ELECTRICITY SUPPLY REGULATIONS
((SECTION-IV)
ENERGY METER & METER RENTALS |
 |
61. PROVIDING METERING EQUIPMENT:
61.1 A correct meter of suitable capacity shall be installed at the point of
commencement of supply on the premises of the consumer for measuring the energy
supplied to him in items of section 26 of the Indian Electricity Act,1910, which
interalia states, "In the absence of an agreement to the contrary the
amount of energy supplied to a consumer or the electrical quantity contained in
the supply shall be ascertained by means of a correct meter and the licensee
shall, if required by the consumer cause to be supplied with such a meter."
61.2 The consumer may, if he so elects, cause his own meter duly tested at the
Board's Laboratory or tested by Chief Electrical Inspector to Government Punjab,
to be installed which will be sealed by the Board. The consumer shall ensure
that he purchases a meter of good quality and the meter should bear ISI
Certification mark and it should pass various tests as per Indian Standard
specification and Board's specification from the firms duly approved by the
Board from time to time.
61.3 Deleted
61.4 Installing meters for general ,agricultural and industrial supply:
61.4.1 Meters installed for recording the industrial and general consumption of
an industrial consumer should be housed in two independent meter-cup-boards( the
cost of these MCBs is to be recovered from the consumer) so that the seal of
meter-cup-board installed for industrial consumer is not unnecessarily broken in
the event of any fault in the general supply meter. Such a step is necessary for
minimizing the chances of access by any unscrupulous consumer to the meter
and/or MDI installed for recording industrial consumption. Agricultural
connections shall be released only after installation of suitable capacity meter
(preferably electronic meters).
61.4.2 TPT/KWH meters having CTs and PTs should be housed in the cubicles
standardized by PSEB and sealed by the officer concerned in such a manner as to
eliminate the chances of tampering and meddling with the equipment by the
consumers.
61.4.3 Metering the Consumption of Stone Crushers: The metering of the
stone crushers should be done on 11 KV even under MS category and consumption
should be metered at 11 KV. 7.5% discount as admissible shall be allowed if the
transformer is installed by the consumer otherwise no rebate shall be allowed
where Board's transformer is installed.
62. SITE FOR INSTALLATION OF METER:
62.1 In accordance with condition No.22 of the" Conditions of Supply' the
Board reserves to itself the right to fix the position of the meter.
62.1.1 The energy meter should be installed at the commencement of supply, as
far as possible, just near the entrance of the premises so that it is easily
accessible to the Board's employees for reading and testing etc.
62.1.2 Energy meter should be installed at a dry place. If it is doubtful that the location selected for the meter may not be dry
under all conditions of weather, it should be installed in a water proof case. Where meters are installed in very dusty places such as in rice shellers,
flour mills, saw mills or surkhi or lime mills, stone crushers etc., these must
be installed in dust proof chambers, and inspected at intervals not exceeding 3
months.
62.1.3 The site of the meter should be selected with due regard to consideration
of economy as well as the convenience of the Board employees in the discharge of
their duties. As far as possible,
the meter should be installed at a place where entry into purdah or religious
place is not involved for its reading, checking or testing etc.
62.2 Location of metering equipment for LS/BS connections.
62.2.1 No new LS or BS connection will be released unless the consumer provides
a separate room of approved design/specifications adjacent to the main entry
gate for installation of metering equipment. The room will have access from inside the factory premises.
62.2.2 All 11 KV connections having load of 1 MW or above, rice Sheller
connections, ice factories, stone crushers and cold storages shall also provide
separate room of approved design/specification adjacent to the main entry gate
for installation of metering equipment. The
design and size of the room shall be intimated to the consumer in the form of
drawing to be supplied by Director/DS(Engg.). The gate of the room may be from
within the factory premises. Cost
of shifting of meters including the cost of cable will be borne by the Board. Location of the metering room will be decided in consultation with the
Sr.XEN/Addl. SE(Enforcement).
62.2.3 Director/Enforcement while advising the shifting of meter/metering
equipment will keep in view that the working of meter/metering equipment is not
likely to be adversely effected due to dust, excessive vibration of the energy
consuming apparatus/D.G.Sets of the consumer etc.
63 SEALING OF METERS ETC:
After the meter has been tested in
the ME Laboratory and found to be working within the limits of accuracy, the
cover of meter which encloses the vital mechanism for measurement and recording
of energy consumed, shall be sealed by ME Organization lest it is tampered with
by any un-authorized person. The
meter cover seals originally
affixed by ME staff should not be tampered with by other employees of the Board. The meter terminal and MCB seals of meter/secondary equipment will be
affixed by the Board officials, as follows:-
|
63.1.1
|
Line Man
|
:
|
Single Phase domestic/NRS and
metered supply of AP connections.
|
|
63.1.2
|
JE/AAE
|
:
|
Three Phase DS /NRS /SP /MS
connections including connections of Board employees and Street Lighting.
|
|
63.1.3
|
AE/AEE/XEN(Ops.)
|
:
|
NRS connections with load above
100 KW, LS and BS categories of connections with loads below 500 KW.
|
|
63.1.4
|
Sr.Xen/
Addl.SE(Ops.)
|
:
|
LS and BS categories of
connections with Loads of 500 KW and above.
|
|
63.1.5 For having effective & accurate auditing for sale of energy
through 220/132/66/33 KV independent feeder at the sending end duly
calibrated and sealed installed by SSE/Sr.Xen. Grid Mtc./Op or P&M and
checked for accuracy of meter and connections within 15 days from the date
of installation by MMTS. Sr.XEN/Incharge shall maintain proper record of
the readings and forward the same for comparasion to Sr.Xen/Op. concerned.
63.1.5.1 EHT/HT
KWH meters, CTs/PTs housing and panel door of breaker controlling
220/132/66/33/11 KV independent feeders shall be sealed and meter reading
recorded by the following:-
|
|
63.1.5.2
|
At 132/220 KV Sub-Stations
|
:
|
by SSE Incharge.
|
|
63.1.5.3
|
At 33/66 KV Sub-Stations
|
:
|
by SSE or AE/AEE Incharge
maintenance
|
|
|
|
|
|
|
Note:- In Sub-Division where there is no post of AAE or the post
is vacant , the sealing work assigned to AAE shall be done by AE/AEE/Op.
concerned.
63.2 Normally it should be ensured that meter terminal cover and MCB seals are
affixed by the competent authority at the time of release of connection. Where it is not possible to do so due to circumstances beyond the control
of competent authority, the
connection may be released by affixing seals by an authority one step lower than
the competent authority ( not applicable in case of J.E.). However, in such cases the proper sealing must be done by the competent
authority within a period of 10 days.
63.3 Detailed instructions of checking of various connections by different
authorities have been given in Reg. No.134.5. it is also incumbent upon the officer/official taking over the charge of
a sub-office/Sub-Division to check the connections as per standing instructions
contained in Reg.No.112 as amended from time to time. While carrying out such checking, where an officer/official is competent
to affix the seals, he will break open such seals at the time of checking and
affix his own seals. Where the
sealing authority is other than the checking authority and the checking
authority suspects the working of meter to be defective without breaking open
the seals, the seals may be broken
to confirm the defective working/wrong connections of such metering equipment if
considered necessary and fact about
breaking seals brought to the notice of competent authority for re-fixation of
seals immediately. However, in the
meanwhile in such cases the checking authority will affix his own seal/paper
seal which shall later on be replaced by the competent sealing authority. Normally the seals affixed by higher sealing authority as defined in Para
63.1 above shall not be broken by lower sealing authority. In rare and emergent circumstances, if it becomes necessary to break open
the seal for checking of connections, the seal may be broken with the approval
of sealing authority or in his presence.
63.4 Paper seals are also affixed by the Enforcement Officers alongwith the
consumer's signatures during the course of the checking of the consumers.
63.4.1 If the existing seals are broken during checking by Enforcement officers,
paper seals should be affixed so that the metering equipment is not left
un-sealed till new seals are replaced by the concerned officer responsible for
resealing.
63.4.2 The meter and the metering equipment be kept under observation and the
same is not to be disturbed.
63.5 The paper seals wherever affixed by Enforcement Officers to keep the
meter/metering equipment under observation as per Para 63.4.2 shall be removed
within a period of three months. In
case it is still necessary to keep such industrial units under watch, new paper
seals be affixed by Enforcement Officer for a further period of three months. Under no circumstances the paper seals affixed by Enforcement Officer be
allowed to continue beyond six months.
63.6 In order to obviate the possibility of tampering with the meters by
unscrupulous consumers by providing fake seals, paper seals in addition to lead
seals should also be affixed by the concerned officers in respect of consumers
having load more than 50 KW. In doubtful cases paper seals in addition to lead seals will
be affixed by the concerned officers irrespective of load of the consumer.
63.7 Record of such paper seals should also be maintained in the relevant MSR
(Meter Sealing Register). Normally
paper seals should be affixed on meter terminal cover, meter cover and CT/PT
chamber. Whenever paper seals so affixed are found to be damaged
either by the officer responsible for providing seals or some other
officer/official, the sealing officer should replace the paper seals by making
suitable entries in the MSR to this effect.
63.8 In order to offset even remove chances of theft of energy by LS/MS
consumers, all the metering equipment provided with CT/PT units shall be
properly sealed and holes, if any existing, should be carefully plugged. CT/PT terminals should be taped. Special
care should be taken in checking such consumers whose average monthly energy
bill is more than Rs.1 Crore.
64 RESEALING OF METERS ETC.
64.1 It should be ensured that seals affixed by the Board on the metering
equipment always remain intact. Whenever breakage of seal comes to notice, it should be
replaced by the authority who had originally affixed it without any undue delay. In such cases, where it is established that the seals affixed at the time
of releasing the connection were not broken by the Board employees, necessary
charges for resealing as provided in the schedule of 'General Charges' should be
recovered.
64.1.1 Before resealing the meter terminal cover, it should be ensured that the
terminal connections of the meter including connections of CTs and PTs are in
order.
64.1.2 Before resealing the meter terminal cover, it should be ensured that the
terminal connections of the meter including connections of CTs and PTs are in
order.
64.1.2 The record of monthly consumption of such a consumer should also be
checked to verify if his consumption in the last few months has not been
abnormally low. In such a case
depending on its merits and if there is strong suspicion of some foul play, the
account of the consumer maybe adjusted as per the procedure laid down under Reg.
No.73.
64.1.3 Future consumption viz-a-viz the
previous consumption should be kept in view to arrive at some final decision to
overhaul the accounts of the consumer.
64.1.4 Concerned officers required to affix seals should take due care while
performing their duty. In case the
seals affixed by them are found to be intact by Enforcement checking authorities
and the consumer is found to be indulging in theft of energy and meter is found
to be recording less due to wrong connections, it shall be assumed that the
officer./official who had affixed the seals is also conniving with the consumer
in indulging in theft of electricity or malpractice.
64.1.5 As regards industrial consumers where the meter involves connections
through CTs/PTs and/or having MDIs, if the seals of the meter cup-Board and
meter terminal cover etc. are broken for attending to some fault in the supply
or the meter or for some other reason, the seal should be affixed by the AE/AEE/XEN(Ops.)
without delay so that the consumer is not in a position to meddle with the
metering equipment. In case the AE/AEE/XEN(Ops.)
is not available at the headquarters, the AAE/JE should affix the seals, which
should be replaced by the AE/AEE/XEN(Ops.) immediately on his return. Matter with regard to sealing by the AAE/JE should promptly be reported
in writing as well as orally to the AE/AEE/XEN.
64.1.6 Cases of consumers in the sub-offices should also be dealt with likewise
and the AE/AEE/XEN(Ops.) must see to the sealing work of these consumers on his
next visit to the sub office which should be arranged at an early date. In case of ordinary industrial
consumer the seal of the meter-cup-Board may in the first instance be fixed by
the AAE/JE concerned but the AE/AEE/XEN(Ops.) should replace it during his
periodical inspection. However, if
the seal relates to meter terminal cover, it should be replaced by the AE/AEE/XEN(Ops.)
at the earliest.
64.2 Meter Cover Seals Affixed by Metering Equipment Labs: In addition
to recovering the resealing charges as per the schedule of ' General Charges' ,
it has further to be ensured that the seal has not been broken by the consumer
intentionally with a view to indulge in theft of energy by tampering with the
internal mechanism of the meter. In
order, therefore to plug this potential source of leakage of revenue, following
procedure should be adopted whenever any case of the breakage of ME/Meter Cover
Seal comes to notice.
64.2.1 Authorized representative of the Board as detailed under Reg.No.63 should
be deputed for affixing paper seals under his signature on cover of the meter to
ensure that it is not possible to open the meter cover without tearing the paper
seals.
64.2.2 He will keep the broken seals if found at site in :as found conditions so that the same can be offered as evidence in court
of law or before 'Dispute Settlement Committee". The factum of breakage of seal or its collection from site, if possible,
should be got confirmed from the consumer by getting his signature on the '
Memorandum of Inspection and Seizure' for evidence.
64.2.3 He should also try to see if there are any other signs of tampering with
metering equipment to suppress the recording of actual consumption of energy. He will record all such sign/pieces of evidence in the memo of inspection
and seizure which may be witnessed by the consumer or his representative at
site. A copy of the said memo shall
be handed over to the consumer/his representative at site.
64.3 In case theft is not established, meter may be replaced through MCO and
meter sent to ME Lab for testing and checking.
64.4 If theft of energy is established, the meter should be removed/replaced. The meter so removed should be kept in sealed container under signatures
of the consumer as well as the checking authority for further investigations and
the consumer be asked to deposit the compensation and AACD in terms of Condition
No.43 of Conditions of Supply and Reg.No.133.3.
64.5 Defective/Inoperative Meter:
64.5.1 If the meter is found to be running slow by more than 3% before replacing
the meter the consumer should be asked to given a undertaking in writing that he
will pay the additional charges, if the meter on actual testing in ME Lab is
found to be running slow.
64.6 After removing the old meter, it should be replaced with a new meter
after charging the meter changing fee. The
meter on removal should be sent to the ME Laboratory within a maximum period of
15 days and account of the consumer should be adjusted immediately on receipt of
the test results from the ME Lab.
64.7 All the meters removed against MCO shall be first checked by concerned JE./AAE
and only such meters shall be packed in cardboard box where theft of energy is
suspected. Cardboard boxes shall be
sealed and duly signed by concerned JE/AAE and the consumer /representative of
the consumer. Testing of such meters should be done in the presence of the
consumer or his representative. In
case the consumer refuses to sign the meter test results./report such meter shall be kept sealed in the Operation Sub-Divisions till final
disposal of the case. In case of meters where theft of energy is not suspected
by JE and the meter is sent to ME Lab without packing if theft of energy is
deducted later on pertaining to such meter then JE concerned shall be held
responsible.
65 SECURITY DEPOSIT AND MONTHLY RENTALS:
65.1 If the prospective consumer desires the Board to supply and install the
meter on monthly rental basis, he will have to deposit the security therefore as
per the 'Schedule of General Charges" as amended from time to time.
65.1.1 Where meters are installed by the Board at the premises of AP consumers
meter rentals shall be recoverable. However in case of Flat rate Tube well consumers where meter is installed by Board for
sample metering, no rentals shall be chargeable. The consumer shall however be
responsible for maintenance and upkeep of meter to avoid any damage to the
meter. In such cases if meter is found damaged its cost will be recoverable from
the consumer.
65.2 Meter Hire if the Meter is supplied by the Board:
In addition to paying the security deposit a consumer shall have to pay
the following monthly meter rentals in accordance with Schedule of General
Charges, as amended from time to time. Rates
in force w.e.f. 1.4.2000 are as under:-
1. Single Phase E/M Meter Rs.11/- per month.
2. Single Phase Electronic Meter Rs.22/- per month.
3. Three Phase/Poly Phase E/M Meter Rs.25/- per month
(Without CTs)
4. Poly Phase Electronic/Static Meter Rs.41/-permonth 3x 10-40 A
5. Three Phase LT meters with CTs.
i) 50/5 Amp. CTs Rs. 57/- per month
ii)100/5A, 150/5A, 200/5A,300/5A
and 400/5 Amps CTs Rs. 42/- per month
6. LT CT operated Solid State/Electronic Rs.125/- per month
meters (without CTs)
7. Solid State/Electronic HT/LT TPT Rs.320/- per month
metering equipment(without CT/PT units)
8. Other LT/HT Polyphase meters/metering: 1.6
paise per rupee
equipment not covered under Item 1 to 7 cost of the meter/ above and CT/PT units given in Para-66.1.4. metering equipment
per month.
Note: Rate of meter rental for Board employee for domestic connections
will be 50% of the rates prescribed under Schedule of general charges.
65.2.1 DELETED.
66 CONSUMER'S RESPONSIBILITY FOR LOSS OR DAMAGE OF METER:
As per Condition No.34 of the Conditions of Supply, consumer will be
responsible for any loss or damage to the meter whether caused maliciously or
through culpable negligence or default on the part of the consumer or any of its
employees, and shall be responsible for paying the cost of repairs or of the
meter itself if the same is declared to be irreparable by the XEN/ME in accordance with the following procedure:-
66.1 Cost of burnt/ partially damaged meters at the premises of DS, NRS and SP
consumers shall be recovered as per the rates circulated by the CE(Comml.) from
time to time or as contained in Schedule of General Charges. The charges in general shall be regulated as under:-
66.1.1. Whenever a meter after getting damaged 50% of the cost of meter rounded off to the nearest rupee, be got
deposited from the consumer found to be at fault.
66.1.2 Whenever a meter after getting damaged can be repaired in the ME Lab,
lumpsum amount irrespective of the actual cost of the repairs be got deposited
as under:-
66.1.2.1 Single Phase Meter E/M Rs.200/- per Meter
66.1.2.2 Single Phase Electronic meter Rs.400/- per Meter
66.1.2.3 Three(Poly) Phase E/M Rs.350/- per Meter
66.1.2.4 Three (Poly)Phase Electronic/Static Meter Rs.700/- per Meter
66.1.3 For other categories of consumer, full cost shall be recovered.
66.1.4 Amount recoverable from the consumer when the meter is found to be
damaged owing to negligence or default or the part of the consumer will be as
under w.e.f 1.4.2000 and shall be subject to modification from time to time. The amounts given hereunder are inclusive of the replacement charges of
the damaged meters.
|
1
|
Single
Phase E/M Meter
|
:
|
Rs.695/-
|
|
|
a)
|
2.5
?10 Amp.
|
|
|
|
b)
|
5-20
Amp.
|
|
|
|
c)
|
10-20
Amp
|
|
|
|
d)
|
10-40Amp.
|
|
|
|
e)
|
20-40Amp
|
|
|
2
|
Single Phase Electronic Meters
(10-40A)
|
:
|
Rs.1,370/-
|
|
3
|
Polyphase
E/M meter
|
:
|
Rs.1,550/-
|
|
|
a)
|
3x10-20
Amp.
|
|
|
|
b)
|
3x20-40 Amp.
|
|
|
4
|
Poly Phase Static Meter ( 3x
10-40 A)
|
:
|
Rs.2,570/-
|
|
5
|
LT CT meter (Without CTs)
|
:
|
Rs.2,000/-
|
|
6
|
LT CT operated Solid State Meter. (without CTs)
|
:
|
Rs.7,840/-
|
|
7
|
LT TPT metering equipment (without CTs)
|
:
|
Rs.13,625/-
|
|
8
|
HT TPT metering equipment(without
CTs/PTs unit) other than L&G make
|
:
|
Rs.15,625/-
|
|
9
|
Solid
State LT/HT TPT metering equipment
(without CT/PT unit)
|
:
|
Rs.20,000/-
|
|
10
|
LT
CTs
a)
50/5 A
b) 100/5, 150/5 , 200/5, 300/5 & 400/5 A
|
:
:
|
Rs.1,580/-
Rs.
600/-
|
|
11
|
HT
CTs/PTs Unit
|
:
|
Rs.40,470/-
|
66.1.5 Before recovery of cost of damaged/partially damaged meters,
investigation should be carried out as provided in Reg.No.67.
66.2 If 11 KV CT/PT unit is damaged, full cost is to be recovered before
replacing the damaged CT /PT unit. The cost to be recovered shall be as per cost of CT/PT unit
circulated from time to time.
66.3 If a meter/metering equipment of requisite capacity is not available, the
consumer should be informed to arrange his own meter/metering equipment of
requisite capacity.
67. FOLLOW UP FOR DAMAGED OR BURNT METER.
67.1 If an energy meter/metering equipment or a component thereof is reported
dead stop, damaged or burnt, before replacing the meter the site shall be
inspected by AE/AEE/XEN(Ops.) in respect of 'LS' 'MS' and 'BS' consumers. However, ordinary cases of general meters reported dead stop by Meter
Readers and Meters Inspectors may be inspected by the J.E. The AE/AEE/XEN(Ops.) should carry out investigation and record his report
on the following lines to determine as to whether the damage to meter is due to
the default/negligence on the part of the consumer as per provision laid down in
clause 34 of the 'Conditions of Supply' :-
67.1.1 Whether the seal of M.C.B meter terminal cover, meter cover and CT/PT
junction box are intact.
67.1.2 Whether there are any unauthorized extensions.
67.1.3 Any outward and physical signs of damage.
67.1.4 Any leakage of rain water into the equipment or meter.
67.1.5 Any lightning effect.
67.1.6 Any sign of spark-over at the terminals.
67.1.7 Any other causes.
67.2 Whenever meter is reported burnt/defective by any domestic
consumer(Single Phase only) direct supply shall be allowed by the Lineman on
duty at the complaint centre. After
restoration of supply, the lineman shall issue 'Direct Supply' order for which a
bound order; book having copies in triplicate shall be made available at all the
complaint centres by the Divn. office. The
order book shall be issued direct to the lineman and its record maintained in
the Divnl. Office.
67.2.1 The Lineman on duty will record day and time of giving direct supply
alongwith other information and will also simultaneously get consent of the
consumer on the 'Direct Supply' order that he will deposit necessary charges
which may be debited to his account by the Board through his electricity bill. The lineman shall hand over first copy of the 'Direct Supply' order to
the consumer immediately thereafter. The
2nd and 3rd copy of the order book shall be handed over to
the JE Incharge of the area on the very next day for submission of his complete
report. The JE shall check the
meter thoroughly and give his complete report regarding reasons of
burnt/defective meter. The 2nd
and 3rd copy of the order book duly filled in shall be handed over by
the JE to the SDO/RA on the next working day for further action in the matter.
67.2.2 The RA shall issue meter change order for replacement of burnt/defective
meter and hand over to JE on the same day. The JE shall get the meter replaced immediately and shall also record
total time on the MCO for which supply of the consumer remained direct. After effecting the MCO, the same shall be returned to the RA for
debiting the required charges to the consumer's account through SC&A
register. After making all the
entries in the 2ndk and 3rd copy of direct supply order, the 2nd
copy shall be pasted in the Sundry Register and cross entry made on the MCO. The 3rd copy shall be returned back to JE for pasting in the
job order book for reference and record.
67.2.3 It shall be the sole responsibility of the lineman to keep 'Direct
Supply" order; book intact/complete. In
the event of completion of a order book, the same shall be deposited with the
Divisional Office and new book got issued by the Lineman. It shall also be sole responsibility of the lineman to ensure
availability of the direct supply order book at the complaint centre. In the event of transfer of a lineman from one complaint centre to
another he shall hand over his order book to his successor. A handing over note shall, however, be recorded in the order book duly
countersigned by the JE Incharge.
67.2.4 The order book shall be got printed by the Sr.XEN/Addl.SE/Op. as per
enclosed proforma. Each book shall
carry Sr.No.having 100 leaves in triplicate. Each leaf of the book shall carry machined No. The complete record regarding issue/receipt of order; book to/from
lineman shall be maintained in the Divn. Office.
67.2.5 It will be the primary responsibility of the Sub-Divisional Officer (AE/AEE/XEN/Op)
to ensure the compliance of the above mentioned guidelines/instructions. In case of failure strict disciplinary action shall be taken against the
delinquent officers/officials.
67.3 The damaged/burnt meter alongwith first report will be forwarded to ME
Laboratory by AE/AEE/XEN(Ops.) within one week after the damaged / burnt meter
is replaced after recovering the cost of the meter from the consumer. The officer Incharge of ME Laboratory after carrying out the test checks,
shall send his report to AE/AEE/XEN(Ops.) concerned within one month in case of
various categories of consumers excepting LS & BS exceeding 100 KW and MS
consumers . Report in respect of
meters with MDI, CTs and PTs for LS or BS etc. shall be prepared by MMTS. Non compliance of these provisions by any of the officers/
officials will be considered as negligence entailing disciplinary proceedings. After receipt of report from AE/AEE/ME Laboratory/MMTS, the case shall be
decided and the cost of estimated damage adjusted as under from the amount got
deposited from the consumer in the first instance.
67.3.1 For Domestic/NRS and AP consumers the extent of responsibility of the
consumer for the damage will be decided by the AE/AEE/XEN(Ops.).
67.3.2 For Industrial, Bulk Supply and Street Light consumers for loads up to
100 KW the extent shall be decided by the Sr.XEN/ASE(Ops.)
67.3.3 For Large, Bulk Supply and Street Lighting with loads exceeding 100 KW,
the meter shall be decided by the SE(Ops.)
67.3.4 Cost of replacement or repairs of the Board's meter on hire with the
consumers, which might get damaged due to floods or any act of God will not be
recovered.
67.4 Defective meters need to be replaced on priority in preference to meters
to be issued for installation against new connections.
67.5 As per provisions of Condition No.34, recovery, if any, is to be effected
after serving the consumer with a notice of show cause. If the amount of recover is more than Rs.5,000/- the consumer shall have
the right to appeal against any recovery.
67.6 At the time of issue of MCO, record entry shall be made in the ledger
duly attested by the ARA/RA. A check register shall be put up to the AE/AEE/XEN(Ops.)
by the consumer Clerk at the close of the month. All those MCOs / SCOs which are not received back within one month from
the date of issue may be brought to the notice of Sr.XEN/ASE concerned every
month so that proper check on issue and return of MCOs can be maintained besides
making cross entry in the ledger.
67.7 Direct Supply in case of LS Consumers:- Direct Supply in
case of Large Supply consumers can be allowed only in exigencies by CE/Operation for only 3 days and if circumstances still
persist, then direct supply can be given beyond 3 days & that too with the
written approval of respective CE/Operation.
68. RESPONSIBILITY OF INSTALLING CORRECT METER.
68.1 In accordance with the provisions of section 26(2) of the IE Act,1910, a
correct meter shall be installed, sealed and maintained by the Board at the
point of supply of the consumer. As the responsibility of installing a correct meter and
maintaining it correct is that of the Board, AE/AEE/XEN(Ops.) should take
particular care to see that every meter before it is installed has been tested
in the ME Lab. and ME seal on the meter cover is in tact, and that it continues
to operate correctly.
68.2 If the meter installed by the Board becomes inoperative or inaccurate at
any stage, no rental should be recovered from the consumer for the period the
meter remains inoperative or inaccurate.
69 ACCURACY OF THE METER:
69.1 According to the Rule 57 of the Indian Electricity Rules, 1956 a meter or
maximum demand indicator or other apparatus placed upon a consumer's premises in
accordance with section 26 of the Indian Electricity Act shall be of appropriate
capacity and shall be deemed to be correct if its limits of error are within the
limits specified in the relevant Indian Standard specification and where no such
specification exists, the limits of error do not exceed 3% above or below
absolute accuracy at all loads in excess of one tenth of full load and up to
full load.
69.2 It also provides that no meter shall register at no load while testing a
meter.
69.3 The meters/metering equipment to be installed at the consumer's premises
should be of appropriate capacity depending upon the connected load/contract
demand and the maximum demand of the consumer. Similarly C.Ts matching the load as well as meter should be installed.
70. CHECKING THE ACCURACY OF METERS:
70.1 Steps to be taken for routine checking of the energy meters:
70.1.1 In order to ascertain whether the meter is working or not, Meter Readers
should switch on one or two lights
for a few seconds before taking monthly meter reading and watch that the disc of
the meter revolves in the correct direction.
70.1.2 Meter Inspectors, JEs, AE/AEE/XEN(Ops.) and Sr.XEN/Addl.SE (Enforcement) should conduct the accuracy test at site with the help of a
stop watch for a short period by putting on a small load of known wattage and
counting the number of revolutions within a specified period to be determined
with the help of stop watch.
70.2 Whenever a meter is found to be in-operative byanyemployee9other than XEN
Enforcement) of the Board, the matter should be brought to the notice of AE/AEE/XEN(Ops.)
in writing so that immediate steps may be taken to replace it and for taking any
other action as deemed proper.
70.3 Whenever a meter is found to be inaccurate by Sr.XEN/Addl. SE(Enforcement),
the matter should be brought to the notice of AE/AEE/XEN(Ops.) and SR.XEN/Addl.
SE(MMTS) (particularly in respect of large supply consumers) in writing. On receipt of the report, the Sr.XEN/Addl. SE(MMTS) should check the
accuracy of that meter at site in the presence of AE/AEE/XEN(Ops.) and the
consumer after which immediate steps should be taken by AE/AEE/XEN(Ops.) to
replace the inaccurate meter and also to take other action as required pursuant
to the checking.
70.3.1 If the meter installed at the premises of a medium supply industrial
consumer is found/suspected to be defective or inoperative, it should be got
checked/tested from Sr.Xen/Enforcement with the help of ERS meter at site. Sr.XEN(Op.) shall also carry out checking in respect of tampering of
seals and genuineness of ME/MTC(Meter Terminal Cover) or CT chamber seals.
70.4 Testing of Meters
other than LS consumers by Enforcements/MMTS;
Such
meters shall be tested by the officers of enforcements/MMTS with the help of
Electronic Reference Standard Meters at normal running load/power factor of the
consumers subject to the condition that the running load shall not be less then
15%of the sanctioned load. Before testing the meters, CTs connections wherever
applicable shall be thoroughly checked. If
CTs connections are found wrong or CTs are found out of circuit and thus not
contributing, the recorded consumption shall be enhanced proportionately,
keeping in view non-contribution of CTs as applicable. This consumption shall be further subject to revision as per test results
of the meter as under:-
70.4.1 If the meter has error within or equal to ± 3% , the accounts of the
consumer need not be overhauled. If,
however, the error exceeds + 2% and is up to + 3% and if the consumer requests
for change of meter the request may be accepted. If the error falls between ?2% and ?3% , the meter of the consumer
should be changed without any request from the consumer.
70.4.2 If the error is beyond ± 3%, the meter shall be declared defective for
replacement and the accounts should be overhauled.
70.4.3 In case the %age error is up to ± 20%, the results should be applied
straight away on the recorded consumption for overhauling of accounts. If the %age error exceeds ± 20% and the meter shall be declared erratic. For overhauling the accounts of the consumer, the monthly consumption
recorded during the period of overhauling shall be subjected to ± 20% error
factor and compared with the consumption as worked out in case of dead stop
meters and higher of the two should be taken for the purpose of overhauling the
accounts provided there has been no change in connected load during the period. If there is change in connected load during the period of overhauling,
the chargeable consumption worked out shall be enhanced/reduced proportionately. The overhauling of account shall be carried out for a maximum period of 6
billing months preceding the billing month of detection of defect/error in the
meter. If the month/date of meter
getting defective/erratic can be established with certainty being within 6
preceding billing months, overhauling of consumption will be restricted up to
that month/date.
70.5 Testing of Meters of LS, MS and BS consumers:
Testing of meters by MMTS will be regulated as under:-
70.5.1 Testing of metering equipment shall be carried out in ' as found
condition' in the presence of consumer or his representative. Retesting will only be admissible in rare cases depending on the merits
of the case.
70.5.2 If the metering equipment on testing is found to be beyond the limits of
accuracy, it shall be kept in as found condition under signature of the consumer
by affixing paper seals till the consumer accounts are overhauled and amount
recovered.
70.6 Testing of Meters by MMTS and ME Divisions:
70.6.1 Meter testing both by MMTS and ME Labs for Large supply consumers( and
other consumer as and when required) shall be carried out at the same loading
steps so as to tally the results in the ME Labs. and spot testing. These
steps will at zero, 10, 25, 50, 75 and 100% loading of the meter capacity.
70.6.2 In case the meter tested by MMTS/ME Lab shows results within ± 3% at all
loads between 10% to 100%, the meter will neither be changed nor the accounts of
the consumer overhauled. However,
in case the results are beyond ± 3% at any loading level between 10% to 100%
the meter will be declared defective for replacement and account shall be
overhauled on the basis of error factor at the operating level defined below:-
70.6.2.1 The operating level for meters with MDIO will be taken as 80% of the
average maximum demand of the consumer as recorded during the last three correct
working months. The error factor of
MDI meter, if any, shall not be considered for taking the average maximum demand
for the purpose of working out of operating level.
70.6.2.2 For consumers other than large supply where MDI meter is not installed,
the operating level shall be taken as 50% of the sanctioned connected load. However, it is clarified that standard power factor of 0.88% lagging and
rated voltage of the meter shall be
taken into account for working out current loading of the meter corresponding to
the operating level connected load.
70.6.3 Before testing the meters by MMTS, the CTs/PTs connections must be
thoroughly checked. Where CTs/PTs
connections are found wrong or CTs/PTs are fond out of circuit and thus not
contributing, the recorded consumption should be enhanced proportionately
keeping in view non-contribution of the CTs/PTs as applicable, and this
consumption shall be further subject to revision as per test results of the
meters as per Para 70.6.4 and 70.6.5 below.
70.6.4 In case where %age error of the meter is up to ± 20%, the results
obtained shall be applied straight way on recorded consumption and accounts
overhauled accordingly, except the
power factor surcharge and demand surcharge.
70.6.5 If %age error of the meter is more than ±20%, the meter shall be
declared erratic. For overhauling the accounts, the monthly consumption recorded
during the period of overhauling, shall be subjected to ±20% error factor and
compared with the consumption as worked out for a dead stop meter( i.e. average
consumption of the last 3 to 6 months or average of the consumption of
corresponding months of the previous year whichever is higher) and higher of the
two taken for the purpose of overhauling, provided there has been no change in
connected load/contract demand, the chargeable consumption worked out above
shall be enhanced/reduced proportionately.
70.6.6 All reference standard meters and meter testing equipment used by PSEB
for testing of consumers meters at consumers premises, in ME Labs. or elsewhere
may be got tested from NPL Delhi or ERTL New Delhi or any other laboratory
recognized by Central Govt./NABL once in two years. The test certificates may be shown to the consumer if requested during
the checking of his meter.
70.7 Instruction for levying Power Factor Surcharge:
70.7.1 Where KWH/KVAH meters are correct i.e. after testing the test results are
within the permissible limits and the power factor is less than 88% due to
inadequate/higher capacity of shunt capacitors installed, very low load
factor/demand factor of the consumer, higher capacity meter /metering equipment
and CTs installed etc. the power factor surcharge shall be levied as per
provisions made in the Tariff Schedule in this regard and no relief shall be
given on this account.
70.7.2 Where on testing either KWH or KVAH or both are found exceeding the limit
of ±3%, the power factor in such cases shall not be computed on the basis of
such test results, notwithstanding the fact that these test results are less or
more than ± 20% and have been
adopted for working out KWH/KVAH consumption as per Para 70.6.4 and 70.6.5 above
for the purpose of calculating the energy charges. Power factor surcharge in such cases, shall be levied for the period of
overhauling on the basis of average power factor computed for correct working
period of three months preceding the period of overhauling.
70.8 The overhauling of accounts shall be carried out for a maximum period of
6 months preceding the date of detection of defective metering equipment. But where the month/date of the meter getting defective can be
established with certainty, being within six preceding months, overhauling of
consumption/power factor figures would be restricted up to that month.
70.9 Normally a defective meter should be changed within a week of testing.
Where it is not possible to do so due to non availability of meter etc.
recalibration of the meter already installed at the consumers premises, by
removing it, should be resorted to and meter reinstalled positively within 15
days. For the period defective
meter is not changed, the average power factor shall continue to be adopted and
KWH consumption worked out as per provisions of Para 70.6 and 70.7 above till
the meter is changed.
70.10 The authority for deciding the consumption/power factor
surcharge as per recommendations involving financial implications up to
Rs.10,000 shall be Director(Billing) whereas CE/EIC(Comml.) shall decide cases
above Rs.10,000/-.
70.11 Testing of MDI Meters:
The maximum demand indicator(MDI) installed at the premises of LS
consumers and others shall continue to be tested for accuracy at 75% and 100% of
the contract demand of the consumers. For
charging the consumer for defective MDI meters provisions of Reg. No. 78 shall
be followed.
71 PROCEDURE WHEN A METER IS CHALLENGED:
71.1 Meters installed at the premises of DS/NRS/BS/SP consumers at supply
voltage less than 11000 volts.
71.1.1 Whenever a complaint regarding the faulty behavior of an energy meter
belonging to the Board is received, the Meter Inspector or JE should be asked to
visit the premises and test the meter at site with the help of a stop watch. If on testing, the complaint of the consumer is found to be correct, the
meter should immediately be replaced. If,
however, any loss to Board is suspected, the dismantled meter should be
expeditiously got tested from ME Lab. and the accounts of the consumer be
overhauled on the basis of the results intimated by Xen/ME. Full
details of the extra amount assessed to the consumer should be intimated to him
as a separate bill. The consumer,
if he so likes, may make a representation or appeal against such an assessment.
71.1.2 In case the complaint of the consumer is not corroborated by the test
carried by the meter inspector or JE, the consumer should be informed
accordingly. If the consumer does
not feel satisfied, he may be advised to formally challenge the accuracy of the
meter and deposit the requisite meter challenge fee.
71.2
71.2.1 If any consumer doubts the accuracy of the meter/metering equipment
installed at his premises, it may be changed if so requested by him. However, the meter shall be procured by the consumer himself and it shall
be got tested/calibrated from the Board's laboratory after the payment of
necessary charges. This will not
entitle the consumer to any refund due to change in average consumption of the
consumer. The consumer will be
entitled for refund etc. only if he challenges his old meter and gets it tested
in the ME Lab after depositing the challenge/testing fee. The accounts of the consumer will be revised only according
to the test results of the ME Lab.
71.2.2 In case the consumer does not accept the readings of the check meter or
insists in the very beginning to send the challenged meter to ME Laboratory, he
should deposit the meter challenge fee. After
the challenge fee is received, the meter should be sent to the ME Lab. promptly
after removal but in no cast it should be delayed beyond a period of fifteen
days from the date of removal of the meter from the consumer's premises. While sending the challenged meters to the ME Lab this fact
must be clearly indicated on the MCO and AE/AEE ME be requested for intimation
of test results at the earliest. After
the meter is received in the laboratory, it should be promptly tested and test
results intimated to the AE/AEE/XEN(Ops.) concerned by ME Lab. within a maximum
period of seven days from the date of receipt of the meter in the laboratory. The AE/AEE/XEN(Ops.) will then immediately intimate the result to the
consumer and after getting his acceptance adjust the accounts accordingly. The whole process should , in no case, take more than a month.
71.2.3 The period, for which the refund is to be allowed, should be determined
on the merits of each case. Normally,
the period may not exceed three months. If,
however, the circumstantial evidence or the variation in consumption warrants
the adjustment for a longer period, the refund may be allowed up to a maximum
period of six months.
71.3 Meters relating to LS and MS Consumers:
71.3.1 When the metering equipment of a consumer other than LS getting supply at
11 KV is challenged, testing shall invariably be entrusted to Sr.XEN/Addl. SE/MMTS
who will test the meter as per procedure detailed in Regulation No.69 in the
presence of AE/AEE/XEN(Ops.) and the consumer or his representative. The testing of 11 KV consumers other than LS metering equipment shall not
be carried out by ME Lab. It shall
be carried out in as found condition by MMTS. However, after the defective meter at the consumer's premises is removed
and sent to ME Lab, the same shall be calibrated and tested there. This procedure for dealing with challenged meters/metering equipment
should invariably be followed in case of MS consumers with character of supply
11000 volts 50 cycles, as per Regulation 70.
71.3.2 When the metering equipment of a consume getting supply at LT is
challenged, it shall be replaced immediately and got tested with all previous
seals intact from ME Lab and the results shall be intimated by the AEE/ME to the
concerned sub division and the consumer and his( consumer) acceptance should be
obtained. In case the consumer does
not agree with the results, metering equipment should be kept by the AE/AEE/XEN(Ops.)
with all previous seals intact to be subsequently got tested, if so desired,
from the Chief Electrical Inspector to the Punjab Govt. The result of such test by Chief Electrical Inspector will be final and
binding on the consumer under provisions of Section 26(6) of Indian Electricity
Act,1910.
71.4 Meters installed at the consumers premises other than LS category shall
be tested by Enforcement/MMTS with the help of ERS meters at normal running
load/power factor of the consumer subject to the condition that the running load
shall not be less than 15% of the sanctioned load. Before testing meter, the CT connections wherever applicable shall be
checked thoroughly. Where CT
connections are found wrong or CTs are found out of circuit, the recorded
consumption shall be suitably enhanced keeping in view non contribution of CTs
as applicable. In case the meter
has error within or equal±3% , the accounts of the consumer may not be
overhauled. However, if the error
exceeds +2% and is up to +3% and consumer request for change of the meter, the
request shall be accepted. If the
error lies between ?2% & -3%, the meter of the consumer should be changed
without any request from the consumer.
71.4.1 In case the error is upto± 20%, the results obtained shall be applied
straight way on the recorded consumption and the accounts overhauled
accordingly.
71.4.2 In case the error is in excess of ± 20%, the meter shall be declared
erratic. The accounts of the
consumer shall be overhauled by taking ± 20% error factor and compared with the
consumption as worked out in the case of a dead stop meters. Higher of the two shall applied for overhauling the accounts provided
there is no change in connected load. If,
however, there is change in connected load during the period, the chargeable
consumption shall be proportionately enhanced/reduced as the case may be.
71.4.3 The overhauling of accounts shall be carried out for a
maximum period of 6 billing months preceding the billing month of detection of
defect/error in the meter.
71.4.4
Officers of Distribution Organization are also authorized to
check the accuracy of MS category of connections with electronic ERS meters.
Such meters will be packed and sealed under the signatures of checking
Distribution Officer & consumer. However, these meters shall continue to be
opened in ME Lab. in the presence of Enforcement Organization and consumers
representative(s) for external/internal inspection so as to ensure that cases
are not involved in theft of energy are detected timely.
71.5 In respect of LS consumers, testing of meters shall invariably be
entrusted to Sr.XEN/ADDL.SE(MMTS) who will test the meter as per procedure
detailed in Reg.No.70 in the presence of AE/AEE/XEN(Ops.) and the consumer or
his representative. However, Sr.XEN/
ADDL.SE (MMTS) may also carry out testing of metering equipments of other
categories of consumers which are specifically entrusted to him by the competent
authority. Testing of LS consumer's metering equipment shall not be carried out
by ME Labs. It should be carried
out in position by the MMTS. However,
after defective meter at the consumer premises is removed and sent to ME Lab.,
the same shall be calibrated and tested there.
72. ADJUSTMENT OF ACCOUNT FOF CHALLENGED METERS:
Following procedure shall be followed in overhauling the accounts of
different consumers who challenge the meters and their meters are got tested
from MMTS/ME Labs:-
72.1 For Industrial/bulk Supply and NRS consumers
72.1.1 All energy and KVAH meters(excluding MDI's) will continue to be tested
and recalibrated in accordance with the IE Rules and ISS. In case of disputed/doubtful meters, testing shall be done at steps of
loads of 10%, 25%, 50%, 75% and 100% of the meter capacity.
72.1.2 If the error at any loading exceeds 3%, meter will be declared defective.
72.1.3 For overhauling the accounts in case of defective meters pertaining to LS
consumers, the slowness/fastness factor will be computed on prorata basis of the
test result corresponding to 80% of the average maximum demand of the consumer
as recorded during the last 3 correct working months preceding the month of
testing. Slowness/Fastness factor
in case of SP, MS, NRS and Bulk Supply Consumers will be computed on prorata
basis of the test results corresponding to 80% of the sanctioned connected load
of the consumer as annotated here under:-
Example:-
Load of consumer 900 KW
Contract Demand 700 KVA
CT Ratio 100/5
Meter Ratio 200/5
Energy meter is tested with following results:-
Supposing the errors determined at different load are:-
At10% full load : %age error (-) 10
25% : " (-) 7
50% : " (-) 5
75% : " (-) 1.0
100% : " (-) Nil
Since the error at any load between 10% and 100% is more than 3%, the
meter is defective and slow.
Let Average of maximum demand recorded during last six months from the
date of testing be equal to 625 KVA. Then
slowness factor is to be calculated corresponding to 80% of 625 KVA i.e. 500 KVA.
Corresponding Current at 500 KVA :500 /100x 5.25= 26.25 Amps.(11 KV)
%age load on which slowness factor :26.25x100 = 26.25 = 26.25%
to be computed 100
Error at 25% : -7%
Error at 50% : -5%
Error at 26.25% : -7 + (-5+7)x1.26
25
: -7 + 0.11 = - 6.89%
Slowness Factor : -6.89%
If recorded monthly consumption as shown by the meter is (say) 40000
Units, the chargeable consumption will be 100/93.11x40000x1 = 42960 KWH.
AEE/MMTS after testing of meter will supply the test results alongwith
the slowness/fastness factor to the consumer and AE/AEE/XEN(Ops.) concerned on
the date of testing. The consumer
should convey his reaction to the test results within a week of receipt of
notice to AE/AEE/XEN(Ops.) otherwise it will be assumed that the consumer has
accepted the test results and slowness/fastness factor and the meter will be
replaced within the correct metering equipment besides over-hauling consumer's
accounts retrospectively up to a maximum period of six months.
72.3 Necessary recovery should be made from the consumer for 2960 units (42960
? 40000) for that month by finding out the difference between the bills for
40000 units and 42960 units. Similar
calculations should be made for each month of the period for which the recovery
is to be made on account of slowness factor.
72.4 The maximum demand indicator(MDI) installed at the premises of LS
consumers should be tested for accuracy at 75% and 100% of the contract demand
of the consumer at whose premises the said MDI has been installed. The consumer accounts be over-hauled on the basis of the percentage error
so determined. In the event of MDI
being defective and the maximum demand being more than the contracted demand, no
demand surcharge for the increased demand so computed for previous period shall
be levied provided the consumer's connected load is well within the sanctioned
connected load. The consumer's
connected load will also be verified when the MDI meter is fund
inoperative/defective regarding the time period during which the load checking
of the consumer is to be considered for implementing the MMTS results, the same
shall be :-
72.4.1 The load checking of the consumer shall be done by the AE/AEE/XEN(Ops.)
immediately but not later than one week of testing of the meter by the MMTS/Enforcement
staff.
72.4.2 While sending the report of MMTS/Enforcement checking to the Dy.Director/CBC,
AE/AEE/XEN(Ops.) shall also send a copy of the report of the last checking
carried out by him, if any, within 6 months before the checking of the MMTS/Enforcement.
72.4.3 In case Dy.Director/CBC has any doubt about the aforesaid details, he may
seek advice of Sr.XEN/ASE(Ops.) concerned for proper billing of the consumer.
72.5 For DS Consumers:
Account of a DS consumer who has challenged a meter and whose meter is
got tested from ME Laboratory should be adjusted as under:-
72.5.1 On receipt of test results from AE/AEE/XEN/ME, it should be verified
whether the meter is correct or not in terms of Rule 57 of the Indian
Electricity Rules,1956, In case the inaccuracy of the meter exceeds +3% at any
load even though the average inaccuracy may be less than +3%, necessary
adjustment should be carried out in consumer's accounts after striking out the
average of percentage errors at different loads. Following example will illustrate the procedure to be adopted.
Supposing the errors determined by testing are:
At 10% Full Load : - 2.5%
25% " : - 0.5%
50% " : +1.5%
75% : 3%
100% " : 3.5%
(+ means fast, - means slow)
Average error : -2.5-0.5+1.5+3+3.5/5
= +1%
If recorded monthly consumption as shown by the meter is (say) 400 units,
the chargeable consumption will be 100
x400 = 396.04 Units.
101
72.5.2 Necessary refund should be given to the consumer for 3.96(400 ? 396.04)
Units, for that month by finding out the difference between the bills for 400
units and 396.04 Units. Similar
calculations should be made for each month of the period for which the
adjustment is required to be made.
73 ADJUSTMENT OF ACCOUNT IF METER FOUND DEFECTIVE:
Following procedure shall be adopted whenever an energy meter on the
premises of a consumer is found to be defective.
73.1 Dead Stop or Burnt Meter.
73.1.1 On receipt of a report regarding a meter becoming defective, dead stop or
burnt, it should be immediately replaced and necessary inquiries conducted. The meter alongwith the report should be forwarded to Xen/ME for further
action.
73.1.2 So far as charging the consumer for the period the meter remained
inoperative is concerned, average consumption of last 4 or 6 months or the
average of the same months of the previous year or the actual recorded
consumption, if any, whichever is higher shall be compared with the consumption
as under and higher of the two figures shall be charged to set the consumer's
account right finally.
|
|
CONSUMPTION
PER CYCLE
|
|
|
|
DS
consumers
|
NRS
consumers
|
|
1.
|
Up
to 2 KW Load
|
100
Units/KW
|
100 Units/KW
|
|
2.
|
Exceeding
2 KW and up to 5 KW
|
200+60
units/KW of load in excess of 2 KW
|
200+60
Units/KW of load in excess of 2 KW.
|
|
3.
|
Load
exceeding 5 KW
|
380+40
Units/KW of load in excess of 5 KW
|
760+80
Units/KW of load in excess of 5 KW
|
73.1.3 In case extension of load was granted to the consumer, probable
consumption should be increased on prorata basis for the period extension of
load was utilized by the consumer.
73.1.4 Where consumption of previous three/six months in case of industry is not
available, adhoc consumption on the basis of load factor and demand factor of
the industry, as circulated by the CE(Comml.) from time to time, shall be worked
out and shall be provisionally billed and after installation of correct meter,
the consumer's account for the previous period shall be overhauled on the basis
of average consumption/power factor/maximum demand actually recorded during the
next three working months.
73.2 In order to ensure that seals affixed to the metering equipment of LS
consumer have not been tampered, the genuineness of the seals shall be got
checked up by the Operations Officers from Sr.XEN /Addl.SE (Enforcement) before
such meters are sent to ME Labs for further action.
73.3 Inaccurate Meters( Other then LS consumers)
73.3.1 If accuracy of a single phase meter is doubtful or the meter is found creeping forward, no adjustment in
accounts may be carried out but the meter should be replaced.
73.3.2 If the inaccuracy of a single phase meter is pronounced or in case of
three phase meters, which may be suspected/found to be incorrect, the consumer
should immediately be informed in writing that the meter already installed at
his premises is incorrect or has been tampered with by the consumer, as the case
may be, and after determining the %age inaccuracy his accounts will be adjusted
as per the test results in terms of Condition No.22.6 of the Conditions of Supply. As
far as possible the existing metering equipment should not be disturbed or
tampered with so that it remains in the ' as found conditions'.
73.3.3 The consumer's meter with load up to 20 KW on challenge be changed and
test results of the meter so removed be obtained from ME Lab for overhauling of
accounts.
73.4 For LS/MS Consumers:
73.4.1 In respect of LS consumers if the working of meter/metering equipment is
found to be inaccurate, the matter may be referred to concerned XEN(MMTS/
Enforcement) for getting the same tested. The
testing shall be done by XEN/MMTS at consumer's premises in 'as found
condition'. Procedure prescribed in
Reg.No.70.5 shall be followed.
73.4.2 In case a meter is found to be inaccurate by Sr.XEN/Addl.SE
(Enforcement), the intimation of the same shall be given to Sr.XEN/Addl. SE(MMTS)
for checking the same at site in 'as found condition' in the presence of the
consumer or his representative. In
order that the metering equipment found inaccurate is not disturbed or tampered
with, paper seals be affixed by Sr.XEN/ Addl.SE (Enforcement) under intimation
to AE/AEE/XEN(Ops.) and Sr.XEN/
Addl SE(MMTS) . After testing by
MMTS if the meter is found inaccurate, the same shall be paper sealed jointly by
AEE/Sr.XEN(Ops.) and the consumer and kept in ' as found condition' till the accounts are overhauled.
\
73.4.2.1 Overhauling of accounts and sending supplementary bill to the
consumer.
On the basis of the checking carried out under regulation No.70.5 the
Centralised Billing Cell shall overhaul the consumer's account expeditiously on
receipt of RSS/test results from the MMTS which shall also deliver a copy of the
test results to the consumer or his representative after the testing is over.
73.4.2.2 On receiving the supplementary bill from the Dy. Director(Central
Billing), the AE/AEE/XEN(Ops.) will send the supplementary bill-cum-notice to
the consumer separately. In case
Sr.XEN/Addl.SE(MMTS) had not supplied a copy of the test results to the consumer
after carrying out the test, a copy thereof may also be attached to the
supplementary bill and in case he has any objection he may challenge the bill as
per the procedure laid down within a period of one week failing which it will be
presumed that he has no objection to making the payment on the basis of the test
carried out by MMTS.
73.4.2.3 If the consumer accepts the test results of MMTS, and makes the payment,
the defective metering equipment should be removed immediately and action to
install a correct metering equipment taken on urgent basis.
73.4.2.4 If the consumer contests the test carried out by the MMTS, the consumer
has the option to get the meter tested from the Chief Electrical Inspector or
else his representation may be reviewed by the competent authority i.e. Circle
Level Dispute settlement and Reconciliation Committee depending upon the amount
of the supplementary bill. In such
a case the consumer should make 33% payment of bill where the bill amount is up
to Rs.1 lac or in excess of Rs.1 lac inclusive of enhanced security for which
powers have been delegated to SE(Ops.) and CE(Ops.) respectively. The consumer will have the opportunity of hearing by the review
committee. The consumer will also
have the right of appeal as is admissible in the case of supplementary bills
raised in the case of theft of electricity. However, the disputed meter be kept intact
73.4.2.5 In case the consumer does not opt for any of the above courses and
challenges the test results or the supplementary bill in the court or obtains
stay order, all out efforts should be made to get the stay vacated or if the
same has not been granted the court may be requested not to entertain the matter
and direct the consumer to get his grievances redressed by taking recourse to
the opportunities available to him in the board or from the Chief Electrical
Inspector under section 26(6) of the Act. In
such a situation the meter should not be replaced and be allowed to remain in
position. A new meter may also be
installed so that the same registers the correct consumption. Future billing should be carried out on the basis of the new meter. In case the consumer is neither prepared to refer the matter to
Electrical Inspector nor comes forward to pay the amount billed to him, he
should be served with a show cause notice as per the procedure prescribed under
Regulation No.124,133.3 to 133.9.
73.4.2.6 All out efforts should be made to get the matter settled either under
section 26(6) or through the dispute settlement and reconciliation committee.
73.4.2.7 If the meter is found to be working accurately but is found otherwise
running slow due to wrong/unstandard connections, %age error be determined
through testing by RSS meters. Overhauling
of accounts shall be done for the period the mistake/defect continued.
73.5 If LS meter/metering equipment goes defective within 15 days
of its installation, the same maybe replaced by the concerned operation officers
themselves after ensuring the genuineness of seals without referring to Sr.XEN/Addl.SE (Enforcement). The defective
meter, thus replaced shall be sent to ME Lab by AE/AEE/XEN(Ops.) officers
promptly.
73.6 Replacement of meter of MS consumer:
If metering equipment installed at the premises of MS consumer is found
to be defective or inoperative, it should be replaced after getting it
checked/tested from the Sr.XEN/Addl.SE MMTS/Enforcement in respect of tampering
of seals and genuineness of ME/MTC or CT chamber seals. Such meters shall be sent to ME Lab. The testing should be carried out within15 days from the request by AE/AEE/XEN(Ops.).
73.7 A consumer, who has been debited additional charges, has also the option
to refer the matter to the Electrical Inspector whose decision will be binding
on the parties. In such an
eventuality the disputed inaccurate meter should not be removed. As a matter of fact old meter should remain in position until the
Electrical Inspector has made the requisite investigation. The consumer should be billed on the basis of the check meter findings of
Sr.XEN/Addl. SE(MMTS) in the intervening period.
73.8 The cases involving incorrect connection, defective CTs/PTs, genuine
calculation mistake etc. are not governed under the above mentioned instructions
but under the provision of Condition No.23 of the Condition of Supply which read
as under:
"Where the accuracy of meter is not involved and it is a case of
incorrect connection or defective CTs and PTs, genuine calculations mistakes
etc. charges will be adjusted in favour of Board/consumer, as the case may be,
for the period the mistake/defect continued."
74. DIFFERENCE OR DISPUTE OVER THE ACCURACY:
Where any difference or dispute arises as to whether any meter is or is
not correct, the matter can be decided, upon the application by either party to
Electrical Inspector under Section 26(6) of the Indian Electricity Act,1910, as
amended from time to time, and if in his opinion, the meter is not correct, the
Electrical Inspector shall estimate the amount of adjustment to be carried out
in the consumer's account for a period not exceeding six months preceding the
date of test. Provided that before the Board or a consumer applies to Chief
Electrical Inspector, he shall give to the other party not less than 7 days
notice of his intention to do so.
75 CHANGING THE POSITION OF A METER:
75.1 On receiving a request from the consumer for the change of site of the
meter, J.E. should visit the site and assess the expenditure involved in such a
change, If no material is involved
in the job, a fee as laid down in Schedule of General Charges as amended from
time to time maybe recovered, but if the job involves new material, the
estimated cost together with 27½ %
departmental charges, as amended from time to time, should be got deposited
before undertaking the job.
75.2 If the change in the position of the meter is necessitated due to an act
of God e.g. floods, no charges for changing/shifting may be recovered.
75.3 No meter change fee will be recoverable if a consumer wants to get his
own meter re-installed after it has been got tested from the Board's laboratory
as a result of periodical checking or on being found defective.
76. INSTALLATION AND MAINTENANCE OF METER SUPPLIED BY THE CONSUMER.
76.1 Under Section 26 of the Indian Electricity Act,1910, the consumer has the
option to instal his own meter. Whenever
consumer desires to exercise this option, the following facts should be brought
to his notice:-
76.1.1 As enjoined under Section 26(3) of the Indian Electricity Act, the
expense and onus of keeping the meter correct falls upon the consumer, and in
default of his doing so, the Board may, after giving him 7days notice for so
long as the default continues, cease to supply energy through the meter.
76.1.2 If at any time the accuracy of the consumer's meter is challenged by the
Board, the meter will need to be tested by the Electrical Inspector to Govt.
Punjab or by the ME Laboratory of the Board on payment by the consumer of the
prescribed charged.
76.1.3 If the meter proves to be correct, the consumer will be entitled to get
back the above charges. Before, however, a meter from the consumer is accepted
for installation, it should be ensured that it has been duly tested and sealed
either by the Chief Electrical Inspector or by the Board's ME Lab and that the
test result is satisfactory.
76.1.4 If a consumer wants his solid state TPT meter to be installed at the
premises, it should be got tested/sealed from the high tech. lab(s) established
by the Board.
76.1.4.1 Sr.Xen/Addl. SE(MMTS) should be associated with the testing of such a
meter in the ME Lab. The meter
should also be tested at site by the Sr.XEN/Addl. SE(MMTS) within 15 days of its
installation.
76.1.4.2 XEN/AEE/AE(Ops.) while accepting such meters shall obtain copy of Test
Report of the manufacturer and place it in the consumer file for reference and
record.
77. PURCHASE OF METER BY THE CONSUMER:
77.1 In the event of the consumer desiring to install his own meter, the
meter, if there is no shortage , may be supplied by the Board. The selling prices of the meter will be:-
77.1.1 Stock issue rate plus storage charges or the market rate whichever is
higher plus.
77.1.2 Supervision Charges.
77.1.3 In addition to this, the consumer will have to pay the installation and
the departmental charges.
77.1.4 In case of permanent disconnection or the meter becoming defective such
meter should be sent to ME and in case the consumer does not come forward to
take back the meter, the same may be kept in ME Lab duly accounted for.
78. TAKING READING OF M.D.Is
78.1 There have been frequent cases in which M.D.Is installed at the
consumer's premises have been found defective on the reading date of the month. This may leave the Board without indication as to what the maximum demand
of the consumer might have been during the month. Following guidelines are laid down for working out the maximum demand if
the MDI installed at the consumer's premises becomes defective /inoperative/dead
stop.
78.1.1 Maximum demand recorded during the preceding three months immediately
before the MDI became defective.
78.1.2 MDI recorded during the corresponding months of the preceding year,
provided the same functioned properly in the said months of preceding year and
three had been no extension in load thereafter.
78.1.3 75% of the contract demand; and
78.1.4 In the case of consumers being fed through independent feeder, the load
may also be computed from the half hourly volts and amps readings as recorded on
the log sheet.
78.2 The competent authority to decide the MDI readings to be charged in such
a case will be Director/Billing.
78.3 The consumers shall not be allowed to increase their connected load or
contract demand during the period the MDI remained defective or inoperative. However, if it is not possible to get the MDI repaired or replaced in a
reasonable period say three months, and the increase in contract demand and
connected load has to be allowed, the
MDI figures worked out in accordance with Para 78.1 shall be correspondingly
increased.
78.4 If any un-authorized extension is detected during the period the MDI
remains defective, the MDI readings computed as per guidelines above shall be
proportionately enhanced.
78.5 The procedure as provided in preceding Para shall also be applicable, if
MDI becomes defective immediately after release of extension in load.
79. INSTALLATION OF METER CUP BOARD-CHARGING OF RENTALS:
79.1 Meter/Metering equipment shall be installed in an MCB(meter cup board)
whose design has been approved by the Board. MCB can be provided by the Board, if so requested by the consumer. However, the consumer may provide his own MCB of the design and
specifications laid down by the Board. Standard
MCBs will be displayed in the offices of the Board for the convenience of the
consumers.
79.1.1 Existing connections where the meter cup board has not been provided or
if provided are not of the design
approved by the Board, a 30 days registered notice may be issued by the field
officers to all such consumers for providing the meter cup board of approved
design, otherwise, the Board shall provide the same at consumer's cost and will
debit rentals as per prescribed rates through energy bills.
79.2 Rental of MCB:
In case the MCB is provided by the Board, the consumer shall pay the
monthly MCB rentals as prescribed by the Board from time to time. Rates in force at present are as under:-
1. For Single Phase LT Meter MCB -Rs.6/-
2. For Three Phase LT meter MCB -Rs.8/-
3. For LT/HT metering equipment -@ 1.6 paise per rupee of the cost of MCB.
4. For LT 3 phase CT operated TPT -Rs.22/-
Meter of any make.
5. For Metering equipment LT CTs of -Rs.22/-
item 4 above. |