1) Name of the Project Goindwal Thermal Plant.
2) Location Goindwal Sahib, Distt. Amritsar.
3) Installed Capacity 2 x 250 = 500 MW
4) Fuel Coal
5) Executing Agency GVK Power (Goindwal Sahib) Ltd., (IPP)
6) Clearance of CEA Not required as conveyed by Govt. of Punjab.
7) Estimated Cost Rs. 2000 Crores
8) Expected date of commissioning 2004 - 06
9) Annual Generation at 68.5% load factor 3000 MU

2715 MU Net

10) Coal consumption To be supplied by IPP
11) Cost of Generation To be supplied by IPP
12) Latest Status Fuel supply agreement with Eastern Coalfields Ltd., and Fuel Transport Agreement with Railways are under negotiations. For Escrow Account Agreement with PSEB matter is under consideration by Board. Company is discussing with FIC/Banks for mobilization of Debt.

 