51. SERVICE CONNECTION CHARGES FOR RELEASE OF CONNECTION:
Service connection charges as provided in 'Schedule of General and Service Connection Charges' are to be recovered from all the prospective consumers and the existing consumers seeking extension in load. Schedule of Service Connection Charges as prevalent is given hereunder:- 51.1 Service Connection Charges for Domestic/NRS Supply: 51.1.1

Fixed per KW Charges

Domestic

NRS

1.

Up to 1 KW

Rs.250/-

Rs.250/-

2.

Above 1 KW and Up to 3 KW

Rs.300/-

Rs.500/-

3.

Above 3 KW and up to 7 KW

Rs.500/-

Rs.750/-

4.

Above 7 KW

Rs.750/-

Rs.1000/-

 

51.1.2 Variable Charges: No Variable charges are leviable up to 150 metres. Beyond 150 metres for all loads variable charges @ Rs.125/- per metre length of service line shall be recoverable.

51.1.3 Yellow Card Holders: They can pay the service connection charges in instalments of Rs.10/- per month.

51.1.4 Domestic and Non-residential consumers falling under the following categories have the option either to pay in lump sum the service connection charges as mentioned under the preceding clause or to pay monthly service rentals @ 1.6 paise per rupee of the estimated cost of service line excluding the cost of 30.48 metres.

51.1.4.1 Application form 'Bet' Areas

51.1.4.2 Members of Scheduled Castes.

51.1.4.3 Applicants falling in sub-mountaneous area.

51.1.4.4 Applicants falling in 'A' category of border area.

51.1.4.5 The connections meant for religious and charitable institutions run by recognized/registered associations or societies registered with Registrar of Societies.

51.1.5 All such prospective and existing consumers who will pay or have paid service connection charges in full shall be exempted from the payment of monthly service rentals.

51.1.6 For connections given before15.9.1964, the service rentals are recoverable at the following rates:-

51.1.6.1 Single Phase Supply:

1.

When length is 30 metres or less

:

Nil

2.

When length exceeds 30metres but not exceeds 76 metres

:

50 Paise per month

3.

When length exceeds 76 metres but not exceeds 152 metres

:

Rs.1.50 per month.

4.

When length exceeds 152 metres

:

Additional monthly rentals @ 6 paise for every 3 metres in excess of 152 metres.

51.1.6.2 Three Phase Supply(Load up to 30 KW):

Service line capacity(KW)

Monthly Service rentals as foot run in excess of 100 Ft. (Rs.)(30.48)

Monthly service equipment charges per service (Paise)

1.

Up to 5 KW

1.30

50

2.

Above 5 KW and up to 10 KW

1.60

60

3.

Above 10 KW and up to 15 KW

1.60

70

4.

Above 15 KW and up to 20 KW

2.20

80

5.

Above 20 KW and up to 30 KW

2.60

100

 

51.1.6.3 Three Phase Supply above 30KW: Service and equipment rentals :@ 1.6 paise per rupee of estimated cost of service line (excluding the cost of 30.48 metres) and equipment per month.

51.1.7. For connections given after 15.9.1964 and the applications registered up to 31.7.1970: 51.1.7.1 Single Phase Supply:- The Service rentals shall be recoverable at the flat rate of 1.6 paise per rupee of the estimated cost of service line(excluding 30.48 metres) and equipment per month.

51.1.7.2 Three Phase Supply (Load up to 30 KW) : 1. Service Rentals : @ 1.6 paise per rupees of estimated cost of service line(excluding the cost of 30.48 metres) and equipment per month. 2. Service equipment charges As per rates provided under

51.1.6.2 per month.

51.1.7.3 Three Phase Supply (Load above 30 KW): Rates as provided in

51.1.6.3 shall be applicable.

51.2 Service Connection Charges for Industrial and Bulk Supply:

51.2.1 For New Connections: Load Service Connection Charges

51.2.1.1 Up to 1000 KW Rs.750/- per KW

51.2.1.2 Above 1 MW Rs.750/- per KW or actual cost whichever is higher. Service Connection charges under Para

51.2.1 shall be applicable for loads up to 1 MW where the length of new or augmented or both line(s) to be provided is up to 300 metres which will include 11 KV line( whether overhead or cable) LT line and service cable. Where this limit exceeds 300 metres, the applicant shall be required to pay actual cost of Rs.125/- per metre for 11 KV line, LT Line and Service Cable in excess of 300 metres as additional Service connection charges(non-refundable). However, no component of distribution, sub-station/transformer to be created would be charged wherever applicable.

Note:- In case of SP consumers only the cost of new HT Line(T-off), LT Line(New/Augmented) and service cable @ Rs.125/- per metre for portion beyond 300 metres shall be recovered in addition to normal service connection charges. Augmentation/bifurcation of existing 11 KV line shall be carried out at the cost of Board/Licensee under system improvement schemes.

51.2.2 Extension in load:

51.2.2.1 Where the consumer is either paying service rentals or had paid the service connection charges on KW basis for the original load:

1

Extension in load bringing the total load up to and including 1 MW

To be charged @ Rs.750/- per KW for extension part only.

However, the charges for service line in excess of 300 metres shall be charged @ Rs.125/- per metre for the length of service line( new or augmented or both) feeding such consumers.

 

2

Extension in load bringing the total load above 1 MW

Rs.750/- per KW (Chargeable for extension part only) or actual cost whichever is higher.

 

3

Rentals on original load, if applicable already, shall continue.

 

51.2.2.2 Where the consumer had paid service connection charges in full:

51.2.2.2.1 No Charges for extension shall be recoverable where the cost of service/common part of service line had been paid by the applicant at the time of release of original connection provided:-