|
C.C. No. 67/2006
Memo
No. 87252/88052/SSM-460
Dated. 21/12/06
Sub: T&D Loss Reduction and Improvement in Consumer service Instructions
thereof.
With a view to take concrete steps to
achieve the desired target for reduction in T&D losses, instructions were
issued vide CC No.37/06 dated 18.7.06. However,
in view of the difficulties being experienced by the field officers in
implementing these instructions in letter and spirit, no. of clarifications
are being sought by them. Keeping
in view these practical difficulties in implementing HVDS Scheme as such &
based on the feedback from the field officers, the matter has been reviewed
and it has been decided as under:-
(i) In case of shifting of AP
tubewell connection, shifting may be allowed on LT if it is technically
feasible to release the connection at the new site on LT i.e. if the feeding
transformer at the new site can take up the load. However, if for allowing tubewell connection at the new site,
augmentation of transformer is involved then the connection at the new site
shall be released only under HVDS as per the instructions issued vide CC No.
37/06 and the cost of transformer in addition to other applicable charges
shall also be borne by the consumer. However,
in case where notice had already been issued to the consumer on or before 30.9.2006 for deposit of charges for
shifting of tubewell connection, then shifting shall be carried out as per
notice served to the consumer.
(ii) For DS/NRS loads above 10 KW and upto 20 KW and SP connections:-
(a) Connection shall be released on
LT provided the length of LT line including the existing LT line from H-pole
near the transformer does not exceed
250 metres
in any case and no augmentation of the existing distribution transformer is
required. However, if the existing
transformer is of less than 200 KVA capacity then it can be augmented upto 200
KVA for release of connection on LT.
(b) In case where augmentation of
transformer beyond 200 KVA is required, the connection shall be released only
by providing new transformer of suitable capacity & LT line of the
de-loaded transformer further to new transformer shall be shifted to the new
transformer.
(c) In case where the new connection
is required to be released on HVDS but it is not possible to release the
connection on HVDS due to locational/practical constraint, such connection
shall be allowed to be released on LT with the approval of Addl.SE/Sr.Xen who
will record reasons for allowing such relaxation.
(iii) For DS/NRS consumers with loads above 20 KW:-
(d) In case where the existing
transformer can take the load to be released with maximum length of LT from
the transformer limited to
250 metres
, the same be released from the existing transformer.
(e) If augmentation of existing
transformer is required to release the load on LT, it should be released by
providing additional transformer of required capacity at the load center and
LT around the proposed transformer will be shifted to this new transformer
ensuring maximum improvement in the LD system.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No.66/2006
Memo No.84797/85597/SSM-414/TW/L-124
Dated.
19/12/06
Subject:- Release of new tubewell connections under Chairman Priority quota –
clarification thereof.
Field officers have
sought clarification as to whether the connections under Chairman's Priority
quota are to be released by providing the distribution transformer at Board's
cost or the prospective consumers may be asked to provide their own
transformer.
In
this context ,it is clarified that as per instructions already issued vide CC
No. 47/05 dated 20.7.05 followed by CC No. 68/05 dated 1.12.05 and CC No.
13/06 dated 17.3.06 ,all new AP tubewell connections under Chairman's
discretionary quota were to be
released on LT through Board's own transformer . As per CC 37/06 dated
18.7.06,all new AP tubewell connections are to be released under HVDS only w.e.f 1.10.06 onwards by providing individual small
distribution transformer for each connection on single pole structure at
Board's cost subject to recovery of service connection charges as per existing
instructions.
In
view of the position explained above, it is clarified that new AP tubewell
connections under Chairman's discretionary quota are also to be released by
providing individual small distribution transformer for each connection on
single pole structure at Board's cost .
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.65/2006
Memo
No. 81953/82753/SSM-416
Dated.
11/12/06
Subject:- Providing Urban Pattern Supply to Dalit Basties ,Be-Chirag Villages & Deras/Dhanies having cluster of 5 or more houses.
The precondition of
minimum 20 houses for providing Urban Pattern Supply to the village Dhanies /Deras at the cost of Board by laying single phase 11
KV system was relaxed to 15 houses vide CC No.20/2004 dated 19.4.2004.
On the persistent demand of
farmers/residents presently residing in Deras/Dhanies, Dalit Basties, Be-chirag
villages etc. forming a cluster of 5 or more houses and located at a distance
of more than 500 mtrs. from the
village phirni, for urban pattern supply The matter has been considered & it has been decided as under :-
(i) Urban Pattern Supply, shall be provided at the Board's cost to
the farmers/residents presently residing in Deras/Dhanies ,Dalit Basties, Be-Chirag Villages forming a cluster of 5 or more houses situated
adjoining to each other and spread over in a stretch of maximum of
300 meters
from one end to the other end and located at a distance more than
500 meters
from the village Phirni without any limit by providing:-
(a) Single phase 11 KV line tapped from the nearest UPS feeder & by installing single phase 11 KV ,10 KVA distribution
transformer.
(b) At the 1st stage the erection of 11 KV single phase
lines and installation of single phase transformers will be completed by RE/APDRP
Organisation and the remaining LT work i.e installation of energy meter and
laying of services will be carried out by respective DS Sub-Divn. of the
concerned area.
The existing
instructions as contained in CC 22/02 dated 31.5.2002, CC 58/03 dated 26.8.03 & 20/04 dated 19.4.04 shall stand amended to the above extent.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.64/2006
Memo
No.79414/80214/SSM-451-A/Vol.II
Dated.
29/11/06
Sub: One
Time Settlement offer for all categories of permanently disconnected
defaulting consumers.
As per instructions issued vide CC: No. 16/06 dated 17.04.2006, the One
Time Settlement (OTS) package introduced vide CC: No. 42/2002 dated 12.08.2002
was available upto 30.9.2006, for reconnection of various categories of
consumers, whose connections were disconnected temporarily/permanently upto
31.3.2005.
In view of the encouraging
response of the consumers, the matter has been considered and it has been
decided to extend the One Time Settlement package upto 31.03.2007 for
revival of sick Industry and other categories of consumers. With this
extension, the consumers whose connections stand disconnected temporarily
/permanently upto 30.09.2005 can opt for reconnection upto the validity of the
scheme i.e. 31.03.2007.Field Officers are requested to give vide publicity to
the above instructions.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.63/2006
Memo
No. 78267/79067/DSA/Vol.I/Comml.
Dated.
27/11/06
Sub: Constitution of State/Zonal Level Dispute Settlement Committees of
PSEB.
In partial modification to the
instructions circulated vide CC No.4/2005 dt. 14.1.205 and in continuation to
CC No. 29/05 dt. 5.5.05 the nomination from industry on the panel of Circle
Dispute Settlement Committee of Operation Circle, Mohali appearing at A(iv)(1),
Page 2 of the Annexure has been
amended to read as under :-
Page
2, A
(iv)(1), Sh. Balbir Singh, President, Mohali
Industries Association, MIA Bhawan,
Bay No. 143-144, Opposite ESI Hospital, Industrial Area, Phase VII, SAS Nagar,
Mohali-160055.
All other provisions of the CC
No.4/2005 dated 14.01.2005 & CC No.29/05 dated 5.5.05 shall remain
unchanged.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 62/2006
Memo No. 77375/78125/CC/T/11/L
Dated : 22.11.06
Sub:- Review of General Conditions of Tariff of Seasonal Industries and consequential review of Tariff order for the year 2006-07.
PSEB
vide CC No. 20/2006 DT. 12.5.2006 and CC 36/2006 dt. 14.7.2006 has revised the
tariff for Seasonal Industries w.e.f. 1.4.2006 and the General Conditions of
Tariff & Schedule of Tariff on
the directions of
Punjab
State
Electricity Regulatory Commission. As per above instructions reduced MMC was
leviable for the off season period for the months of March to August. Punjab
Rice Millers Association (Regd.) and
Punjab
Cotton Factories and Ginners Association (Regd.) petitioned PSERC against levy
of MMC during off season period.
PSERC
after considering the petition and hearing the view point of PSEB & Rice
Miller Association has decided vide order No. PSERC /Reg. 153/6752 dt.
31.10.06 that the General Conditions of Tariff made applicable by the commission with effect from 1.4.2006 shall not
apply for the financial year 2006-
07 in
so far as Seasonal Industries are concerned and the instructions in this
respect as applicable before the issue of General Conditions of Tariff will continue to apply for the financial year 2006-07. So for seasonal
Industries the tariff as was applicable prior to 1.4.2006 would remain
applicable for the financial year 2006-07. Necessary action may be taken
accordingly.
It
is also requested that wide publicity may be given for the information of the
concerned consumers please.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No.61/2006
Memo No. 76213/77013/ SSM-414/TW
/Policy-06-07
Dated.20/11/06
Subject:- Tubewell Policy- Release of tubewell connection under General Category-
Amendment thereof .
On
the basis of feed back from the field officers, instructions were issued vide
CC No.58/06 dated 3.11.06 that in the Operation Divisions, where no AP T/W
application, registered upto 31.3.88 under General Category was pending, new
AP T/W connections under General Category would be released against the test
reports received against applications registered upto 31.3.90 in the order of
seniority based on the date of registration of application and the material for the release of these
connections would be issued by the Stores Organization subject to
certification by the concerned Sr.Xen/Addl.SE on the indent itself that no T/W
application registered upto 31.3.88 under General Category is pending under
his Division. The Operation Divisions where applications registered upto
31.3.88 under General Category were still pending for release of connection,
all out efforts are to be made by the field officers to clear such pending
applications registered upto 31.3.88 and thereafter action should be taken as above regarding release of new AP connections under General
Category against applications
registered upto 31.3.90.
The matter has been reviewed further and
it has been decided that the
cut-off date for release of new AP tubewell connections under General Category
in respect of operation divisions where no AP T/W application registered upto 31.3.88 under General Category is
pending, shall be 31.12.90 instead of 31.3.90
All
other terms & conditions of CC
No. 58/06 dated 3.11.06 shall remain unchanged.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 60/2006
Memo No. 74287/75087/Indl./SNG/55
Dt. 14.11.06
Sub: Non-availing of Full sanctioned load at the time of release of new
Connection –Amendment to ESR 35.
Clarification has been sought by field offices regarding applicability
of ESR Clause 35 titled "Non availing of full sanctioned load at the time
of release of new connection" for the cases involving extension in load on the plea that the Regulation is applicable for release of new
connections sonly.
Upon ,consideration of the after
it has been observed that the instructions are not clear as to whether these
are applicable to new connections only or to cases of extension in load as
well it is also felt that extension n load involves addition of new
equipment/machinery which is; equivalent to installing load of new connection
for all intent and purposes. Thus ,it is very much logical that the facility
of; building up of the load in phases as per instructions of ESR clause 35
should also be applicable for cases involving extension inn load.
The matter has been considered by the WTMs and it has been decided to
incorporate a new clause 35.1.3 in the PSEB Electricity Supply Regulations as under:
"The provisions contained in ESR clause 35.1.1 and 35.1.2 shall be
applicable for release of extension in
load also ,to those LS consumers ;whose connected load including applied
extension in load is more than 1 MW"
All other terms and conditions as applicable as per ESR 35 shall remain
unchanged.
Sd/-
Director/S-II
PSEB,Patiala.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No. 59/2006
Memo No. 73295/74095/SSM-414/Drip
Dated.10/11/06
Subject:- Release of tubewell connections on
priority to the farmers installing Drip/ Micro Sprinkler Irrigation system.
The present water scene of
Punjab
is pointing towards the repid degradation of ground water resources. The
ground water table decline has crossed
30 cm
annually and more than 100 blocks of the state have suffered groundwater
degradation of more than 100% . Thousands of tubewells in the state have been
forced to be converted from centrifugal to submersible pumping even in this
era of power shortage. In the long
run, ground water conservation is the only alternative to restrict this
dangerous trend of ground water level decline.
The Government of India has launched National Horticulture Mission (NHM)
for holistic development of
horticulture in the country . Another programme of Micro Irrigation (MI &
Drip/Sprinkler System) of horticulture has been launched. To encourage water
conservation by using drip/sprinkler irrigation system and in the best
interests of the farmers & State, a meeting regarding allowing priority
power connections to the farmers installing drip/micro sprinkler irrigation
system under the above two programmes launched by the Government of India was
held on 21.7.2006 under the Chairmanship of Chief Secretary ,Punjab. As per
decision taken in the meeting , the matter has been considered and it has been
decided as under:-
i) Release of tubewell connections on priority shall be allowed to the prospective consumers in the State on Drip/Micro Sprinkler Irrigation Systems installed on a minimum area of 2(two) hectares for fruit crops,
and 1(one) hectare for vegetables
and non horticulture crops.
ii) The Priority shall be allowed on a Joint Certificate from the
Divisional Soil Conservation Officer and the Deputy /Assistant Director of
Horticulture.
iii) The tubewell connection will be released after the installation
of the Drip/Micro Sprinkler Irrigation System.
iv) The priority shall be admissible upto the release of connection
without any cut off date subject to following terms & conditions.
a) The
prospective consumer must have land in his own name and will submit FARD in
this regard at the time of registration of application.
b) Only One tubewell
connection shall be allowed under this priority category.
c) The
prospective consumer shall submit an affidavit duly attested by First Class
Magistrate that in case he is found using the tubewell connection for any
other purpose, his tubewell connection shall be disconnected without any
notice.
d) The priority
shall be allowed by Sr.Xen/Addl.SE/Op. concerned after fully satisfying
himself with regard to the genuineness of the priority claim & that the
prospective consumer has actually installed the sprinkler system.
e) The consumer
should purchase ISI marked material for drip irrigation/sprinkler system
through demand draft with valid receipt. The equipment so purchased shall be
clearly identified with Sr.No. and Make etc. on the bill itself. The material
should be duly tested / approved by National Test House/ any other
agency/Govt. approved agency or duly
recommended
and tested & approved by Punjab Agricultural University Ludhiana and
Punjab Small Scale Industrial
Corporation.
f) The concerned Divisional Soil Conservation Officer/Dy.Director
Horticulture, as the case may be, must certify after installation of Drip
irrigation/Sprinkler system at site, that material procured is ISI marked duly
tested by the approved Test House/Govt. Agency and system as a whole has been
installed on a minimum area of two hectares for Fruit crops & one hectare
for Vegetable & Non-horticulture crops and is of approved design / layout
.
g) To avoid misuse of
the priority, the test reports relating to drip irrigation / sprinkler system
shall be verified by the AE/ AEE/Xen/Op. only. The concerned officer at the
time of verifying the test report must record on the test report itself that
the prospective consumer has installed proper/ valid sprinkler system
indicating the Sr. No. & other details of the equipment installed on the
test report itself.
h) The working of
the Drip Irrigation/Micro Sprinkler system shall be checked by the AE/ AEE/Xen/Op. concerned once in a year and a certificate of checking shall be placed
in the consumer file so as to ensure that the system is in the working order
and this priority is not being misused. In case it is found on checking that
this priority is being misused, the tubewell connection shall be disconnected
on the spot without any notice.
i) ESR No.13.4.18 & 13.4.18.1 & & 13.6.18.2 are amended accordingly.
Procedure / roster to be followed by field officers for the release of
AP tubewell connection / issue of material had been circulated vide CC.No.
43/2006 dated 4.8.2006 and for restoring this facility of allowing priority
tubewell connection to prospective consumers adopting Drip/Sprinkler System,
the procedure/roster is amended as under : -
i) 1st - General Category
ii) 2nd - General Category
iii) 3rd - General Category
iv) 4th - Ex-servicemen
priority
v) 5th - Kandi Area
priority
vi) 6th - Own
transformer priority
vii) 7th - Drip/Sprinkler
System priority
viii) 8th - General
Category & so on.
It
is requested that wide publicity may be given by the field officers for
information of general public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.
58/2006
Memo
No. 71737/72537/SSM-414/TW-06-07
Dated.3.11.2006
Subject:- Tubewell Policy- Release of tubewell connection under General Category.
Instructions were issued vide CC No.25/06 dated 2.6.06 that all out
efforts should be made by the field officers to clear the AP T/W applications
registered upto 31.3.88 under general category and issue of material for
release of new AP T/W connections was allowed in respect of test reports
received against applications registered upto 31.3.88 only in the order of
seniority based on the date of registration of application. An amendment was
issued vide CC No.42/06 dated 3.8.06 and the instructions were also reiterated
in the T/W policy for the year 2006-07 issued vide CC No.43/06 dated 4.8.06.
There
is a feed back from the field officers that in the Border, North & Central
Zones, there are no pending T/W applications under general category registered
upto 31.3.88. In the West &
South Zones also in many of the Divisions, there are no pending applications
under general category registered upto 31.3.88. Thus in view of above
instructions the release of new T/W connections in the Border, North &
Central Zones and some of the Divisions under West & South Zones, has been
held up. The matter has been reviewed and it has been decided as under:-
i) In the Operation
Divisions, where no AP T/W application, registered upto 31.3.88 under General
Category is pending, new AP T/W connections under General Category shall be
released against the test reports received against applications registered
upto 31.3.90 in the order of seniority based on the date of registration of
application.
ii) The Operation Divisions where
applications registered upto 31.3.88 under General Category are still pending
for release of connection, all out efforts shall be made by the field officers
to clear such pending applications registered upto 31.3.88 and after the
backlog of applications registered upto 31.3.88 is cleared, action shall be
taken as per Para- (i) above.
iii) The material for the release of
connections under General Category against applications registered upto
31.3.90 shall be issued by the Stores Organization subject to the condition
that a certificate is given by the concerned Sr.Xen/Addl.SE on the indent
itself that no T/W application registered upto 31.3.88 under General Category
is pending under his Division.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.
57/2006
Memo No. 70819/71619
/ SSM-249/VDS/SP
Dated: 3/11/2006
SUB:- Voluntary Disclosure Scheme for S.P. consumers.
To regularize the already running unauthorized load of SP Category Consumers so that the feeding system of PSEB could be upgraded in
commensurate with the already running load, thus ensuring continuity of the
quality power supply, it has been decided to introduce VDS for Small Power
supply (SP) consumers only w.e.f. 7.11.06 upto 31.1.07 with the following terms and conditions :-
(i) No load surcharge shall be charged during the period the scheme shall
remain operative.
(ii) The load shall be deemed to have been released from the date of written
declaration indicating the extra load installed by the consumer. This written
declaration shall be considered as the A&A form for the enhanced load and
kept in the consumer case file and suitable entry shall be made on the
existing A&A form. The small power industrial consumer shall be allowed to
declare the additional load to the extent of 100% of the existing sanctioned
load.
(iii) SCC at half the normal rate
of Rs.750/-per KW i.e. Rs.375/- per KW shall be recovered for the additional
load
(iv) ACD at the prevalent rate of Rs.500/-or part thereof per KW for extra
load shall be recovered in case of no change of category after extension.
(v) In case of change of category from SP to MS as a result of
additional load, the ACD as
applicable under MS category i.e. Rs.750/- per KW or part thereof shall be
recovered for the total load giving due credit for the ACD already deposited.
(vi) As a result of change of category due to increase in load, consumer
shall be governed under the tariff applicable to the changed category from the
date of declaration of load.
(vii) The load shall be checked/verified by the AE/AEE/XEN (OP.) subsequently
& consumer will be given a period of six months for installation of shunt
capacitor of requisite capacity if required.
(viii) Wherever augmentation of line is involved, the same shall be done by
the Board on priority.
(ix) The release of load under VDS shall be further subject to condition
that the consumer shall submit an affidavit for submission of NOC for his
total load from the PPCB within six months of declaration of extended load, if
the same is applicable to his industry to be decided by load sanctioning
authority.
Similarly NOC from Municipal Corporation/Committees, and PUDA shall not
be insisted upon from such consumers, whose industry is already running in the
residential areas or other restricted areas subject to the condition that if
any statutory body or courts objects later on for the extension so granted,
PSEB shall be at liberty to withdraw the extension for which suitable
undertaking may be taken from the consumer. However, such consumers shall be
required to deposit ACD at double the normal rates for the extended load only. In case of change of
category from SP to MS, the ACD for the existing load shall be charged as per
MS category after giving due credit for the ACD already deposited and for the
extended load, the ACD shall be charged at double the normal rates for MS
category.
(x) This scheme shall not be available to the consumers located in
Chandigarh
periphery area.
It is requested that wide publicity may be given by the field
officers for information of general public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 56/2006
Memo
No. 69540/70340 /CC/T/1/Misc./SC
Dated : 31.10.2006
Sub:- Grant of free electricity for domestic purposes up to 200 units per
month to the Members of Scheduled Castes having sanctioned load up to 1000
Watts.
As per instructions issued vide CC No. 11/2006 dt. 1.3.2006 SC domestic
consumers with connected load upto 500 Watts were allowed free electricity
upto 200 units per month w.e.f. 1.9.05. In compliance of instructions issued by Govt. of
Punjab
received vide Chief Secy. GOP note
dated 11.10.06, it has now been
decided to grant concession of free electricity upto 200 units per month to SC
DS consumers with connected load upto 1000 Watts w.e.f. 2.10.2006. Accordingly
w.e.f. 2.10.06 the SC consumers with connected load above 500 Watts and upto
1000 Watts have also become eligible for free electricity upto 200 units per
month.
It has further been decided that w.e.f. 2.10.06, meter rental, MCB
rental, Service charges and octroi
etc. will also not be charged in the energy bills of the SC domestic consumers
with connected load upto 1000 Watts i.e. if any SC DS consumers with connected
load upto 1000 Watts has his consumption upto 200 units per month or 400 units
bi-monthly, his bill amount will be zero.
Necessary action should be taken accordingly and it should be ensured
that concession is passed on to the eligible consumer, during the current
billing cycle of October, November 2006. All the instructions issued vide CC
No. 11/2006 for allowing free electricity to SC DS consumers with connected
load upto 500 Watts will be applicable except that limit of connected load has
been increased to 1000 Watts w.e.f. 2.10.06.
Following points may be kept in view :
(i) Refund in cash to remaining SC DS
consumers with connected load upto 500 W on a/c of free electricity upto 200
units per month w.e.f. 1.9.05 may continue to be given as per instructions
issued vide CC No. 17/2006 and CC 32/2006.
(ii) Free electricity with 200 units per
month will also be admissible to new SC DS consumers with connected load upto
1000 W from the date of connection.
Field Officers
are requested to give wide publicity of the above concession being provided by
the Board so that maximum number of eligible consumers are in a position to
avail of the same. Advertisement is being given in various news papers
requesting the eligible consumers to submit requisite documents to concerned
subdivisions. It should be ensured that intimation on the prescribed performa.
(Advice) is sent to the CSC immediately on receipt of requisite documents from
the consumer.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC: No 55 / 2006
Memo
No. 68576/69376/ SSM-249/VDS/DS
Dated:
31.10.06
Subject: Voluntary Disclosure Scheme (VDS) for DS /NRS category of consumers.
In view of the over
whelming response to the VDS for DS and NRS consumers introduced vide CC
No.45/05 dated 12.7.05 and the feedback, from field offices that unauthorized
load of DS/NRS consumers is
resulting into overloading of the system and frequent breakdowns especially
during summer season, the matter has been considered & it has been decided
to introduce the voluntary disclosure scheme for DS & NRS consumers w.e.f
1.11.2006 so that DS/NRS consumers may declare their unauthorized load & get it regularized to enable PSEB to augment the system in line with the
increased load.
The VDS for DS & NRS consumers shall remain in force for
three months i.e upto 31.1.2007.
2. The main features of
this scheme shall be as under :-
i) There will be no checking of connected load
during the period VDS remains in force and resultantly no penalty for
unauthorized extension in load shall be levied.
ii) The load shall be computed as under :-
Description |
Domestic |
NRS |
Remarks |
Light
Point |
60
Watts (1/2 of total light points to be taken into account) |
80
Watts |
Fraction
of Light Point to be taken as one |
Fan
Point |
80
Watts each
(1/3rd
of total No. of sockets to be taken into account) |
100
Watts each |
Fraction
of Fan Point to be taken as one. |
Wall
Sockets |
60
Watts each (1/4th of total No, of sockets to be taken into
account) |
80
Watts each (1/3rd of total No. of sockets to be taken into
account) |
Faction
of Socket to be taken as one socket. |
Power
sockets |
1000
Watts each
(1/4th of total No. Sockets to be taken into account) |
2000
Watts each (1/2 of total No. of sockets to be taken into account) |
Faction
of Socket to be taken as one socket. |
i) After
computing the load as above, the consumer can intimate the computed load for
regularization on the reverse of the energy bill also, which will form part of
A&A form and placed in consumer file. During the VDS period, the load will
be regularised without any verification and test report.
ii) The extra load shall be regularized in the name of existing consumer, may
be owner of the premises or tenant or actual user as the case may be without
asking for any additional documents for effecting change of name or for
establishing identity of the original consumer.
iii) Mass awareness camps shall be arranged
where the concerned Officers/Staff of DS organization shall be available to the
public in the said Camps for regularization of extra load on the spot after
accepting payment of ACD and reduced SCC there & then.
iv) Reduced Service Connection
Charges (by 50%) shall be recovered against such declaration as under:-
SR.No. |
Load |
DS
(Rs.per KW) |
NRS
(Rs.per KW) |
I |
Upto
1KW |
Rs.125/- |
Rs.125/- |
II |
Above
1KW & upto 3KW |
Rs.150/- |
Rs.250/- |
III |
Above
3KW & upto 7KW |
Rs.250/- |
Rs.375/- |
IV) |
Above
7KW |
Rs.375/- |
Rs.500/- |
vii) ACD recoverable shall be as per existing rates which are as under:-
a) Domestic Rs.500/-per KW or part thereof.
b) Non Residential (NRS)
Rs.700/-per KW or part thereof.
viii) Augmentation of
service line/transformer and the power system and change of meter etc. shall be
done by the Board at its own cost.
ix) After extension in load, if
load falls in range from 11KW to 50 KW the connection shall be released with LT
metering in 3 phase category by providing independent T/F of 10/16 /25 /63KVA or
higher capacity with zero LT and meter shall be installed in MCB or pillar box
on the pole /under the distribution transformer. However more than one
connection can be given from the same T/F if the premises are nearby by
providing meters in pillar boxes or in MCB /CT Chambers on poles.
For loads ranging from 51 KW to 100 KW shall be released at 11 KV only
with LT metering by providing independent 63 /100/200 KVA distribution
transformers. DS/NRS loads above 100 KW shall continue to be released as per
existing instructions as per Schedule of Tariff SV and SVI, at 11 KV supply
voltage as per discretion of the Board
x) No load surcharge shall be levied.
xi) The
total load(including unauthorized extension) shall be considered for the purpose of regulating service connection charges in the specific
slabs mentioned above, but the actual charges to be recovered shall be for the
unauthorized load only at the rates as
applicable for the slabs relating to the total load.
xii) DS/NRS consumer shall be allowed to extend their load under VDS subject
to maximum of 100% of the sanctioned load .
xiii) In case of new connections released under DS/NRS category , no extension
in load under VDS shall be allowed for a period of 6 months from the date of
release of connection .
The field officers shall give wide publicity to the scheme for information of the General Public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.54 /2006
Memo No.
67173/67973 /SSM-249/AP.
Dated: 20.10.2006
Sub: Voluntary Disclosure Scheme vis-à-vis compulsory regularization of unauthorized extension in load by Agriculture Tubewell
consumers.
Feedback has been received from
the field offices that due to depleting water table, No. of AP consumers have installed higher capacity motors
thus putting excess load on the system which loads to higher losses, and overloading/ breakdowns in the system . It would, therefore, be in the
interest of the Board that the unauthorized load of AP consumers is regularized
after recovering appropriate charges. Moreover, there is demand from the various Kissan Unions also that VDS for AP consumers, on
the pattern as introduced vide CC
23/2006 dated 26.5.2006, should be
re-introduced .
2. The matter has been considered and it has been decided to introduce the
VDS for AP consumers under which they will be able to voluntarily disclose /
declare their excess / unauthorized load & get the same regularized after
paying requisite charges as per VDS . The scheme will
remain inforce from 1.11.2006 to 31.1.2007.
3. The charges for regularization of the excess / unauthorized load so declared under VDS
shall be Rs.1000/- per BHP as Service connection charges and Rs.200/- per BHP as
ACD,without levy of any load surcharge.
4. The temporary
tubewell connection released during the paddy season of 2005 and regularized as
per CC No. 9/2005 shall not be covered under this scheme as no extension in load
is permissible to such regularized tubewell connection upto a period of 3 years
from the of release /regularization of such a temporarily tubewell connection.
5. Salient features of the scheme shall be as under:-
(i) The regularization shall be done immediately as
deemed regularization on detection of unauthorized load or self-declaration by
the consumer regarding unauthorized load. It is emphasized that the farmers who
visit the sub divisional offices for regularization of the additional load
should be attended properly and promptly. His application regarding declaration
of the additional load be accepted and necessary entries of the additional load
be made in his passbook and ledger and the BA-16 Receipt issued for the charges
recovered. The consumer shall install the shunt capacitors of requisite capacity
as per the total load and the test report shall be arranged by SDO Incharge
through JE Incharge who should indicate total load of the motor and KVAR
capacity of the Shunt Capacitor installed. The requirement of new forms has
been dispensed with. The extra load shall be regularized after deposit of
requisite charges for extended load only and getting suitable entry made in the
passbook.
(ii) Augmentation of the line
and distribution transformer, wherever required after due consideration /
verification by Sr.XEN/Op. concerned shall be done by PSEB at its cost. For the
purpose of regularization of the load, the loading of the transformers may be
taken as 100% instead of the existing 80%. In case with the addition of
unauthorized load , the loading of the existing transformer becomes beyond 100%
the action to augment the transformer capacity shall be taken with the approval
of SE/DS as under :-
a) 25/63
KVA transformers which become more than 100% loaded shall be replaced with 63
KVA/100 KVA transformer respectively with the condition that neither a new tubewell connection shall be released from this transformer
nor any tubewell connection from other over loaded transformer shall be shifted
to this augmented transformer .
b) In case
of 100 KVA transformer, the de-augmentation shall be done by providing small
individual transformers of 6.3/10/16 KVA rating .
The regularization of unauthorized load shall not be withheld due to over
loading of distribution transformers as the unauthorized hidden load was already
on the system . [
Field officers are requested to give wide publicity to this
scheme and organize mass consumer contact camps in rural areas to regularize the
higher capacity motors on the spot during the VDS period.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.53/2006
Memo
No..65412/66212/SR 134.5
Dated:17.10.2006
Sub: Commercial Circular No.34/06 dated 6.7.2006 – Clarification thereof.
An open house discussion
with the field officers under the Chairmanship of Member/D was held and it has been decided to issue following clarifications/
amendments to the Commercial Circular No.34/06
dated 6.7.06:-
1. Keeping in
view the problems faced by the field officers in dealing with the theft of
energy cases, the matter has been considered and it has been decided that
checking regarding theft of electricity be carried out by the following
officers/officials of the Board:-
1. |
All domestic/ NRS/AP /SP /BS connections upto 20 KW |
JEs/AAEs of Operation Wing( within his jurisdiction). |
2. |
All domestic/ NRS/AP /SPMS/LS/BS connections upto 500 KW |
Any officer of operation wing not below the rank of AE( within his jurisdiction). |
3. |
All Large & Bulk Supply beyond 500 KW and Railway
Traction |
Any officer of operation wing not below the rank of Sr.Xen ( within his jurisdiction). |
| |
Enforcement Officers: |
|
1. |
All categories of consumers with loads upto 500 KW |
Any Officer of the Enforcement Wing not below the rank of
AEE( within his jurisdiction). |
2. |
All categories of consumers with loads above 500 KW |
Any Officer of the Enforcement Wing not below the rank of
Sr.Xen( within his jurisdiction). |
| |
MMTS Officers: |
|
| |
Medium Supply / Large Supply / Bulk Supply. |
Sr,Xen/Addl.SE/MMTS |
Since special courts for
dealing with the cases of theft of energy as covered Under Section 153 of
Electricity Act-2003 are yet to be constituted by govt. of Punjab, as such after
carrying out the inspection of the premises, authorized officer shall prepare a
detailed inspection report containing details of connected load, meter/metering
equipment details, working of meter, condition of seals and other irregularities
noticed (such as any artificial means of theft of electricity).
The authorized officer
and other members of the team accompanying him shall carry photo identity cards.
The inspection report shall be signed by the authorised officer, all members of
the inspection team and consumer/person or his/her representative. A copy of the inspection report shall be handed over to the consumer/
person or his/her representative at site under proper receipt. In case of refusal by the consumer/ person or his/her representative, a
copy of the inspection report shall be pasted at a conspicuous place in/outside
the premises. Simultaneously, the
inspection report shall be sent to the person under registered post.
In case the theft of
electricity is established, the supply of such premises shall be disconnected
forthwith and meter/metering equipment shall be sealed in 'as found conditions'. in order to take further action in view of the circumstances explained
above, a copy of the inspection report shall be sent by the authorized/checking
officer/official to the concerned assessing officer for making assessment of
charges as per provisions of Section 126 of Electricity Act-2003.
As per notification No.
1/60/03-EB(PR)/1186 dated 27.12.04 of the Govt. of Punjab, the following
officers of the Board are authorized to make assessment of charges payable by
the LT & HT consumers:-
Category of consumers |
|
Assessing Officers |
All HT
consumers above 1 MW load |
: |
CEs of the Operation Wing of respective Distribution Area |
All HT Consumers upto 1 MW load |
: |
SE/Dy.CEs of Operation Wing of the Distribution Area. |
All LT Industrial consumers |
: |
Sr.Executive Engineers/Addl/SEs of Operation Wing of the
Distribution Area. |
All other LT consumers. |
: |
Assistant Engineer/Assistant Executive Engineers/Executive
Engineers of Operation wing of the Distribution Area. |
2. Unauthorised use of electricity (UUE) under section 126 of the
Electricity Act-2003.:
The UUE shall be dealt
as per Section 126 of the E.A.2003 and covers the following means:-
(i) by any artificial
means , or
(i) by a means not
authorized by the concerned person or authority or licensee, or
(ii) through a
tampered meter, or
(iii) for the purpose
other than for which the usage of electricity was authorized.
Following types of cases shall also be covered under
UUE:-
(a) Where a consumer
engages un-authorizedly in supply of electricity to any service disconnected by
the Board/Licensee or in the illegal restoration of his own service disconnected
by the Board/Licensee.
(b) Where a consumer
keeps connected to Board/Licensee's supply system any apparatus or adopts any
electrical appliance for the purpose of splitting the phase to run his three
phase appliances when the Board/Licensee's three phase supply is not available
to him.
(c) Where a consumer
uses electricity supplied under a particular tariff for a purpose for which some
other (especially higher) tariff is in-force, or
(d) Where a consumer
without the permission of the Board/Licensee extends the Board/Licensee's supply
to any premises other than the premises to which the supply is given or to any
consumer/unit within the same premises. Provided
that extension of Board/ Licensee's supply for a religious or non commercial
social function of the consumer himself not exceeding three days shall not be
considered as unauthorized use of electricity.
3. Procedure for booking a case for unauthorized use of electricity.
(a) An
assessing officer, (designated as per GOP notification dated 27.12.04 and
detailed under para-1 above, suo moto or on receipt of reliable information/
complaint regarding unauthorized use of electricity in a premises shall promptly
conduct inspection of such premises.
(b) The assessing officer and other members of the team shall carry along
with them photo identity cards, which shall be shown to the person present at
the premises before entering therein.
(c) If on inspection of the premises or after inspection of the equipments,
gadgets, machines, meter etc. or after inspection of the records, the assessing
officer comes to the conclusion that the person is indulging in unauthorized use of electricity,
he shall prepare an inspection
report giving details of connected
load, condition of seals, working of
the meter and also mention the irregularities noticed which established
unauthorized use of electricity.
(d) Details
of evidence substantiating the unauthorized use of electricity in the premises
shall be clearly recorded by the assessing officer in the inspection report.
(e) The inspection report shall be signed by the assessing officer and each
member of the inspection team and the person or his/ her representative, and handed over to the person or his/ her representative
present at site, under proper receipt. In
case of refusal to accept the report, a copy of the inspection report must be
pasted at a conspicuous place in/outside the premises. Simultaneously, the
inspection report shall be sent to the person under registered post.
(f) The assessing officer shall provisionally assess to the best of his
judgement the amount to be paid by the person benefited by the use of
unauthorized use of electricity.
(g) The
order of provisional assessment under section-126 of the Electricity Act -2003
(as per proforma enclosed) shall be served upon the person under proper receipt
through registered post or courier or
speed post or by hand (indicating the identity of the person to whom delivered).
(h) The person served with the order of provisional assessment may accept
such assessment and deposit the assessed amount with the licensee within 7 days of such provisional assessment order
served on him, and in that case, he shall not be subjected to any further liability or any action by any authority whatsoever.
(i) The reply to the notice of provisional assessment order shall be
submitted by the person within 7 days of
its receipt. The assessing officer, only after affording a reasonable
opportunity of hearing to such person, shall pass a final assessment order specifying the amount
payable by such person on account of unauthorized use of electricity.
4. Submission of reply by the person:
If
the person submits his reply within the stipulated period, the assessing officer
shall analyze the case within 7 working days from the date of submission of
person’s reply, after carefully considering all the submissions and documents
submitted by the person, facts on record and the inspection report. The case of
unauthorized use of electricity shall be dropped immediately, if it is concluded
by the assessing officer that there
is no unauthorized use of electricity, and the decision in this respect shall be
communicated to the person under proper receipt, within 15 days of submission of
reply by the person.
5. Affording personal hearing to the person. (Levy of charges for UUE):
(a) If the assessing officer concludes that there is unauthorized use of
electricity, he will provide personal hearing to the person within 15 days of
submission of reply and will pass a
final order of assessment specifying the amount payable by the person
, only thereafter.
(b) If the assessing officer reaches a conclusion
that the unauthorized use of electricity
has taken place, it shall be presumed
by the assessing officer that such an unauthorized use of electricity has been continuing for a period of 3 months immediately preceding the date of inspection in case of domestic and
agricultural consumers and for a period of 6 months immediately preceding
the date of inspection for all other categories of
consumers, and he shall provisionally assess the consumption per month
based on the following formula:-
(A) For cases of unauthorized use of electricity covered under sub-section
6(b)(i),(ii) and (iii) of Section 126 of the Act:-
(1) Units assessed = L x D x H x F,
where L is the load found connected during the course of inspection in KW.
D
is number of working days per month, during which unauthorized use/theft/pilferage is suspected and shall be taken
for different categories of use as below:-
a) |
Continuous industry |
30 days |
b) |
Non-continuous industry |
25 days |
c) |
Domestic use |
30 days |
d) |
Agriculture |
30 days |
e) |
Non-Residential(Continuous) viz hospitals, hotels,
restaurants, guest houses, nursing homes, petrol pumps. |
30 days |
f) |
Non Residential (general)i.e. other than (e) |
25 days |
g) |
Water works & Street Lights |
30 days |
h) |
Other categories. |
30 days |
H
is use of supply hours per day, which
shall be taken for different categories of use as below:-
a) |
Single Shift industry(day/night only) |
08 hrs. |
b) |
Non-continuous process industry(day/night) |
20 hrs. |
c) |
Continuous process industry |
24 hrs. |
d) |
(i) Non
Residential(General) including restaurants)
(ii) Hotels, Hospitals, nursing homes, guest houses, petrol pumps. |
12hrs.
20 hrs. |
e) |
Domestic |
08 hrs. |
f) |
Agriculture |
06 hrs. |
g) |
Water works |
08 hrs. |
h) |
Street Lights |
12 hrs. |
| |
Other categories. |
12 hrs. |
F
is load factor,
which shall be taken for different categories of use as below:-
a) |
(i) Industrial (General)
(ii) Power Intensive, Arc Furnace |
60%
75% |
b) |
Non-Residential |
60% |
c) |
Domestic |
40% |
d) |
Agriculture |
100% |
e) |
Direct Theft |
100% |
f) |
Other categories. |
100% |
(2) The
consumption so assessed as above shall be charged i) for a period of 3 months in
case of domestic and agriculture supply consumers and for a period of 6 months
in case of other consumer categories, ii) at one and half times the rate per
unit of the tariff applicable to the consumer category, after adjusting the
amount paid by the person for the energy consumption for the assessment period
if any.
(3) In cases
where fixed monthly tariff exists, monthly assessment shall be made at one and a
half time the monthly rate.
(B) For cases of unauthorized use of electricity covered under sub-section
6(b)(iv) of section 126 of the Act.
(i) If it is established during inspection of a premises that the energy
supplied is used for a purpose on which higher tariff is applicable, the total
energy consumed in the previous 3 months in case of domestic supply or
agriculture consumer and 6 months for all other category consumers, from the
date of detection, shall be charged at one and half times the rate applicable
for the category for which load was found to have been used.
(ii) The above calculations are subject to the condition that meter is
recording energy accurately. Else,
the energy will be calculated on the basis of LDHF formula as per details in A-1
above.
(iii) The amount already paid by the person for the energy consumed during the
assessment period, if any, shall be adjusted in the amount assessed as above.
(iv) This assessment shall not relieve the consumer from any penalty imposed
by law/regulations or under any provisions of the code.
The
period of 3/6 months may be suitably reduced if it is established from the facts stated by the person at the time of
inspection or any other such
evidence noticed by the assessing officer that the offence has been committed
for less than 3/6 months respectively. However, the assessing officer shall duly
record reasons for reduction in the period of such provisional assessment. The
amount shall be assessed at a rate equal to one and a half times the tariff
rates applicable for the relevant category of consumers. Credit for the
amounts, if any paid by the person during the period for which the assessment is
made shall be allowed, to avoid duplication of billing for such period.
In case of seasonal industries, the off-seasonal
period (non-working) shall not be included in the period under assessment.
For AP consumers the tariff rate without Govt. subsidy
shall be applicable for assessment of charges.
(c) The person will be required to deposit the assessed amount with the
licensee within 7 days of receipt of the final order of assessment. The licensee may, after taking into consideration the financial position
and other conditions of person, extend the last date of payment or approve the
payment to be made in installments on a written request made by the person and
submission of an undertaking to abide by the schedule of payment along with the interest due as per rules.
(d) The person served with the final assessment order may accept the order
and deposit the assessed amount with the licensee and in that case he shall not
be subjected to any further liability or any action by any authority whatsoever.
6. Appeal to Appellate Authority.
(a) No appeal shall be entertained by
the appellate authority (prescribed as per para-3 of CC 34/06 dated 6.7.2006)
unless the person deposits an amount equal to 1/3rd of the assessed
amount with the licensee and encloses documentary evidence of such deposit along with the appeal. Further, no appeal shall lie to the
appellate authority against the final order of the assessing officer if the
final order is made with the consent of the parties.
Any person aggrieved by the final assessment order made by the assessing
officer may, within 30 days of the
said order, prefer an appeal in such form, verified in such manner and be
accompanied by such fee as specified by the Commission in its Regulations for procedure of filling appeal before the Appellate
Authority to an appellate authority. (PSERC Notification dated 7.3.05 –
Annex-III of CC No. 34/06 dated 6.7.2006)
(b) The appellate authority shall dispose
of the appeal within 90 days of its receipt after hearing
the parties and pass an appropriate
speaking order and send the copies of order to the assessing officer and the appellant. The order of the appellate authority shall be
final. No civil court shall have the
jurisdiction to entertain any suit or
preceding in respect of any order
passed by the assessing officer or
appellate authority.
(c) In case the appellate authority decides that the case of unauthorized use
of electricity is not established, no further proceeding shall be taken against
the appellant and the case shall be dropped.
(d) Where the case of unauthorized use of electricity is established, the
person will be required to make the payment against final assessment order
within 7 days of its receipt.
7. Default in payment of amount assessed.
(a) In case of default in payment
of the assessed amount or any of the
installments of the assessed amount agreed
to by the person or 1/3rd amount in case filling of appeal is contemplated by the person, the licensee shall, without giving
any further notice in writing, disconnect the supply of electricity, remove the
meter and service line.
(b) When a person defaults in making payment of assessed amount, he, in
addition to the assessed amount shall be liable to pay, on the expiry of thirty
days from the date of order of assessment, an amount of interest @16% per
annum compounded every 6 months.
(c) The levy of charges on account of unauthorized use of electricity shall
continue till the cause of levy is removed and verified by the licensee.
8. The
compliance of above instructions should be carried out in letter & spirit. Any
difficulty in the implementation of these instructions may be immediately
brought to the notice of this office through the concerned EIC/CE/DS.
Sd/-
Chief Engineer/Comml,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.52/2006
Memo No.64057/64857 /SSM-450
Dated: 10.10.2006
Sub: - Release of AP T/W connection to Gram Panchayats for irrigating Gram
Panchayat land on priority.
As per
ESR-13.6.15 one no. tubewell
connection on priority is admissible to Gram Panchayats to enable them to lease
out the Shamlat land of the Gram Panchayat at a higher rate. However, keeping in view the huge backlog of AP test reports, a ban was imposed w.e.f. 12.4.2002 on the issue of demand notices to all AP categories including
Gram Panchayat priority. In a recent meeting
of the Programme Implementation Committee chaired by Hon'ble Dy.C.M., Punjab
held on 10.7.2006 at
Chandigarh
, it was desired that in order to supplement the income of Village Panchayats, tubewell connections may be released by the Board to
Village Panchayats on priority.
The matter has
been considered and Chairman PSEB has been empowered to allow priority (upto the
release of connection ) for a tubewell connection in the
Panchayat
Land
and in the name of Panchayat. However, if panchayat is already having T/W
connection in the
Panchayat
Land
, then another connection will not be sanctioned/released.
The
field officers shall ensure that wide publicity is given to above decision to enable Village Panchayats to make use of
this scheme.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 51/2006
Memo
No. 63945/64745/C-231/Mohali/L
Dated : 4.10.06
Sub: Waiver of Advance Consumption Deposit on captive power generation -
amendment to Sales Regulation Clause 170.3.2.11.
As per existing instructions if a PSEB consumer is also operating a CPP unit and some of his load is fed from
PSEB supply, he is required to pay ACD for the load exclusively fed from TG /DG set as well. The recovery of ACD for load fed
from TG/DG sets was introduced vide Commercial Circular 26/2002 and incorporated
in sales regulation as ESR 170.3.2.11. Advance
Consumption Deposit is recovered from various categories of consumers at a prescribed rate to safeguard the recovery of
electricity charges of the electricity consumed by a consumer. With the
formulation of captive power policy vide CC 26/02 dated 10.6.02, the co
generator/NRSE project developer as well as CPP owners who were also consumers
of PSEB were required to pay ACD of the load to be fed from co generation plant,
NRSE plant and captive power plant. The logic for recovery of ACD for this load
which is normally fed from the plant is that the plant owner can draw energy from PSEB system for the entire load normally being fed from his own
plant provided the meter and the feeding PSEB line is of adequate capacity. It
has however been noted during the
past years while implementing the captive power policy, that the plant owners do
not resort to drawl of energy from PSEB system to the extent PSEB had assumed.
The energy generated by consumer and consumed by him does not in any way call
for covering the risk of non payment of energy bill for the energy supplied by
PSEB. Therefore, recovering of ACD for the energy consumption for the energy
supplied from the consumer's TG Set is not fair. The matter has been considered
and it has been decided to amend the clause 170.3.2.11 as under:
"Existing consumers or new consumers who wish
to install TG sets as Co generation plant/NRSE plant/CPP and wish to run some
load exclusively from their TG sets as CPP shall not be required to deposit ACD
charges for the load to be run exclusively from the TG sets as CPP. However
permission fee (installation charges) and interfacing (parallel operation)
charges, if any applicable shall continue to be levied. In the event of TG set
load is found running from PSEB system, then load surcharge shall be recovered
for the load found running extra over & above sanctioned load to be fed from
PSEB system. Consumers shall also be liable to pay compensation for damage if
any caused to PSEB lines /equipment. "
Field
Officers are requested to give wide publicity to the above instructions.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No.50/2006
Memo
No. 63222/63822/SMI-259
Dated
: 29.09.2006
Sub: Release of Temporary Tubewell Connections during the Paddy Season of
2006.
On the
persistent demand of farmers instructions were issued vide CC No.26/2006 dated
2.6.06 regarding release of temporary tubewell connections during the Paddy
Season of 2006. As per these
instructions, temporary tubewell connections were to remain operational from
20.6.06 upto 30.9.2006 i.e. these are to be disconnected by 30.9.06.
Feedback
has been received from the field officers that during the current paddy season
the temporary tubewell connections were made operational late i.e. w.e.f
20.6.06. Further ,due to late sowing
of paddy by the farmers as per advice of the Scientists from
PAU
, the paddy season will last for another 10 to 15 days and some delegations of
farmers have approached the field officers with the request that temporary
tubewell connections released during the current paddy season may not be
disconnected upto 15.10.06.
In view
of above, the matter has been considered and it has been decided that all
temporary tubewell connections which were released during the current paddy
season as per CC No.26/2006 dated
2.6.06 shall now be disconnected by 15.10.06 instead of 30.9.06. The instructions issued vide CC 26/06 dated 2.6.06 shall stand amended to
this extent and all other terms & conditions shall remain unchanged.
Field
officers are requested to give wide publicity to this scheme through all
possible means including announcements through public address systems of
Gurudwaras/Mandirs etc
Sd/-
Dy.CE/Sales, for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No__49/2006
Memo
No. 66502/67302
Dated
: 19.9.06
Sub:- Load
Surcharge in case of NRS consumers, ESR clause 86.5.0.
As
per Sales Regulation Clause 86.5, if the connected load of a NRS consumer
exceeds the sanctioned load, the excess load shall be unauthorized load and such
excess of the connected load shall be charged load surcharge and the
unauthorized load so detected has to be regularized. Instructions are silent
where marginal load beyond 100 KW is detected and the consumer decides to keep
his load below 100 KW. As per instructions, the consumer is required to pay the
Transformation charges, in addition to service connection charges. The matter
has been considered and it has been decided to introduce Clause 86.5.1 in
continuation to SR clause 86.5 as follows:-
86.5.1. "In the cases
where loads are detected upto 110 KW, the consumer should have option to get the
load regularized or submit fresh Test Reports for reduced load in which case he
would be required to pay only load surcharge for the excess load but ACD,SCC and
Transformation charges would not be leviable. However in case such consumers are
subsequently found to be running load above 100 KW they would not be given any
relief to reduce their load and should then be charged both Transformation
charges as well as ACD & SCC etc. as per provision under Sales Regulations
Clause 86.5. However for load detected more than 110 KW, the existing
instructions shall continue to apply."
All
other terms and conditions of Sales Regulation Clause shall remain unchanged.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 48 /2006
Memo
No. 65449/66249 / Indl.187-KHN
Dated. 15.9.2006
Sub:- Grant of Feasibility clearance to Industrial units.
It
has been observed that in some feasibility clearance cases, the proposal
forwarded by the field office for release of new connection / extension in load
to the prospective / existing consumer is subject to the system constraints such
as commissioning of new 66/132/220 KV S/Stn. or augmentation of the existing
transformer /feeding transmission line which are likely to take long period for
erection /commissioning. Allowing conditional feasibility clearance in such
cases where grid constraints are there for release of load puts the Board in
awkward position as the prospective / existing consumers start putting all sorts
of pressure for release of load and the onus for release of load falls on PSEB
which in turn is unable to do so due to system/ grid constraints .
In view of above, the matter has been considered
and it has been decided as under:-
"Feasibility
clearance for release of new connection/extension in load in case where the
applied load/extension in load cannot be released due to the system/grid
constraints such as installation/augmentation of power T/F or erection of new
Sub-Stn./Transmission line, may not be given. The requisition for these new
connections/extension in load for which feasibility clearance is not given due
to system /grid constraints may be kept pending for consideration for
feasibility clearance until Board is in a position to release the load/extension
in load within a period of six months. However, such applicants shall retain
their seniority as per date of requisition".
The strict
compliance of the above instructions be ensured by all the field officers.
Sd/-
Dy.CE/Sales, for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 47
/2006
Memo No. 57031/65301/SSM-118
Dated. 13.6.06
Sub: ` Consumer Complaint Handling Procedure-
Appointment as Ombudsman.
Punjab
State Electricity Regulatory Commission vide Notification No. PSERC/JSF-29/4523
dated. 30.8.2006 has appointed Smt. Surinder Paul Kaur as Ombudsman in persuance
to Section-42 of the Electricity Act. read with "PSERC (Forum and
Ombudsman) Regulations 2005"(already circulated vide CC No. 27/06 dated
6.6.06). The copy of the Notification dated 30.8.2006 is enclosed herewith for
information of the field officers.
It is requested that the
field officers may give wide publicity to the above for the information of
general public.
DA/As
above.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.46/2006
Memo
No.56645/57445/Tissue Cultutre/Tariff
Dated :
07.09.2006
Sub: Exemption of Electricity Duty to existing Agri. Tissue Culture Units.
The Govt of
Punjab
has decided to grant 50% exemption from payment of ED w.e.f. 18.2.2006 to
existing Agri Tissue Culture units. Accordingly notification No.
11/259/2005-PE-(4)/10155 dt. 3.7.2006 has been issued ,the operative part of
which is reproduced below:-
" In pursuance of the decision of Council of Ministers
taken in its meeting dated 18.2.2006 held under Chairmanship of the Chief
Minister, Punjab and in exercise of the Power conferred by Section 12 of the
Punjab Electricity (Duty) Act, 2005 and all other powers enabling it on this
behalf , the Govt. of Punjab is pleased to grant 50% exemption from the payment of Electricity
Duty which is charged @10% advalorem for a period of 5 year from 18.2.2006 to
the existing Agri. Tissue Culture Units situated in Punjab State and to refund the basic electricity duty already paid by these units
through adjustment in future bills. This exemption has not been granted on
surcharge payable on the basic Electricity Duty. This Electricity Duty exemption
is subject to approval of a transparent metering arrangement by the Supplier and
the Chief Electric Inspector
Punjab
through which the electricity units drawn from the supplier for consumption can
be measured. This is also subject to a certificate of eligibility to be issued
by the Deptt. of Industries/Agriculture.
You are requested to take necessary action in the matter accordingly.
Sd/
Director/Sales-II
For
CE/Commercial,
PSEB
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C
No.45/2006
Memo No. 50400/51200/SSM-118 Dated: 11.8.200
Sub: Consumer Complaint Handling Procedure- Amendment thereof.
Instructions regarding adoption of 'Consumer
Complaint Handling Procedure' as approved by PSERC were issued vide CC
No.40/2006 dated 29.7.2006 followed by CC No.41/06 dated 1.8.2006.
As per
nomenclature approved by PSERC, the various dispute Settlement Committees are
designated as 'Zonal Level Dispute Settlement Committee', Circle level Dispute
Settlement Committee & 'Divisional Level Dispute Settlement Committee'.
However in CC
No.40/2006 dated 29.7.2006 & CC No.41/06 dated 1.8.2006, these committees
were designated as Zonal Level Dispute Settlement Committee(ZLDSC), Circle Level
Dispute Settlement Committee(CLDSC), & Divisional Level Dispute Settlement
Committee (DLDSC). The same may be
replaced to read in line with the nomenclature as approved by PSERC i.e. Zonal Dispute Settlement Committee (ZDSC), Circle Dispute Settlement Committee
(CDSC) & Divisional Dispute Settlement Committee(DDSC) respectively.
2. Nodal Officer (i.e. SE/Dy.CE/HQ Circle of the concerned) as indicated
against Zonal Level Dispute Settlement Committee (ZLDSC), under Para-3 (ii)(a)
of CC No.40/2006 dated 29.7.2006 maybe amended to be read as SE/Dy.CE/HQ
of the concerned Zone .
3. Presenting Officer as indicated against Circle Level Dispute Settlement
Committee(CLDSC), under Para-3(ii)(a) of CC No.40/2006 dated 29.7.2006 maybe
amended to be read as Sr.Xen/Addl.SE/DS
of the concerned Division..
All other terms & Conditions of CC 40/2006 dated 29.7.2006 and CC
No.41/206 dated 1.8.2006 shall remain unchanged.
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No. 44/2006
Memo No.
50176/50976/SMI-259 dated
8.8.2006
Sub: Release of temporary tubewell connections during the paddy season of
2006.
Instructions
were issued for release of temporary tubewell connections during the paddy
season of 2006 vide CC No. 26/2006 dated 2.6.2006 . The para Viii of this
circular reads as under:-
" The service cable length of connection shall normally be
limited to 100 Mtrs.. However in hardship cases the length of service cable may
go upto a miximum of 110 Mtrs".
It has come to the notice of this office that the above clause is
being misused by adopting pick& choose policy in respect of 'hardship cases' .
The matter has been considered & it has been decided that
temporary tubewell connection shall be allowed with maximum service cable upto 110 Mtrs.
All other terms & conditions of CC No. 26/2006 dated. 2.6.2006
shall remain unchanged.
Dy.C.E./Sale
For Chief
Engineer/Comml.
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C
43/2006
Memo
No.49219/50019/SSM-414/TW-07-07
Dated
4.8.2006
Sub: - Tubewell Policy for the year 2006-07.
Keeping in
view pending test reports as on 31.3.06 as per the data / information received
from Chief Engineers/DS, the policy for release of new AP T/W connections during
the year 2006-07 has been considered and it has been decided as under :-
i) Target for release of 40,000 No. new AP tubewell connections during the
year 2006-07 has been fixed which
shall cover the test reports received upto date both for General Category and
Priority Categories. Adequate funds should be got allocated for release of these
connections so that the material for release of connections is provided by the
Board.
ii) Based on the zone wise position of the pending test reports as on
31.3.06,the allocation for each zone has been fixed as under:-
SR.No. |
Zone |
No. of
connections allocated |
1. |
West |
15300 |
2. |
South |
11000 |
3. |
North |
4300 |
4. |
Central |
5500 |
5. |
Border |
3900 |
| |
Total |
40,000 |
The
quarterly progress report for the release of tubewell connections shall be sent
by CE/DS concerned to CE/Commercial so as to monitor the progress achieved.
iii) As per data available, there are 39,589 No. pending Test reports as on
31.3.06 against which tubewell connections are yet to be released. Keeping in
view the target of 40,000 No fixed for the release of. new AP tubewell
connection during the year 2006-07,only these 39,589 pending test reports would
be covered for release of tubewell connections. Besides these test reports, the
test reports to be received against priority categories during the year shall
also be covered.
I}}}iv) }}Although cut-off date for issue of demand
notice under general category is 31.3.91 but keeping in view the pending test
reports it has been decided that demand notice(s) against applications
registered under general category from 1.4.90 to 31.3.91, shall not be issued
upto 31.12.06 after which this will be reviewed & necessary instructions to
allow issue of Demand Notice(s) for application registered from 1.4.90 to
31.3.91, if feasible, will be issued. However Demand Notice(s) for the applications registered upto 31.3.90 will continue to
be released as per instruction already inforce.
The ban imposed on issue of fresh demand notices w.e.f. 12.4.02 shall
continue except for applications registered upto 31.3.1990 under General
category besides priority cases allowed under Chairman's discretionary quota
(five percent), Ex-serviceman's priority & Kandi area priority.
v) The issue of
demand notices by the Sub Divisions shall be
regulated by Dy.CE/SE/DS, who shall, keeping in view the availability of
material, decide the number of demand notices to be issued by respective Sub
Division on quarterly basis in such a way that Sub Divisions will be in position
to release the connection(s) within three months from the date of compliance of
demand notice(s) by the prospective consumers.
vi) All out efforts need to be made by the
field officers to clear the applications registered upto 31.3.88 for which
strict compliance of the following instructions already issued vide CC.25/2006
dt. 2.6.06 amd as amended vide CC No. 42/06 dated 3.8.06 be ensured by field
officers :-
a) Issue
of material for release of new AP tubewell connections will be allowed only in
respect of test reports received against applications registered upto 31.3.88 in
the order of seniority based on the date of registration of the application.
b) No material shall be issued by Stores Organization for the release of
tubewell connections under general category against applications
registered after 31.3.1988 till the back log of applications registered upto
31.3.88 is cleared in all the zones and revised instructions will be issued
thereafter .
vii) As per procedure presently being followed for release of T/W connection,
separate seniority queues such as Chairman priority ,Ex-serviceman priority,
Kandi Area priority ,HT/LT seniority queues, own T/F seniority etc.are maintained at Sub Division level. SDO incharge should monitor at
his personal level that the connections in all the seniority queues are released
side by side. The following
procedure shall be followed for the release of AP tubewell connections/issuance
of material by the field officsers :-
(a) Chairman Priority connection shall have over riding priority over all
other categories.
(b) For other categories ,the roster for
release of connections/issue of material shall
be followed as under:-
i) 1st – General
Category.
i) 2nd _ General
Category.
ii) 3rd _ General Category
iii) 4 th _ Ex-servicemen Priority
iv) 5 th _ Kandi Area Priority.
v) 6th _ Own Transformer Priority.
vi) 7th _ General Category and so on.
If
test report against any priority category is not pending ,then slot for that
priority category will go to general
category. For example in a sub-division if no test report under Ex-servicemen
priority is pending, then 4th slot in the roster will also go to General
Category.
viii) As per instruction issued vide CC 13/2006 dated 17.3.06, the new AP T/W
connection shall continue to be released on LT supply upto 30.9.2006.
ix
) Voltage
Regulation of 11KV feeder may not be a constraint for issue of demand notice to
such prospective consumers, who are otherwise eligible for issue of demand
notice. In such cases, an undertaking/affidavit that AP connection under the
present system constraints is acceptable shall be obtained from the prospective
consumer as per the existing instructions.
x) CE/MM & CE/Workshop shall assess the requirement of material and take
necessary steps to ensure timely procurement of material required for release of
40,000 Nos. new AP tubewell connections during the year 2006-07 keeping in view
the decision taken by WTMs on 14.6.06 to release all new AP tubewell connections under HVDS w.e.f.
1.10.2006.
xi) The
status of pending test reports,demand notices may be displayed on the Notices Board of concerned operation Sub-Division with regard to release
of AP connection during the year 2006-07.
All other
terms and conditions for release of tubewell connection shall remain unchanged.
Dy.C.E./Sales,
For Chief
Enginee
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C:C:No.42/06
Memo No. 42248/49059 /SSM-414 Dated:
03.08.06
Sub: - Release of tubewell connection under General Category.
Instructions
were issued vide CC 25/2006 dated. 2.6.2006 that no materal shall be issued by
store organisation under general category against applications registered after
31.3.88 till the backlog of applications registered upto 31.3.88 is cleared in
all the zones of PSEB. Para-III of the above circular provides as under :-
"The
works already in hand for whilch sufficient material stand issued before
31.5.2006 shall be completed & may not be withheld on account of above
instructions . However, where only Poles and fittings /stay set etc. have been
issued,no further material be issued".
The above relaxation was given
with a view that the genuine cases where bulk of material stood already issued/given may not be unnecessary
withheld. It has however been observed that
tubewell applicants registered after
31.3.88 are putting all sorts of pressures to get the material released under provision of above para with the result that most of the tubewell
connections being released are for applications registered after 31.3.88. This
has defeated the very purpose of nstructions
issued vide CC-25/06 dt. 2.6.06. Accordingly, it has been decided to delete Para III of CC-25/06 dt. 2.6.06 with immediate effect.
All other terms & conditions of CC 25/06 dated 2.6.2006 shall remain
unchanged
Dy.C.E./Sales,
For Chief
Engineer/Comml.,
PSEB,
Patiala.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No.41/2006
Memo No. 2170/2970 Dated: 1.8.2006
Sub: Consumer Complaint Handling Procedure- Constitution of Dispute Settlement
Committees.
In continuation of instructions regarding 'Consumer Complaint Handling
Procedure' to be followed with effect from 1.8.2006 issued vide CC.No.40/2006
dated 29.7.2006, it is clarified that various Dispute Settlement Committees of
PSEB shall stand reconstituted w.e.f. 1.8.2006 as under:-
A) Zonel Level Dispute Settlement Committees (ZLDSCs)
1 |
Chairman |
: |
Engineer-in-Chief/CE/DS
of concerned Zone |
2 |
Member
from Accounts Wing |
: |
a) |
Chief
Auditor- Central,South &West Zones |
: |
b) |
CAO Revenue
- North & Border Zones |
3 |
Member
from Commercial Wing |
: |
a) |
Dy.CE/Dir.Sales-I
- Central Zone |
b) |
Director/Sales-II
- North & Border Zones |
c) |
Director/Billing - South & West
Zones |
4 |
Nominated
Members |
: |
Representatives
of the Industry for the respective zone as per CC No.4/2005 dated 14.1.2005 |
B) Circle Level Dispute Settlement Committees (CLDSCs)
1 |
Chairman |
: |
Dy.CE/
SE/DS of concerned Circle |
2 |
Member
from Accounts Wing |
: |
Dy.C.A.
of concerned Zone under which
the Circle falls |
3 |
Member
from Commercial Wing |
: |
Dy.Director/Sales
dealing with the concerned Circle |
4 |
Nominated
Member |
: |
Representative
of the Industry for the respective zone as per CC No.4/2005 dated 14.1.2005 |
C) Divisional
Level Dispute Settlement Committees (DLDSCs)
1 |
Chairman |
: |
Addl.
SE/Sr.Xen/DS of concerned Zone |
2 |
Member
from Accounts Wing |
: |
Accounts
Officer/Field of concerned Circle under which the Division falls. |
3 |
Member |
: |
Xen/AEE./AE
to be designated by concerned Dy.CE/SE/DS from within the Circle. |
All other terms and conditions of CC No.40/2006 dated 29.7.06 shall
remain unchanged.
Dy.C.E./Sales,
For Chief
Engineer/Comml.,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C:C:No. 40/2006
Memo No. 1242/2042 / SSM-118 Dated: 29.7.2006
Sub: - Consumer Complaint Handling Procedure.
In order to provide an inexpensive,expeditious and efficacious mechanisum to resolve the
differences and disputes, the Board had constituted a number of committees at
different levels to settle the
differences / disputes arising between the Board and the consumers. The exising set up of the various Dispute Settlement Committees as
constituted by the Board is as per ESR-No.142 and as amended by instructions
issued vide CC.No.4/05 dated 14.1.2005
and 39/05 dated 7.6.2005.
2. In terms of the provisions of Regulation-5(2) of the "PSERC (Forum
& Ombudsman) Regulations,.2005", PSERC vide its order dated June
26,2006 has approved the ' Consumer Complaint Handling Procedure' vide its letter No. 3385
dated 28.6.06 (copy enclosed) & have directed that this system shall be effective from 1.8.2006. The said procedure is self explanatory and needs no
elaboration.
3. It should be ensured that the
new system is set in place well in time and made functional from the date
specified by the Commission i.e. 1.8.2006.
The salient features of the 'Consumer Complaint Handling Procedure' as
approved by the PSERC are as under:-
i) Nature of Complaints
Consumer
complaints shall pertain to:
· Billing
· Metering
· Interruption/failure of power supply
· Voltage variations
· Load shedding/scheduled outages
· Disconnection/Reconnection
· Any other matter concerning supply of electricity
ii) Constitution of various Dispute Settlement Committees has been
mentioned in para-4 of the enclosure. As required under para-4 (2) and para
–4(3) of 'Consumer Complaint Handling Procedure', the Presenting Officer and Nodal Officer shall be as under:-
| |
Dispute
Settlement Committee- |
Presenting
Officer |
Nodal Officer |
Financial
Limit |
a) |
Zonal
Level Dispute Settlement Committee-(ZLDSC) |
SE/Dy.CE/DS
of the concerned Circle. |
SE/Dy.CE/HQ
Circle of the concerned |
All
cases above
Rs.2
lacs in each
case. |
b) |
Circle
Level Dispute Settlement Committee
(CLDSC) |
Sr.Xen/
Addl.SE/ DS of the concerned Circle |
Sr.Xen/Addl.
SE/Tech.of the concerned Circle |
All
cases above
Rs.50,000/-
and
upto
Rs.2 lacs in each case. |
c) |
Divisional
Level Dispute Settlement Committee-(DLDSC) |
Xen/AEE/AE/DS
of the concerned Sub-division |
Divisional
Supdt.of the concerned Division |
All
cases upto
Rs.50,000/-
in
each case. |
iii) The procedure for redressal of complaint as per para –6 of 'Consumer 'Complaint Handling Procedure', shall be strictly followed.
However, as far as para –6(8) is concerned, it is decided as under:-
When unanimity
is not reached while disposing of the disputed case by the above Dispute
Settlement Committee, the majority decision will be applicable. However, the
minutes to be recorded shall be self speaking and views of dissenting Member(s)
should be indicated alongwith the operating part of the decision specifically.
Copy of decision in each case shall be sent by Chairperson of DSC concerned to CE/Commercial without exception.
As per para-6(12) of 'Consumer Complaint Handling Procedure' the
Chairperson of DSC is competent to fix the amount to be deposited before
consideration of the case by the Committee. In case the consumer is unable to
make the part payment of 20% ,the chair person will record the specific reasons
for fixing the amount to be got deposited less than the part payment of 20%.
iv) Regarding para-6(14) of 'Consumer Complaint Handling Procedure', it is
clarified that the Nodal Officer will maintain proper record of all the
complaints received as disposed off on
behalf of the DSC.
i) The 'Consumer Complaint Handling Procedure', shall come into effect with effect from 1.8.2006
and all the existing complaints/appeals (all cases pending for review /appeal in
various DSCs / DSA) except those on matters pertaining to open access granted
under the Electricity Act,2003 and Sections 126,127,135, to 140,142,143,146,152
and 161 of the Act, before any authority previously constituted(i.e. DSCs / DSA) shall stand transferred to the jurisdiction of respective Dispute
Settlement Committees and Forum for Redressal of the Grievances, as the case may
be. All the previously constituted committees shall cease to exist with
effect from 31.7.2006.
ii) The field officers will :-
a) give wide publicity to the existence of the 'Consumer Complaint
Handling Procedure' by periodical press release, display on notice boards in the
distribution sub-divisions or at the Complaint centres/Bill collection
centres,web site of PSEB and such other means to make the public aware of the procedure;
b) make available an updated copy of the 'Consumer Complaint Handling
Procedure' ,as revised from time to time for inspection by members of the public
during normal working hours:and
c) Provide an updated copy of the aforesaid procedure revised from
time to time to the consumers and any other person who requests for it at a
price of Rs. 50/- per copy.
vii) Consumer's
right to approach the Forum.
A complainant aggrieved due to non-redressal of his complaint under
the 'Consumer Complaint Handling Procedure', may approach the Forum established
by the Board vide CC.27/06
dt.6.6.2006 under as sub-section (5) of Section 42 of the Act read with "
PSERC (Forum & Ombudsman) Regulations, 2005.&qu |