules in the module repairing labs at
Jallandhar and Ludhiana.
- Imparting training to the staff of the communication organization.
- Providing technical support to the Communication Design Directorate, SLDC
Directorate, PR&C Directorate.
4. Achievement:
Modern air conditioned training cabins is set up in T&C Hall at Jallandhar.
PSEB is the only constituent of ULDC scheme SC&NR Project, which has planned,
installed, tested and commissioned the PLCC equipments of its own. PSEB is maintaining
this equipment of its own whereas other constituents have executed the same
through firms. PSEB was especially requested by the other constituents to impart
training on data communication over PLCC. As such PSEB has already imparted
training to 24 No. participants of various other constituents of ULDC scheme,
namely Nuclear Power Corporation of India, M/s ALSTOM (Now M/s AREVA), UPPCL,
HVPNL, HPSEB, DTL, BBMB, & PGCIL. |