Search Go
 

SHANAN POWER HOUSE, PSEB, JOGINDER NAGAR (110 MW):INTRODUCTION:110 MW Shanan Project is the most picturesque project in the beautiful surroundings of Himalayan ranges. It is situated in the North Indian State, Himachal Pradesh at an approximately longitute of 76 degree ? 51? East and latitude of 32 degree ? 2? North. It takes advantage of two small rivulets at an altitude of about 6000 ft., in Brot valley. The idea of harnessing a power potential of 4X12 MW (48 MW) initially was envisaged by Col. Battye, the then Chief Engineer of Govt. of Punjab in 1922. This 48 MW Stage Ist Project was constructed at the initial cost of Rs. 2,53,43,709/- and commissioned in 1932 and was officially opened by His Excellency, The Viceroy of India at Shalimar Receiving Station, Lahore on 10th March, 1933.Shanan Power House, 1st Stage of 4X12 = 48 MW was renovated to 4X15 = 60 MW in 1982. No major work in the form of additions and alterations in Head works, water conductor system, Power House building was involved.The Shanan renovation project was finally commissioned in December, 1982. SHANAN EXTENSION PROJECT (50 MW).As originally conceived by Col. Battye, the extension of the 1st Stage of Uhl river Project was proposed by constructing an additional unit of 50 MW. This extension work mainly consisted of a new extended reservoir at Brot, laying of new penstock for 50 MW and construction of new power house building. Finally this project with unit of 50 MW was commissioned in March, 1982 SALIENT FEATURES OF SHANAN POWER HOUSE

Sr. No. Description Shanan 1st Stage Shanan Extension
1. Rating of each unit 15 MW 50 MW
2. No. of units at PH 4 Nos. 1 No.
3. Manufacturer GANZ MAVAG, Hungary GANZ MAVAG, Hungary
4. Turbine out put 21800 HP 70000 HP
5. Max Net Head 548 M 548 M
6. Min. Net Head 446 M 481.6 M
7. Rated Net Head 487.7 M 487.7 M
8. Discharge required 525 Cusecs 425 Cusecs
9. Type of turbine Horizontal Pelton Wheel Vertical Pelton Wheel
10. No. of Blades 21 22
11. Dia of Runner 2569 mm 2800 mm
12. Generator Voltage 11000 Volts 11000 Volts
13. Type of Generator Horizontal Shaft Suspension
14. Normal speed 428.5 RPM 375 RPM
   GENERATION ACEIVEMENTS (In MUs):
Sr. No. Year Generation (In MUs)
1. 1982-83 424.896
2. 1983-84 540.674
3. 1984-85 470.209
4. 1985-86 521.016
5. 1986-87 530.903
6. 1987-88 517.389
7. 1988-89 567.361
8. 1989-90 538.650
9. 1990-91 573.176
10. 1991-92 577.252
11. 1992-93 591.523
12. 1993-94 512.253
13. 1994-95 533.594
14. 1995-96 551.697
15. 1996-97 507.401
16 1997-98 600.019
17. 1998-99 637.183
18. 1999-2000 506.507
19. 2000-01 487.703
20. 2001-02 473.110
21. 2002-03 469.279
22. 2003-04 564.205
23. 2004-05 515.474
24. 2005-06 508.950

Shanan Hydel Project has achieved the record generation of 637.18 MUs in the year1998-99since its commissioning, which was the milestone in the history of Shanan Hydel Project. U.B.D.C POWER HOUSES, STAGE-I & II (91.35 MW)Upper Bari Doab Canal Hydro Electric Project (UBDC) is located near Pathankot falling in the district of Gurdaspur in Punjab. The Power station is situated on the Upper Bari Doab Canal, which draws water from river Ravi for the dual purpose of Irrigation and Power generation. Water of river Ravi passes through Ranjit Sagar Dam at Thein before entering into UBDC Canal. At present, UBDC Project comprises of two stages of Hydro Power stations i.e. Stage-I and Stage-II. Stage-I Project consisting of three Power Houses namely I,II & III each having a generating unit of 15 MW was erected and commissioned during 1971-73. Stage ?II of UBDC Project consisting of three additional Power Houses namely I,II&III each having a generating unit of 15.45 MW was erected and commissioned during 1989-92. As such UBDC Hydro Electric Project has a total installed capacity of 91.35 MW.The Power Houses are situated at different reduced distances (RD?s) of the channel and located as mentioned below: - of the channel and located as mentioned below: -

Sr. No. Description UBDC Stage-I UBDC Stage-II
1. Capacity 3X15 = 45 MW 3X15.45 = 46.35
2. RD PH-I 13500 ft. PH-II 24750 ft. PH-III 40000 ft. PH-I 13500 ft. PH-II 24750 ft. PH-III 40000 ft.
3. Location PH-I Ferozepur PH-II Sujanpur PH-III Sarna PH-I Ferozepur PH-II Sujanpur PH-III Sarna

 Salient features of the UBDC Project are given as under: -

Sr. No. Description of the generating units UBDC Stage-I UBDC Stage-II
1. Rating of each unit 15 MW 15.45 MW
2. No. of units of each PH 3 Nos. 3 Nos.
3. Manufacturer 1 No. AEI (UK) 2 No. HEL 3 No. BHEL
4. Turbine out put 21000 HP 21340 HP
5. Max Net Head 18.3 M 18.3 M
6. Min. Net Head 14.8 M 14.8 M
7. Rated Net Head 17.1 M 17.1 M
8. Discharge required per m/c for max. Generation 3625 Cs 3625 Cs
9. Type of turbine KAPLAN KAPLAN
10. No. of Blades 6 4
11. Dia of Runner 3962 mm 3900 mm
12. Generator Voltage 11000 Volts 11000 Volts
13. Type of Generator Vertical Shaft Vertical Shaft
14. Normal speed 150 RPM 166.7 RPM
15. Direction of Rotation Clock wise Clock wise

The commissioning dates of UBDC PHs are given below :-Stage-I Power HousesPower House No. 1. 30.08.1971
Power House No. 2. 24.05.1972
Power House No. 3. 12.04.1973Stage-II Power HousesPower House No. 1. 06.08.1989
Power House No. 2. 26.06.1991
Power House No. 3. 01.01.1992P.S.E.B has incurred an expenditure of 17.41 crores through Pb. Irrigation department for re-modelling of escape channel at RD- 72720 to enhance its capacity from 1500 Cusses to 7200 Cusses. This work has been completed in 7/2004. This has enabled PSEB to have extra generation from UBDC PHs by enabling the inflow through the Hydel Channel during the lean period even when Irrigation Indent is Nil. This is evident with the generation of 217 MU during the current year from April to July. As such the total generation during the year 2005-2006 is likely to be about 450 MU.A scheme for renovation and modernization of UBDC PHs during the 10th five year plan has been approved by the Board costing to Rs.789/-lac. An amount of Appx.Rs.150 lac has been already spent. This will help in smooth running of the generating units by replacement of the old and worn out equipment.Residual life Assessment of UBDC PHs Stage-I, having completing more than 30 years, has since been got carried out from M/S BHEL. Recommendations of RLA Studies is under consideration and after implementation, the life of Stage-I PHs shall be enhanced considerably.

GENERATION ACHEIVEMENTS (In MUs):

Year Actual Generation (In MUs)
UBDC Stage-I UBDC Stage-II Total Generation (in MU's.)
1988-89 206.51 - 206.51
1989-90 198.30 2.57 200.87
1990-91 152.91 47.82 200.73
1991-92 178.16 74.72 252.88
1992-93 144.83 122.81 267.64
1993-94 126.07 128.50 254.57
1994-95 133.75 154.00 287.75
1995-96 114.28 154.87 269.15
1996-97 131.84 142.37 274.21
1997-98 85.80 120.97 206.77
1998-99 131.07 124.83 255.90
1999-2000 137.35 181.42 318.77
2000-2001 155.89 190.16 346.05
2001-2002 114.11 206.28 320.39
2002-2003 168.90 224.87 393.77
2003-2004 190.90 236.54 127.44
2004-05 171.27 208.40 379.67
2005-06 250.14 280.49 530.63

Note:-  UBDC Stage-I&II project has achieved the record generation of 530.62 Mus in the year 2005-06 since its commissioning. RANJIT SAGAR DAM PROJECT, SHAHPURKANDI (600 MW):The earliest recorded proposal of storage on the river Ravi was mooted in 1912 for a 200 ft. high Dam near village Thein. It was inspected by committee headed by Mr. Willey in 1926-27 who had recommended to carry out the survey of the area, but up till 1954 nothing substantial was done except inspections by Geologists. It was in 1957 that the proposal of storage Dam on Ravi River materialized into an Irrigation scheme. The power generation aspect was then postponed to a future date. The first multipurpose project report was submitted to Government of India in 1964. Finally the project was accorded approval by Government of India in April 1982.Ranjit Sagar Dam (Thein Dam) Project is one of the largest multipurpose river valley project on the river Ravi about 24 KMs up-stream of Madhopur Head Works. It houses four generating units of 150 MW each with total installed capacity of 600 MW. It has firm power of 162 MW at 100% load factor. The average annual generation from this project during the last 3 years is around 1150 MUs, out of which 4.6% of energy generated is supplied free of cost to H.P. and 20% of energy generated is to be supplied to J&K at the generated cost at the Bus Bar. The Project has been conceived as a peaking station. The power generated is being fed into the existing 220 KV Grid substation at SarnaThe dates of commissioning unit wise are as under: -Unit No. I : 12.8.2000
Unit No. II : 12.10.2000
Unit No. III : 20.8.2000
Unit No. IV : 15.9.2000Salient features of the RSD Project are given as under: -

Name : Ranjit Sagar Power Plant
Location : Shahpurkandi (Pathankot)
Dam Maximum Height above river bed Maximum Height Level of top : 135.00 m 160.00 m 540.00 m
Capacity : 4 x 150MW = 600 MW
Sources of Water : River Ravi
Reservoir a) Name b) Capacity : Ranjit Sagar 2344 Million Cum (Live storage) 3280 Million cum (Gross storage)
Water conductor system A) Tunnels a) Length b) Diameter c) Slope of invert d) Maximum Discharge through the tunnels : : 2 No. (P-I & P-2) P-I = 819 M, P-2 = 845M, 12.00 M Concrete reinforced. 9800 cumecs
B) Penstocks a) Numbers b) Internal diameter of each c) Maximum discharge capacity d) Number of turbines fed by each penstock : 2 Nos. penstock headers, 4 Nos. penstock branches 5.17M of penstock branch, 8.5M penstock header. 342 Cum/ Sec. 2 Nos.
Turbines a) Number b) Type c) Make d) Net head e) Rated output of each unit f) Normal speed :
4 Nos. Vertical shaft Francis BHEL 121.90M (Max.), 76.0M (Min.), 100M (Rated), 100M designed head) 154 MW 166.67 rpm.
Generators a) Number of Units. b) Make c) Voltage d) Capacity e) Current f) Power Factor g) Speed. h) Excitation system : 4 Nos. BHEL 13.8 K.V 166.667 MVA 6973 Amp. 0.9Lag 166.67 rpm. Static
Step up transformers. a) Number and voltage ratio b) Capacity : 13 Nos., Single phase : 13.8/220 62.5 MVA

 GENERATION ACHEIVEMENTS (In MUs):The Power Generated from 2000-20005 by RSD Project is given as under:

2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 435.06 MU's 1228.75 MU's 1150.49 MU's 1547.59 MU's 1144.15 MU's 2013.193 MU?s

i)  Ranjit Sagar Power Plant has caheived the record generation of 2013.19 Mus in the year 2005-06 since its commissioning , which was the milestone in the history of RSD Project. ANANDPUR SAHIB HYDEL PROJECT (134 MW):Anandpur Sahib Hydel Project is situated about 32 KMs. downstream of Bhakhra Dam towards Ropar side. This Project has been so named due to its vicinity to the famous historic Holy town of Anandpur Sahib, Birthplace of Khalsa. The Town itself is situated on the foot hills of picturesque Shivalik mountainous range and attracts thousands of people all the year around but more so during Holla Mohalla festival in the month of March. The famous Naina Devi temple is also situated nearby atop the hilly peaks of Shivalik. This Project was constructed to utilize additional water of Bhakhra Nangal System as a result of Interlinking of Beas and Sutlej Rivers at Dehar. This additional water has been utilized for power generation by constructing a new 34 KMs RCC Lined Canal named Anandpur Sahib Hydel Channel with 10,150 cusec capacity, taken off from left Bank of Nangal Reservoir (Nangal Pond) on the Sutlej river. This canal runs almost parallel to Nangal Hydel channel on the left side. The power potential of the Anandpur Sahib Hydel channel has been tapped by constructing 2 No. identical Power House at Ganguwal and Nakkian. The Ganguwal Power House is located approximately 19 KMs downstream of Anandpur Sahib Hydel Channel from Nangal Pond. Its tail water is taken to Nakkian Power House through a second stretch of approximately 11 KMs Canal. Both the Power Houses have been so located that gross head (92.69 Ft.) is equal in both the cases. The tail water from Nakkian Power House is being led into Sutlej River through Lohand Khud Escape. Each Power House has been equipped with 2x33.5 MW Generating Sets coupled with Kaplan Turbine Make BHEL Hardwar, are being supplied water through steel penstocks of 6 meters dia. The Hydro Generators are of suspension type having 2 No. Guide bearings. The Turbine governor is of electro-hydraulic type and excitation system is of conventional type with pilot and Main Exciter. The power is generated at 11KV and stepped up at 132 KV, is further fed into Regional Grid for exclusive use of Punjab.The Power Houses were commissioned during 4/5-1985 and it is being observed that all the 4 No. Machines of both Power Houses are being run satisfactorily since their commissioning on the full/part load as per availability of water, which depends upon the releases from Nangal Pond at Nangal. The requirement of water for full load running of Power Houses is approximately 10150 Cusecs.The Power Houses of Anandpur Sahib Hydel Project are working quite satisfactorily from the date of commissioning without any major breakdown. Electricity is generated as per availability of water in the AHC. The plant is giving a very good plant availability factor to the tune of 94% on the average. The Anandpur Sahib Hydel Project is giving a satisfactory performance. Salient features of the ASHP Hydel Project are given as under: -

Sr. No. Description PH-I PH-II
1. Capacity 67 MW 67 MW
2. RD 18911 M 29741 M
3. Location Ganguwal Nakkian
4. Rating of each unit 33.5 MW each 33.5 MW each
5. No. of units of each PH 2 Nos. 2 Nos.
6. Manufacturer BHEL BHEL
7. Turbine out put 46.25 HP 46.25 HP
8. Max Net Head 30.5 M 30.5 M
9. Min. Net Head 29.9 M 29.9 M
10. Rated Net Head 28.0 M 28.0 M
11. Discharge required per m/c for max. Generation 5050 Cusecs/m/c 5050 Cusecs/m/c
12. Type of turbine KAPLAN (Vertical shaft) KAPLAN (Vertical shaft)
13. No. of Blades 6 Nos. 6 Nos.
14. Dia of Runner 4000 mm 4000 mm
15. Generator Voltage 11000 Volts 11000 Volts
16. Type of Generator Suspension Suspension
17. Normal speed 187.5 RPM 187.5 RPM
18. Direction of Rotation Clockwise Clockwise
 GENERATION ACHIEVEMENTS (in MUs):
Year Actual Generation (In MUs)
PH-I Ganguwal PH-II Nakkian Total Generation(in MU's.)
1985-86 250.76 234.03 484.79
1986-87 287.64 282.05 569.69
1987-88 410.24 398.67 808.91
1988-89 371.40 371.01 742.41
1989-90 382.64 369.61 752.25
1990-91 331.17 328.18 659.35
1991-92 440.35 433.56 873.91
1992-93 444.31 434.80 879.11
1993-94 322.52 317.09 639.61
1994-95 458.43 449.47 907.90
1995-96 483.28 479.80 963.08
1996-97 480.80 479.32 960.12
1997-98 290.62 288.44 579.06
1998-99 540.72 530.97 1071.69
1999-2000 418.84 417.87 836.71
2000-01 324.78 326.90 651.68
2001-02 256.43 253.68 510.11
2002-03 375.41 374.14 749.56
2003-04 414.44 414.88 829.31
2004-05 276.55 280.74 557.28

The Anandpur Sahib Hydel Project has achieved the record generation of 1071.69 MUs in the year 1998-99 since its commissioning, which was the mile stone in the history of Anandpur Sahib Hydel Project.MUKERIAN HYDEL PROJECT, STAGE-I (207 MW):Mukerian Hyde Project is one of the main Hydro Electric Projects in the Northern Region situated in the Hoshiarpur District of Punjab. The Mukerian Hydel Project is run of the river project, constructed at Mukerian Hydel Channel emanating from Shah-Nehar Barrage. The Shah-Nehar-Barrage is constructed at the down stream of Pong Dam situated at the River Beas . The Barrage has 52 gates and thus a small artificial lake of holding capacity of 3404 acres feet has been created which feeds the Mukerian Hydel Channel. Mukerian Hydel Channel is 37 Km.long and lined by Cement Concrete and having maximum water carrying capacity of 11500 cusecs. The Mukerian Hydeel Project comprises of 4 No. Power Houses. Power House No. 1 & 2 have 6 Nos (3 at each Power Houses). Machines of 15 MW capacity each whereas Power House No.III & IV have 6 No. (3 at each Power Houses) machines of 19.5 MW capacity each. The total maximum generating capacity is 207 MW of all the 12 No. Machines. The Power Houses are situated at different reduced distances (RD?s) of the channel and located as mentioned below:-

Description PH-I PH-2 PH-3 PH-4
Capacity 45MW 45MW 58.5MW 58.5MW
R.D. 6365Mtrs. 16004 Mtrs. 18879 Mtrs. 27404Mtrs
Location Talwara Hazipur Ralli Uchi-Bassi

Salient features of the Mukerian Hydel Project are given as under:-

Sr./No. Description of the generating units PH No.1&2 PH No.3&4
1 Rating of each units 15 MW 19.5 MW
2 No. of Units at each PH. 3 No. 3 No.
3 Manufacturer M/s BHEL Bhopal M/s BHEL Haridwar.
4 Turbine Output 21000HP 27300HP
5 Max.Net Head. 17.5 Mrs. 22.5Mtrs.
6 Min.Net Head 16.5 Mtrs. 21.95Mtrs.
7 Rated Net Head 16.8 Mtrs. 21.95 Mtrs.
8 Discharge required per M/c for max. generation. 3708 cusec 3701 cusec.
9 Type of Turbine KAPLAN KAPLAN
10 No. of blades. 6 6
11 Dia. of runner 3962mm 3650mm
12 Generator voltage 11000 Volts 11000 Volts.
13 Type of generator Vertical salient pole and Umbrella Vertical salient pole and Umbrella.
14 Normal speed 150 RPM 166.7 RPM.
15 Direction of rotation Clockwise Clockwise

 The dates of commissioning Unit wise are as under: -

Name of PH Unit No. Date of Commissioning Date of synchronization Date of commercial operation
MPH-I Unit-I Unit-II Unit-III 02.10.1983 14.10.1983 26.11.1983 02.10.1983 14.10.1983 26.11.1983 02.10.1983 14.10.1983 26.11.1983
MPH-II Unit-IV Unit-V Unit-VI 05.05.1988 03.06.1988 28.02.1989 18.05.1988 03.06.1988 28.02.1989 18.05.1988 03.06.1988 28.02.1989
MPH-III Unit/VII Unit-VIII Unit-IX 11.11.1988 26.01.1989 10.03.1989 29.03.1989 22.03.1989 22.03.1989 29.03.1989 22.03.1989 22.03.1989
MPH-IV Unit-X Unit-XI Unit-XII 25.12.1988 10.03.1989 01.04.1989 22.03.1989 22.03.1989 25.05.1989 22.03.1989 22.03.1989 25.05.1989

 The generating Units at each Power Houses can be put in service/running with minimum flow of 1600 cusec. The Mukerian Hydel Project generates electrical energy at 11 KV and after stepping up to 132 KV, the same is transmitted to Grid system at 132 KV. Power House No. I is connected with Power House No.II and Power House No.II with PH No.III and PH No.III with PH-IV through 132 KV double circuits carried on towers. There are four 132 KV circuits for evacuation of electric energy generated, two numbers at PH-II to Jallandhar (through 132 KV Bhogpur and 132 KV Tanda circuits) and other two at PH-IV through 132 KV Sri-Hargobindpur Circuit I&II.

GENERATION ACHEIVEMENTS (In MUs):

Year Actual Generation (In MUs)
MHP-I MHP-II MHP-III MHP-IV Total Gen. (In MUs)
1988-89 222.69 3.35 - - 226.04
1989-90 277.37 202.45 330.81 326.69 1137.32
1990-91 299.24 244.21 313.61 311.45 1168.51
1991-92 265.51 243.45 317.64 313.26 1139.86
1992-93 245.17 234.36 307.02 305.88 1092.43
1993-94 253.53 248.26 318.76 314.25 1134.80
1994-95 284.24 293.26 377.03 375..85 1330.38
1995-96 314.45 309.63 322.18 398.53 1344.79
1996-97 277.69 285.01 348.16 363.98 1274.84
1997-98 287.29 297.08 377.25 377.85 1339.47
1998-99 326.23 337.15 435.03 430.03 1528.44
1999-2000 331.05 341.16 435.51 439.10 1546.82
2000-01 266.16 270.38 351.41 332.92 1220.87
2001-02 255.32 257.12 331.44 322.70 1166.58
2002-03 178.35 171.86 224.96 220.34 795.51
2003-04 226.42 224.83 290.59 287.39 1029.23
2004-05 191.30 177.44 225.19 227.68 811.62
2005-06 272.36 251.39 357.14 357.36 1238.25

This Mukerian Hydel Project has achieved the record generation of 1546.82 MU?s in the year 1999- 2000 since its commissioning, which was the milestone in the history of Mukerian Hydel Project. MICRO HYDEL PROJECTS:To exploit small Hydro potential available at various falls in the Canals running in Punjab State, four Micro Hydel Projects having machines rated 400 KW and 500 KW each with total installed capacity of 3.9 MW have already been commissioned at Rohti, Thuhi, Daudhar & Nidampur.The detail of Micro Power Houses is given as under:

Sr. No. Name of Micro Power Houses No. of Units Capacity of each units (KW) Installed Capacity (KW) Year of commissioning
1. Nadampur 2 400 800 1985-86
2. Daudhar 3 500 1500 1987
3. Rohti 2 400 800 1989
4. Thuhi 2 400 800 1989

1. Nidampur Power House is situated on Ghaggar branch Canal near Village Nidampur on Patiala-Sangrur Highway.2. Daudhar Power House is situated at Ajitwal-Badnikalan rural link road on Abohar branch Canal near Moga town.3. Rohti Power House is situated on Patiala-Nabha road at a distance of 19 KMs from Patiala on Ghaggar link Canal.4. Thuhi Power House is situated on Ghaggar branch Canal near village Thuhi at the distance from 4 KMs from Nabha Town.Technical data:

a. Turbine KAPLAN (Horizontal)
b. Step-up Transformer 0.400/11 KV
c. Generator Type Horizontal Shaft
d. Water Head 9.84 ft. for 2X400 KW (Capacity) 13.12 ft. for 3X500 KW (Capacity)
 GENERATION ACHIEVEMENTS (In MUs):
Sr. No. Year Nidampur Daudhar Rohti Thuhi Generation (In MUs)
1. 1990-91 2.454 4.555 0.405 2.639 10.053
2. 1991-92 2.783 5.251 0.692 3.031 11.757
3. 1992-93 3.351 4.381 0.428 3.459 11.619
4. 1993-94 1.538 3.121 0.291 1.692 6.642
5. 1994-95 2.575 4.232 0.467 1.754 4.028
6. 1995-96 2.079 4.444 0.801 2.061 9.385
7. 1996-97 2.345 4.708 0.937 1.796 9.786
8. 1997-98 0.863 3.578 0.738 1.784 6.963
9. 1998-99 2.044 4.429 1.259 2.139 9.869
10. 1999-00 2.108 5.482 1.175 2.602 11.367
11. 2000-01 2.066 5.513 0.703 2.132 10.414
12. 2001-02 2.409 4.641 0.559 2.078 9.687
13. 2002-03 1.894 4.186 0.874 2.009 8.963
14. 2003-04 2.652 4.965 0.071 2.189 9.877
15. 2004-05 1.066 1.251 0.015 1.226 3.558
16. 2005-06 1.78 2.53 1.64 1.01 5.96

 The Operation & Mtc. of all the four Micro Power Houses has been handed over to M/S DSL Powers (P) Ltd., Ludhiana on lease basis for 10 (ten) years w.e.f. 11.07.05.  ON GOING PROJECTS (UNDER CONSTRUCTION)I) Mukerian Hydel Project Stage-II (2x9 MW)Mukerian Hydel Project Stage-II is located at RD-880 M of the Mukerian Hydel Channel Stage-II, which takes off from Mukerian Hydel Chhannel Stage-I at RD-35500M. The project site is located about 5 KMs from Unchi Bassi and 12 KM from Dasuya Township in Distt Hoshiarpur of Punjab. Two generating units of 9 MW each with Kaplan Bulb Turbine are proposed for the project. The turbines are designed with net head of 8.23 M. The project envisages average annual generation of about 140 MUs at a approx. generation cost of Rs. 1.30 /kWh.Detailed Supply-cum-Works Contract Agreement for Rs. 70 Crores for Electrical & Mechanical Works on turnkey basis has since been placed on M/s BHEL in May 2004. The original commissioning dates for Unit-I & II were 7.3.06 and 7.6.06 respectively. However due to water logging problem which arose during excavations the commissioning of project has delayed. Now new site for PH has been selected and accordingly new commissioning schedule would fall in the year 2007-08.II) MICRO HYDEL PROJECT (2X850 KW)Guru Gobind Singh Super Thermal Power Station (GGSSTP) near Ropar City having installed capacity of 6x210 MW, draws about 750 Cusecs of water for cooling purposes from Nangal Hydel Channel (NHC).A new escape cum hydel channel of about 4.4 KM length is being built to discharge above water into river Satluj. The topography of area along the course of above channel permits a net head of about 9.57 M & this head is being utilized by generating power.As such a Micro Power House of total installed capacity of 1.7 MW (2x850 KW) is presently under construction at RD- 3400 M & is being executed on turn key basis.The major civil works are almost complete. The electro mechanical equipment's installation would commence shortly. The likely commissioning of this project is estimated to be by the end of Sept,2005.The project will generate about 134 MU per annum at 90% load factor. PROPOSED PROJECTSI) Shahpur kandi Hydro Electric Project (168 MW)It is envisaged to develop 168 MW Shahpurkandi Hydro Electric Project. The site is 11 KM down stream of Ranjit Sagar Dam and 8 KM up-stream of Madhopur head works in Distt. of Gurdaspur. It is proposed to construct 54.5 Mtr. high and 725 Mtr. long concrete dam and 7.7 KM long Hydel channel of capacity 385 cumecs. 2 No. power houses are to be developed, one of capacity 2x40 MW and second of capacity 2x40 + 1x8 = 88 MW. All the clearances like techno-economic clearance from CEA, environment and forest clearance of Ministry of Environment and Forests, approval from Planning Commission and TAC of Minsitry of Water Resources have been obtained. The estimated cost of the project is about Rs. 1700 Crores. The estimated completed cost after accounting for interest during construction is about Rs. 2632 Crores. The estimated power generation based on dependable year basis is 815 MUs. The cost of generation will be around Rs.3.50 per unit during the first year of operation. The land for the project stands acquired and an amount of Rs. 130 Crores has already been spent on it. The excavation work of Dam has already been taken in hand. Now M/s NHPC have been selected as an implementry agency and Bipartite MOU has since been signed. M/s NHPC will revise/up grade the project report and project cost.II) 75 MW UBDC Stage-III HEPUBDC Stage-III Hydro Electric Project envisages harnessing of hydro potential to the tune of 75 MW of UBDC Canal beyond the point where UBDC Hydel Channel merges with UBDC Canal. It is proposed to construct a 20.6 KM long Hydel Channel of capacity 375 cumecs, 9.2 KM long Escape Channel , also of capacity of 375 cumecs, 22.4 KM long Alternate Irrigation Channel of capacity 8 cumecs and 0.7 KM long Carrier Channel of capacity 195 cumecs. Power House-I proposed with three units each of 15 MW capacity (total 45 MW) while the Power House II will have two units each of 15 MW capacity (total 30 MW) . Escape Channel outfalls into river Beas about 9 KM down stream of Shally pattan. The project envisages annual generation of approx. 472 MUs. The total cost of completion of project is estimated to be Rs. 640 Cr.The project is envisaged to be executed on BOOT basis & for this purpose a private developer has since been selected through global tendering. Further negotiations are going on & this project is likely to be initiated within the current financial year 2005-06. The per unit cost quoted by the developer is Rs. 2.69 with Hydrological risk of developer and Rs. 2.50 if Hydrological risk lies with PSEB.



Terms & Conditions | Privacy Policy | Feedback | Admin Login
Developed and Maintained by Phoenix IT Solutions Ltd.
©2007 PSEB -All Rights Reserved