SALIENT FEATURES OF VOLUNTARY DISCLOSURE SCHEME
FOR REGULARISATION OF EXTENSION OF LOAD IN AGRICULTURE SECTOR.
Being introduced now to remain valid up to 30.6.2004:-
(i) AP consumers who got AP
connections released under general or any other priority category shall deposit
Rs.4000 per BHP for all types of motors for unauthorized loads irrespective
of the type of pumpset installed.
ii) ACD @ Rs.200/- per BHP for
the extension in load shall be deposited.
(iii) The regularization shall be done immediately
as deemed regularization on detection of unauthorized load or self declaration
by the consumer regarding unauthorized load. The formalities regarding submission
of the sanction of A&A forms shall be done later on. The consumer shall
install the shunt capacitors of requisite capacity as per the total load and
the test report should indicate the installation of such a capacitor.
(iv) No load surcharge on self declaration
or detection through checking shall be recovered from the AP consumers during
the validity of the scheme.
(v) Augmentation of the line and distribution
transformer, wherever required after its close verification by Sr.Xen/Op concerned
shall be done by PSEB at its cost. For the purpose of regularization of the
load, the loading of the transformers may be taken as 100% instead of the existing
80%. Secondly, in case with the addition of unauthorized load the loading becomes
beyond 100%, the transformer up to 63/100 KVA may be installed on the existing
pole mounting sub-station with the prior approval of SE/Op
(vi) The scheme shall
remain valid up to 30.6.2004 . After the closure of the scheme in case tube
well consumer is detected to have installed unauthorized load or himself
declares the unauthorized load, his case for regularization of unauthorized
load shall be considered provided he pays the consumption charges for the last
six months in addition to the regularization charges mentioned in Para (i) &
(ii) above. |