Search Go
 
MUKERIAN HYDEL PROJECT - STAGE - II

1)

Location

To be situated at RD- 550M of newly built channel of approx, 3.5 Km length, off taking from RD-35500m of Mukerian Hydel Channel of MHP Stage-I of maximum carrying capacity 11,500 Cusecs.

2)

Main Features:

Project envisages to provide a permanent outfall structure for the Mukerian Hydel Channel Stage-I in to river Beas & additionally to generate power.

3)

No. of Power Houses.

One

4)

No. of Units:

Two

5)

Total generating capacity

2x 8.25 = 16.5 MW

6)

Designed net Head:

Approx. 7.21 M

7)

Design Discharge:

10,000 cusecs

8)

Type of Development

Run-of-the canal

9)

Commissioning:

2002-06

10)

Cost of Project:

Approx. 138 Cr.

11)

Total energy contribution annually

  134.3 MU + 74 MU =208.3 MU
annually saved by preventing annual forced closure of MHC-I for stone crate dumping (208.3 MU) 

12)

Cost per unit:

Approx. Rs. 1.92 per unit

13)

Cost of the Project:

Rs. 138 Crore (Approx.)