|
Tariff Related Issues
Some Tariff related issues have been raised by various Consumers/Consumer
Organizations. The Commission has examined all these issues along with responses
of the Board thereto. These issues are discussed below:
8.1 TWO PART TARIFF AND MONTHLY MINIMUM CHARGES
PSEB has proposed to introduce two part tariff for all categories of consumers
except agricultural pumpset and temporary supply consumers. Fixed/demand charges
for Large Supply industrial consumers, Railway Traction, MES and Bulk Supply
are proposed to be levied on the sanctioned contract demand and for other categories
namely Medium Supply, Small Power, Domestic Supply, Non-Residential Supply and
Public Lighting fixed/demand charges are proposed to be charged on the basis
of sanctioned load. Energy charges are proposed to be continued to be levied
on energy consumption by the consumers of all categories. With this proposal
for introduction of two part tariff, the Board has also proposed to discontinue
the recovery of monthly minimum charges applicable to these categories. The
Commission in its first two orders has been directing the Board to consider
introduction of two part tariff for at least Large Supply and Medium Supply
industrial consumers. In its latest Tariff Order for 2004-05, the Commission
had directed the Board to prepare a detailed and well considered proposal for
introduction of two part tariff for Large Supply and Railway Traction consumers.
It was further directed that the proposal should cover other categories as well
especially Medium Supply and Small Power if not some others also.
Various consumers? associations have objected to the proposal of the Board
for introducing two part tariff. The following issues have been raised in this
context:
(i) It has been pointed out that fixed/demand
charges proposed at Rs.150/- per KVA for PIUs/arc furnaces and Rs.100/- for
general industry should be the same and there is no justification for levying
higher fixed/demand charges on PIU/arc furnaces.
(ii) Rate of fixed/demand charges is high and the consumers having low consumption/load
factor would be hard hit as their average rate would increase substantially.
(iii) The levy of fixed/demand charges in
case of general consumers would be an additional burden on the consumers. This
should not be levied.
(iv) Demand/fixed charges should be leviable
on actual maximum demand and not on sanctioned contract demand in case of Large
Supply and Railway Traction consumers.
(v) At the time of power cuts, the per unit
cost of the industrial consumers would increase substantially as industrial
consumers may not be able to consume even the energy required to recover fixed
charges. It has been emphasized that in case two part tariff is to be introduced
then there should be provision for reduction of fixed charges proportionate
to power cuts.
(vi) There should be provision for maximum
overall rate to check abnormal increase in average rate as was prevalent when
two part tariff was in force for Large Supply and Medium Supply consumers a
few years back.
(vii) Various consumers? associations/forums
have in general appreciated the proposal to discontinue levy of monthly minimum
charges but have opposed the proposal for levy of fixed/demand charges.
PSEB in its reply has stated that:
(i) Fixed/demand charges for PIUs/Arc Furnaces
are proposed to be at higher rates due to higher utilization of assets/infrastructure
by them as their load factor is much higher as compared to general industry.
Demand factor in respect of PIUs is also higher.
(ii) The Board?s fixed costs are about 40%
and it has been proposed to recover only 19% of this cost through revenue from
fixed/demand charges. The Board would gradually increase the fixed charges to
the level of 40% in the coming years as fixed costs of the Board are about 40%
of total revenue expenditure/costs. Also the average rate for single part tariff
would be equal/comparable to average rate under two part tariff.
(iii) The tariff is designed in such a way
that overall level of revenue recovery through two part tariff structure is
the same as it would have been under the single part tariff.
(iv) Fixed charges are leviable on the basis
of commitment made by the Board and consequent reservation of capacity by the
Board.
(v) No relief in demand/fixed charges proportionate
to power cut is feasible as there is no saving in fixed costs of the licensee
during power shortage.
(vi) Provision of maximum overall rate would
lead to complicated billing procedure besides having financial implications.
(vii) For any utility some minimum revenue
inflow is essential to meet with its fixed charges. It could be recovered either
through minimum charges or through fixed charges.
The Commission notes that various issues in implementing two part tariff
need detailed examination. This is especially important in view of vastly different
views of the consumers on the subject. Moreover the issue needs a detailed study
as the Board had earlier changed over from two part tariff to single part tariff
for Large Supply and Medium Supply categories. The Commission, however, observes
that almost all States (except Punjab, Haryana and Goa) have introduced
two part tariff for Large Supply category and most of the states have introduced
two part tariff for Railway Traction category.
The Commission, therefore, decides to continue with the present system of
single part tariff for the current year and levy of monthly minimum charges
at the rates approved by the Commission as heretofore. The Commission further
decides to introduce two part tariff for Large Supply and Railway Traction categories
from the year 2006-07. The Commission, therefore, directs the Board to prepare
a detailed and well considered proposal in this regard and submit the same to
the Commission within 3 months of this order. The Board should keep in view
the problems quoted by the objectors while framing the proposal. The proposal
should contain load and contract demand profiles of different types of industries
under Large Supply category and Railway Traction consumers. The proposal should
bring out the reasons for reverting back from two part tariff to single part
tariff earlier, revenue implications on the consumers and for the Board as well.
8.2 SLABS IN DS CATEGORY
PSEB has proposed introduction of a new slab of 0-30 units under DS
category so that marginal/economically weaker consumers alone get the benefit
of substantially subsidized tariff of Rs.2/- per unit. The Board has proposed
to modify the existing
slabs. The existing and proposed slabs are as under:
| Sr. No. |
Existing |
Proposed |
| (i) |
Upto 100 units/month |
Upto 30 units/month |
| (ii) |
101 to 300 units/month |
31 to 100 units/month |
| (iii) |
Above 300 units/month |
Above 100 units/month |
Many consumers? associations have objected to the proposal of PSEB for restructuring
the slabs. It has been pleaded that the proposal is not in conformity with the
objectives of the new society to be built. The Board in its response has stated
that it agrees in principle that the proposal of two slabs i.e. 0-100 and above
100 units is for the purpose of simplicity. However, the slab of 0-30 units
has been proposed to provide lower tariff to the weaker sections which is in
conformity with the provision in the draft National Tariff Policy.
The Commission notes that the addition of 0-30 units slab is statedly
proposed by the Board to protect the interests of the poorest consumers. The
Commission further notes that the draft National Tariff Policy provides that
the consumers below poverty line, who consume below specified level, say 30
units per month, may receive a special support through cross subsidy. It further
provides that tariff for such designated group of consumers would be atleast
50% of the average cost of supply. A similar provision exists in the National
Electricity Policy notified by the Ministry of Power, GOI.
The Commission also notes that the draft National Tariff Policy is
still under discussion and may take some time before it is notified by the Govt.
of India. In the State of Punjab the tariff rate applicable to
this category with monthly consumption of 0-100 units is about two third of
average cost of supply. The Commission also notes that there is no demand from
the consumers for introduction of a new slab for economically weaker consumers
as proposed by the Board. The Commission further observes that presently domestic
SC consumers having load upto 300 watts are allowed free supply upto 50 units
per month. The Commission also observes that consumption of 30 units per month
is not adequate even for poor sections of the society. Also change in existing
slab would effect some consumers very adversely. The Commission considers it
not advisable to change the slabs at this stage especially in the current year
in view of increase in tariff. The Commission further observes that the present
slab system under Domestic Supply category had been reviewed very recently in
the Commission’s Tariff Order for 2004-05 and it was decided to maintain status
quo.
The Commission, therefore, decides to continue the existing slabs in Domestic
Supply category.
8.3 TWO OR MORE CONNECTIONS IN ONE PREMISES
Some consumers? forums have objected to the policy of the Board for
not allowing more than one connection in a Domestic Supply consumer premises
where such additional connection(s) are required due to social problems like
family partition or a portion being let out to a tenant. It has been brought
out that the Board has been insisting upon billing the entire consumption as
a single consumer under DS category and denying the benefit of slab system to
each family unit. It has further been brought out that the Board has been frequently
changing the policy in this regard and the excess money recovered from the effected
consumers during transition period is not being refunded by the Board.
The issue of defining the premises and releasing one or more than one
connection in the same premises has been laid down in the Sales Regulations
of the Board. It has also been laid down that where more than one connection
(other than that of Domestic consumers) is detected in the same premises, the
connections are required to be clubbed into one connection. In respect of DS
categories, the Board is permitting release of a separate DS connection for
each family unit in one house/premises where many families live and are having
separate kitchens. Similarly separate connection is allowed to be released to
the authorized tenant(s) subject to completion of certain formalities/receipt
of undertaking etc. from the landlord. These instructions are also applicable
to the existing consumers. Further in all such (existing as well prospective)
cases meters are required to be installed at an accessible place near the gate
of the premises to avoid any chance of theft of energy.
The Commission notes that the definition of premises reading as ‘premises
is a unit of building complex, which has separate entry, and is appropriately
partitioned from the neighbouring premises in a manner that electric connection
running in the said premises can not be used in the neighbouring premises and
vice-versa’ provided in the Sales Regulations of the Board is quite clear. The
Commission observes that in respect of Domestic Supply consumers, ground realities
vis-à-vis problems of Domestic Supply consumers of the State have to be kept
in view. The Commission observes that under the present social customs/practices
prevailing in the State wherever there is genuine division/partition of a family,
separate portions of the same house/premises are used by the newly formed individual
family units. The Commission further observes that as such it is essential to
allow running/release of separate connection for each family unit having separate
kitchen in the same house and all these connections in one premises need to
be treated as independent connections for billing purposes under DS category
i.e. tariff applicable for each individual connection would be as per slabs
provided under DS category. The Commission also observes that the tenants would
furnish requisite affidavit for having hired the said portion as heretofore
so that benefit of being billed in lower slab is not misused. The tenants would
also furnish an affidavit from the landlord that the landlord would clear all
the liabilities, if any outstanding against the tenant, as per prevailing instructions.
All these connections shall be metered and consumers would pay ACD/Security,
Service Connection Charges as one time charges besides paying meter/MCB rentals,
service charges and electricity bill etc. However, energy meters would be installed
at an accessible place near the gate to avoid chances of theft of energy and
to facilitate the same being read conveniently. The Commission further observes
that all decisions would have prospective effect only.
The Commission, therefore, decides to uphold present policy of the Board in
respect of premises/houses of DS consumers and the existing instructions permitting
release/running of more than one connection for each family unit(s) having separate
kitchen/tenant subject to completion of requisite formalities and providing
energy meter(s) at an accessible place near the gate, shall continue. These
new connections for the family units/tenants would be treated as separate connections
for all intents and purposes.
8.4 PENALTY FOR UNAUTHORISED LOADS
PSEB has requested for revocation of suspension of the checking of
connected load for Domestic Supply consumers. It has been brought out that with
the rapid urbanization in the State of Punjab, there has been
consequent growth in per capita consumption of domestic consumers and installation
of unauthorized loads by the consumers. It has further been brought out that
unauthorized loads in domestic sector have potential to cause frequent interruptions
and outages to the distribution system leading to overloading of transformers/lines,
cables and service lines etc. resulting in deterioration of quality of supply.
It has also been brought out that continuation of suspension of checking of
connected load would have serious implications on the overall loss reduction
and revenue enhancement programme.
The Board has also intimated that keeping in view the provisions of Electricity
Act, it would evolve appropriate guidelines and redressal mechanism to provide
relief to any victimization or harassment that may inadvertently result. The
Board has also proposed to introduce a scheme of ‘Voluntary Disclosure of Connected
Load and Meter Status’ for all consumer categories with the consent of the Commission.
The Board has also stated that when some Domestic Supply consumers are caught
stealing energy by using improvised instrument installed in the internal wiring
inside the consumer premises which affects the working of the meter, then the
amount of compensation can not be worked out correctly till load of the consumer
is checked. The Board has, therefore, submitted for revocation of this directive.
The Commission in its Tariff Order for 2004-05 had decided to suspend
checking of connected load by the Board for Domestic Supply consumers. The Commission
had also directed the Board to come up with a suitable and practical proposal
in this regard alongwith ARR and Tariff Application for the next year.
Various consumers? organizations and chambers of industrial consumers
have brought out that there should be no checking of connected load as it leads
to harassment of consumers. They have also brought out that some times additional
loads/points are installed by the consumers to meet their urgent requirement.
The Commission notes that checking of loads for domestic consumers
leads to harassment of consumers and consequential complaints/disputes. On the
other hand, there is no revenue gain to the Board on this account. The Commission
however observes that whenever any Domestic Supply consumer is caught stealing/abstracting
energy either by tampering the meter or bypassing the meter or kundi connection
or directly hooking Board’s lines, then checking of load of the consumers is
essentially required for determining quantum chargeable from the consumers.
The Commission, therefore, decides that suspension of checking of load of
domestic consumers would continue for the current year also. However, the Board
would be at liberty to check the connected load of Domestic Supply consumers
who are found abstracting energy illegally either through kundi connection/hooking
Board’s distribution line/cable or by tampering or bypassing the meter
etc. The Commission also decides that the Board should immediately introduce
a scheme of ‘Voluntary Disclosure of Connected Load and Meter Status’
for Domestic and Non-Residential Supply consumers.
8.5 METER RENTALS
Some general category consumers/consumer forums have objected to the
Board’s present system of charging meter rentals on account of provision of
meter/metering equipment/MCB etc. by the Board at the premises of the consumers.
It has been brought out that due to substantial reduction in cost of meters/metering
equipments and interest rates, the present rates of meter rentals need immediate
substantial reduction. It has also been submitted that the Board is charging
rentals @ 1.6 paise per rupee cost of meter/metering equipment per month and
full cost of meter/metering equipment is recovered in a period of about 62 months..
It has also been stated that there is also need for reduction of security deposit
rates for meter/metering equipment. It has further been brought out that whenever
meter/metering equipment gets damaged due to negligence on the part of consumers,
the cost of meter recoverable as per Schedule of General Charges fixed in April
2000 needs immediate review for reduction as there is substantial decrease in
cost of meter/metering equipments.
Presently meter rentals are determined @ 1.6 paise per rupee cost of
meter/metering equipment where meter/metering equipments are provided by the
Board at the consumers’ premises. For single phase and three phase whole current
meters, the rates of meter rentals have been worked out in absolute amounts
and have been specified by the Board for different ratings in Schedule of General
Charges/Sales Regulations. For equipments not so covered, monthly rentals are
to be calculated in absolute terms by the field officers of the Board with the
same formula @ 1.6 paise per rupee cost of meter/metering equipment. The rentals
being charged for meter/metering equipment/MCB etc. are a part of non tariff
income of the Board. Security deposit rates are presently covered under Sales
Regulations of the Board and the same would be covered under Supply Code being
finalized by the Commission. Regarding recovering the cost of meter, the procedure
is laid down in Sales Regulations of the Board and separate rates have been
specified for meter/metering equipment damaged due to the fault/negligence of
the consumers in case meters are irreparable and separately for those repairable..
The cost being recovered for meters damaged due to the fault/negligence of the
consumers is a part of existing Sales Regulations/Schedule of General Charges
which are yet to be submitted alongwith justification by the Board for approval
of the Commission.
The Board in its response dated May 17, 2005 has stated
that the issue is being examined in the Board and the Board would submit its
proposal shortly for approval of the Commission.
The Commission notes that there is a case for reduction in meter rentals
and security deposits due to substantial decrease in the cost of meters and
interest rates. The Commission also notes that the cost of meter/metering equipment
recoverable from the consumers, wherever meter/metering equipment is damaged
due to fault/negligence of the consumer, also needs to be reviewed. The Commission
further notes that in the absence of details and detailed proposal from the
Board, the decision on the same can not be taken by the Commission.
The Commission, therefore, directs the Board to submit a detailed proposal
for revision of rentals for meter/metering equipment/MCB etc, rates of security
deposit and cost recoverable from the consumers in case of damage of meter.
The Board should submit appropriate proposal within 2 months from the date of
issue of order to enable the Commission to review the same and take a decision.
The Commission further decides that in the meanwhile existing system of the
Board may continue.
8.6 RECEIVABLES
Some industrial consumers? associations have brought out that receivables/defaulting
amount of the Board are rising substantially and the Board is not indicating
the figures of defaulting amount in its ARR. It has further been brought out
that defaulting amount against the State Government Departments is rising and
the Board is not taking any action to disconnect supply/recover the outstanding
amount which is contrary to the instructions of the Board, according to which
defaulting consumers are to be disconnected. They have also pointed out that
the Board is giving a discriminatory treatment to them vis-à-vis departments
of Govt. of Punjab and have requested the Commission to direct the Board to
furnish figures of defaulting amount in the ARR/Tariff Application and also
take immediate action to reduce the outstandings.
The Board has intimated that collection efficiency of the Board is
99% and is almost the highest amongst all the SEBs/distributions licensees of
the country. The Board has also supplied details of the receivables.
The Commission has studied the data pertaining to receivables/defaulting
amount and observes that the defaulting amount of the Board can be classified
under 4 categories:
(i) Amount involved in court cases/litigation/cases
pending before Board’s various review channels.
(ii) Amount outstanding against Government
Departments where disconnection of supply may lead to inconvenience for the
general public and law & order problem in certain cases;
(iii) Old cases where permanent disconnection
orders have been effected;
(iv) Other consumers.
The Commission notes that there is increase in outstandings against
Govt. departments and other consumers. The Commission also notes that the Board
has little control on clearance of defaulting amount involved in litigation.
However the Board should take up with the concerned Government departments for
expeditious clearance of outstandings and payment of current bills. The Commission
further observes that the Board has to be very vigilant so that outstandings
against other consumers are not allowed to increase and efforts are made to
recover outstanding amount from the consumers whose premises have been disconnected
by way of adjustment of their security/ACD and filing recovery suits.
The Commission notes that the position of receivables for the last 4-5 years
is as under:
(Rs. in crores)
| Year |
Receivables at the
end of the year
|
Total Revenue of the Board
including non-tariff income
|
Receivables in equivalent
number of days revenue |
Receivables as percentage
of revenue |
| 1998-99 |
414 |
3396 |
44 |
12.2 |
| 1999-2000 |
446 |
3654 |
45 |
12.2 |
| 2000-01 |
399 |
4302 |
34 |
9.3 |
| 2001-02 |
491 |
4585 |
39 |
10.7 |
| 2002-03 |
572 |
5341 |
39 |
10.7 |
| 2003-04 |
598 |
6112 |
36 |
9.8 |
The Commission also notes that the comparative position of 5-6 major
Electricity Boards/Utilities (Ref. Tata Energy Data Directory and Year Book
2002/03) for the year ending March 31,2000 is as under:
(Rs. in crores)
|
Name of State |
Total Receivables
|
Receivables as percentage
of revenue |
| Andhra Pradesh |
678 |
15.0 |
| Haryana |
200 |
10.5 |
| Maharashtra |
4280 |
40.8 |
| Punjab |
475 |
13.4 |
| Rajasthan
(TRANSCO) |
522 |
13.8 |
| Uttar Pradesh
(Power Corporation) |
5699 |
102.8 |
| West Bengal |
1749 |
83.6 |
The Commission notes that there is a minor difference between the figures
of receivables as contained in the balance sheets of the Board and as given
in the compilation by TERI. The Commission observes that collection efficiency
of the Board is about 99% and the receivables are equal to less than 40 days
revenue in the last 4 years. The Commission also observes that position of the
Board is almost at the top as far as receivables are concerned and can further
improve if the receivables from State Government departments are cleared and
outstandings against other consumers are not allowed to increase.
The Commission decides that the Board should take up the matter with the State
Government at the appropriate level for immediate clearance of outstandings.
The Commission also directs the Board to take effective steps to reduce outstandings
against other consumers and the Board should furnish age analysis of the receivables
alongwith the next ARR.
8.7 DEPRECIATION RESERVE FUND
PSEB has requested the Commission for revoking its directive for creation
of Depreciation Reserve Fund. It has been brought out that it has not come across
any instance of such a Depreciation Reserve Fund in any corporate or State entity.
It has
also been submitted that from a first principle basis, funds required for any
investment would be met firstly from internal resources and the balance is met
from long-term loans. It has been further stated that the funds required for
repayment of existing long-term loans are met from the internal accruals inclusive
of depreciation provisions. The Board is also of the firm opinion that creation
of separate Depreciation Reserve Fund is not required even under the law.
The Commission had issued a directive to the Board in its Tariff Order
for 2004-05 that the Board should submit a proposal for creation of Depreciation
Reserve Fund containing a proper system to ensure that the money in the proposed
Depreciation Reserve Fund is not diverted by the Board for unauthorized purposes.
The Commission notes that there can be no dispute on the basic principle
that the depreciation accruals are to be earmarked for the specific purpose
for which these are meant. This is so in all the organizations. The Commission
further notes that the depreciation can be used either for replacement of old
assets or creation of new assets or repayment of loans obtained for creating
assets. It is to ensure that the funds made available to the Board through depreciation
are used for the purpose for which these are meant and are not diverted for
any other purpose like meeting revenue deficit etc. For this purpose, the Board
can come up with a suitable proposal. Regarding Board’s observation, as already
stated above and in the last Tariff Order also, the money available through
depreciation can be used for repaying loans taken for capital purposes. These
can also be used for funding capital works even under the system being advised
by the Commission.
The Commission, therefore, decides that the Board should devise methodology
to ensure that depreciation funds are used only for the purpose for which these
are meant and are not diverted.
8.8 GENERAL PROVIDENT FUND
PSEB has requested the Commission to defer the applicability of Commission’s
directive for creation of a separate General Provident Fund Account till the
creation of corporate entities under the proposed reforms. It has also been
intimated that a part of provident fund contribution of the employees is currently
being utilized by the Board to fund its capital investment plan and the approval
of the Government of Punjab has already been obtained. It has also been intimated
that the Board is providing interest on this amount to ensure that the assured
return is provided to the employees as per the provisions of the General Provident
Fund Scheme. It has further been intimated that the Board has also made investment
to the tune of about Rs.151 crores (till March 2004) out of this fund, in other
securities. The Board has also brought out that there has been no case of delay
in payment of provident fund to any retiree/employee for shortage of funds.
It is apprehended by the Board that in case a separate account is created as
per directive of the Commission, then it may not be able to generate enough
return to provide assured return to the employees on long term basis. Simultaneously
the Board would have to find alternate sources for arranging funds to meet with
capital funding requirements.
The Commission had issued a directive in Tariff Order for 2004-05 that
the Board should submit a detailed proposal for creation of a separate General
Provident Fund Account alongwith its ARR for the year 2005-06 or during its
processing. It was further provided that atleast new accretions in the General
Provident Fund should be deposited every year in a separate account. The Board
had also been directed to ensure that deposits in the General Provident Fund
Account of the employees are deposited without any undue delay and withdrawal
from account be restricted to authorized purposes only.
The Commission notes that diversion of deposits in General Provident
Fund for meeting the capital investment fund requirement can be made even from
the separate account as approval of the State Government already stands obtained
by the Board. It should, however, be treated as interest bearing loan from the
proposed General Provident Fund Account. It has also to be ensured that the
deposits in General Provident Fund Account are not used for funding revenue
expenses.
The Commission, therefore, decides that the Board should take steps to open
a separate General Provident Fund Account. The new accretions in the General
Provident Fund Account of the employees should be deposited in this account.
In case any money is required by the Board to be utilized for funding capital
investment plan requirements, the Board may take interest bearing loan from
the General Provident Fund Account.
8.9 SUBMERSIBLE PUMPSETS
The Board has proposed that the flat rate for AP tubewells having submersible
pumpsets should be 24% higher than the flat rate for AP tubewells with monoblock
pumpsets. The Board has made this proposal as according to it the energy consumption
by the submersible pumps is more by 24% than the energy consumption of monoblock
pumps having the same horse power rating. The Board has supplied field reports
to substantiate its version.
The Commission notes that the results of two studies supplied are at
variance and no definite and conclusive data regarding higher consumption of
submersible pumpsets has been made available by the Board.
The Commission, therefore, decides not to accept this proposal of the Board
for charging higher flat rate to submersible pumps and decides to continue the
existing practice of charging same flat rate for all unmetered AP tubewells.
8.10 KVAH TARIFF
Many industrial consumers? associations/chambers and one employees?
association of the Board have suggested for introduction of KVAH consumption
based tariff in lieu of KWH based tariff for atleast Large Supply and Medium
Supply consumers. It has been further brought out that the suggestion if implemented
would motivate the Large Supply and Medium Supply industrial consumers to have
higher power factor which would in turn help in improving the system parameters
and reduce technical losses.
The Commission in its Tariff Order for 2004-05 had directed the Board
to submit a detailed paper on the introduction of KVAH tariff atleast for Large
Supply, Medium Supply and Railway Traction categories in the ARR for 2005-06.
In its response the Board has stated that experience from other states
which have introduced KVAH tariff for their HT consumers has revealed that it
had adversely affected revenue of the power utilities of those states. It has
further been stated that the Board is on the verge of unbundling and can ill-afford
to experiment with the introduction of KVAH tariff which may result in loss
of revenue.
The Commission had decided to raise the threshold limit of power factor
from 0.88 to 0.90 in respect of Large Supply, Medium Supply and Railway Traction
consumers effective from July 01, 2005 in the Tariff Order for
2004-05. The Commission had also decided to introduce power factor incentive
w.e.f. July 01, 2005 for those consumers who achieve higher power factor. Thus
the purpose of motivating the consumers to improve their power factor is likely
to be achieved with the introduction of power factor incentive. The Commission,
therefore, observes that it would be worthwhile to watch the benefits of upward
revision of threshold limit of power factor and introduction of incentive for
higher power factor and then to review the issue. In the meantime the Board
is advised to carry out a detailed study on the proposal of introduction of
KVAH based tariff.
The Commission, therefore, decides to continue with the existing system of
KWH based tariff and directs the Board to carry out study for practicability
of introducing KVAH tariff for Large Supply, Medium Supply and Railway Traction
consumers.
8.11 HIGH VOLTAGE REBATE
PSEB has proposed to change the criteria of allowing high voltage rebate
permissible for all categories of consumers except Railway Traction connected
at 11 KV and above. It has been proposed that the consumers connected at prescribed
voltage level as per PSEB norms would not be entitled for any rebate. It has
been further proposed that the consumers connected at voltage higher than PSEB
norms for connected load would be entitled for 3% rebate but the consumers connected
at voltage lower than PSEB norms would be levied surcharge. The quantum of surcharge
has not been specified.
The present system is as follows:
(i) Large Supply consumers and consumers
of all other categories except Railway Traction catered supply at 33 KV/66 KV
are allowed rebate @ 3% of energy charges. LS consumers and consumers of other
categories except Railway Traction, catered supply at 132 KV/220 KV are allowed
rebate @ 5% of energy charges;
(ii) For Large Supply consumers except Arc
Furnaces having contract demand exceeding 2500 KVA and upto 4000 KVA catered
at 11 KV, the energy consumption is enhanced by 10% to cover for transformation
losses, incremental line losses and service charges. 17.5% surcharge is leviable
on all Arc Furnace consumers and other Large Supply consumers having contract
demand above 4000 KVA and catered at 11 KV.
In addition Medium Supply, Small Power, Domestic Supply and Non- Residential
Supply consumers catered supply at 11 KV are allowed 7.5% rebate on their bill
amount. Also Large Supply consumers catered supply at LT i.e. 400 volts are
levied 20% LT surcharge. The steel rolling mills catered supply under LS category
but connected at LT are levied steel rolling mill surcharge @ 5% in addition
to LT surcharge @ 20%.
Some industrial consumers? associations have objected to the proposal
of PSEB with the plea that whenever supply is catered at 33 KV or higher voltage,
there is a significant cost saving to the Board in terms of infrastructure and
technical losses. It has also been submitted that substantial investment is
made by the consumers in availing supply at higher voltage thus the consumers
are eligible for high voltage rebate. It has been brought out by some of the
industrial consumers? associations that the Board in its ARR for the year 2004-05
had recommended enhancement of quantum of rebate and there is no reason for
discontinuing the rebate being allowed to 33 KV/66 KV consumers for the last
more than 10 years. It has also been brought out that high voltage rebate, as
decided by the Commission in its Tariff Order for 2004-05, should atleast be
continued till the cost of supply is calculated consumer-wise and voltage-wise
as cost of electricity would definitely be less for EHT consumers.
The Commission observes that it is following the concept of average
cost of supply. The Commission also observes that tariffs for Large Supply consumers
had been worked out by the Board at base voltage level of 11 KV and that of
Medium Supply consumers the tariffs had been worked out at base voltage level
of 400 volts. The Board had also been allowing/proposing rebate for high voltage
supply. These basis of tariff had been accepted by the Commission. The Commission
observes that the Board in its ARR for 2004-05 had proposed higher rebate @
6% for Large Supply consumers getting supply at 33 KV or higher voltage. The
Commission also observes that in case any Large Supply consumer is connected
at voltage lower than 11 KV then he is liable to pay LT surcharge as the Board/Licensee
is required to invest additional amount in creating capital infrastructure and
bearing additional T&D losses. The Commission further observes that where
supply is availed at a voltage higher than base voltage level, the utility is
benefited by way of saving of capital cost and operating costs besides reduction
in losses. Basically rebate is allowed to provide incentive to consumers to
take measures for improvement of grid condition and lowering of T&D losses.
Thus it is considered advisable to continue the existing provisions of 3% rebate
to consumers availing supply at 33 KV/66 KV. The Commission also considers it
prudent to continue 5% rebate to those consumers (other than Railway Traction)
catered supply at 132 KV/220 KV.
The Commission directs the Board to submit a comprehensive proposal bringing
out all the aspects of the matter and the proposal should also include revenue
implications. The proposal should be submitted alongwith next ARR for 2006-07.
Meanwhile the Commission decides to continue the existing system.
8.12 DEMAND SURCHARGE FOR EXCEEDING CONTRACT DEMAND
PSEB has proposed to charge maximum demand over and above the contract
demand at 200% of the proposed demand charges for Large Supply, Bulk Supply
including M.E.S and Railway Traction consumers.
Presently consumers of all these categories are covered under single
part tariff and energy charges are based on actual energy consumption subject
to monthly minimum charges. In case of Large Supply category, monthly minimum
charges are based upon connected load and in case of Bulk Supply including MES
and Railway Traction categories these are based upon contract demand. Any excess
demand over and above the sanctioned contract demand is charged @ Rs.250/- per
KVA irrespective of number of defaults for Large Supply and Railway Traction
consumers. However, for Bulk Supply consumers including M.E.S. connected at
11 KV or higher voltage the excess distribution transformer capacity installed
by the consumers is treated as excess demand and the consumers are charged @
Rs.750/- per KVA of excess distribution transformer capacity for each default.
Some industrial consumers? associations have objected to this proposal
of the Board and have suggested that the charges for excess demand over and
above the sanctioned contract demand should be 1.2 ? 1.25 times of normal demand
charges. It has also been suggested that there should be tolerance of atleast
10% of sanctioned contract demand and surcharge/penalty should be leviable only
if actual demand exceeds beyond the tolerance level over and above the contract
demand.
The Board has not specifically commented upon this issue but the proposal
of the Board is a part of the proposal for introduction of two part tariff.
The Commission observes that the ‘contract demand means maximum demand
in KVA sanctioned to the consumers and the same shall not exceed 100% of sanctioned
load in KW by using power factor of 0.88’. The Commission also observes that
‘maximum demand in any month is defined as highest average load measured in
Kilovolt Amperes during 30 or 15 consecutive minutes period of the month’. The
Commission further observes that presently meters with 30 minutes integration
for consumers billing are installed. The Commission further observes that the
Board’s system is planned and provided on the basis of commitment of consumers
i.e. contract demand as such in case the consumers’ actual maximum demand in
any month exceeds the sanctioned contract demand then it leads to overloading
of system, adversely affecting the performance of line, sub-station and the
transmission & distribution system besides increase in losses and violation
of agreement. Even capacity of the metering equipment to be provided is determined
on the basis of sanctioned contract demand. The Commission, therefore, observes
that consumers exceeding sanctioned contract demand need to be penalized.
The Commission decides that since two part tariff is not being introduced
for the time being, as such demand surcharge for demand exceeding sanctioned
contract demand should continue as per the prevalent rates.
8.13 PARALLEL OPERATION CHARGES
Many industrial consumers? chambers/associations have objected to the
parallel operation charges being charged from the Captive Power Plant owners.
It has been brought out that parallel operation charges have been levied by
the Board not only on such Captive Power Plant owners who are running in parallel
but also on those who do not run the Captive Power Plant in parallel with the
Board?s grid system. It has been brought out that consumers desirous of running
Captive Power Plants in parallel have to make huge investment to strengthen
their generation system, control equipment to withstand high voltage level of
the Board?s grid and the large grid disturbances. It has also been brought out
that the Board does not spend a single penny while paralleling is resorted to.
It has been brought out that Captive Power Plant owners like to operate their
plants in parallel with the Board?s grid only to optimize their generation.
Such consumers can not draw power from the Board?s system as they are governed
by the limitation of contract demand. It has also been pointed out that the
Board is also running its grid in parallel with a number of constituents in
the region and is not paying any parallel charges to any of them.
As per prevailing instructions of the Board, Captive Power Plant owners
who are consumers of the Board and want to have interfacing with the Board’s
system with option to run the plant in synchronization with the Board’s system
are required to pay monthly parallel operation charges @ Rs.200/- per KVA of
5% of the installed capacity of TG Sets in KVA. In addition those Captive Power
Plant owners who are not Board’s consumers but are willing to get power from
the Board’s system during breakdown, maintenance and failure of their power
plant are allowed the facility to operate their DG/TG sets in synchronism with
grid and run their load from the Board’s system subject to availability of power.
Such Captive Power Plant owners are also required to pay monthly parallel operation
charges @ Rs.200/- per KVA of 5% of the installed capacity of TG Sets in KVA.
Consumers of the latter category are also required to pay higher of monthly
charges @ Rs.200/- per KVA or for sale of power at double the normal relevant
tariff on monthly basis. Further 10% of installed capacity of Captive Power
Plant is to be kept reserved by the Board through its generation and transmission
system.
The Commission in its Tariff Order for 2004-05 had directed the Board
to furnish full justification of parallel operation charges being recovered
from the consumers. The Board has supplied the detailed position in the ARR
for the year 2005-06. It has also been concluded by the Board that there is
need to undertake significant studies which will take time and effort to arrive
at determination of charges payable by the Captive Power Plant owners.
PSEB in its reply has further stated that parallel operation charges
are adequate and necessary because the consumers having captive power plant(s)
running in parallel with the system of the Board are directly using supply through
grid, transmission lines, generating system and other assets relating to the
Board. Also the consumers enjoy uninterrupted power supply during 24 hours a
day. In order to provide benefits to CPPs during parallel operation of the plants,
the Board is required to maintain its system, at a cost, which is not recovered
from the CPPs through the charges for the contracted demand.
It has also been stated that in order to provide grid support, the
Board would require to draw additional resources either from its already contracted
capacities or additional capacities from others. Under the present requirements
to maintain the grid quality, the intermittent supply requirements put strain
on managing the operations. The imbalances resulting in financial loss to the
Board need to be commercially covered. It has also been clarified by the Board
that charges are leviable on those consumers/CPP owners who are running their
load through grid in parallel to the Board’s system and not those who are having
Captive Power Plants but not in parallel to the Board’s system.
The Commission notes that the consumers or persons having Captive Power
Plant running in parallel with the Board’s system enjoy following benefits over
and above the others:
· Availability of uninterrupted and reliable power supply
with better voltage regulation.
· Stability of power supply to such an industry is far
far better.
· All variations in load of the owner or variation in output
of the Captive Power Plant are absorbed by the grid thereby minimizing chances
of tripping of Captive Power Plant.
· Electrical performance of Captive Power Plant is better
with the grid support.
The Commission notes that all these benefits do cost the Board. The
Commission also notes that presently monthly minimum charges are leviable on
the basis of sanctioned load in case of Large Supply consumers. Such consumers
having Captive Power Plants are levied monthly minimum charges for the load
minus the TG set capacity of Captive Power Plants; thus the consumers are not
liable to pay even the monthly minimum charges for this load and quantum of
parallel operation charges is a small fraction of monthly minimum charges. The
Commission also observes that there is need for commissioning a study by the
Board for assessing the quantum of charges.
The Commission therefore decides that till the study is complete the parallel
operation charges being levied on Captive Power Plant owners shall continue
to be levied at the prevalent rates. These parallel operation charges shall
be leviable on all Captive Power Plants which run in parallel/synchronism with
grid of the Board, irrespective of the fact whether Captive Power Plant owners
are consumers of the Board or not. The Commission further decides that adequate
measures be taken by the Board to ensure that no Captive Power Plant owner is
allowed to run the plant in parallel with the Board’s system without prior
permission and getting the adequacy of the protection system checked from the
Board.
8.14 GENERAL CONDITIONS OF TARIFF AND SCHEDULE OF GENERAL CHARGES
The industrial consumers? associations/forums have been objecting to
the other charges being levied by the Board to the consumers without approval
of the Commission. These charges are being levied under General Conditions of
Tariff and Schedule of General Charges of the Board.
The Board has not submitted the justification for the specified quantum
of various charges. The Board has, however, recently submitted General Conditions
of Tariff for approval of the Commission.
The Commission observes that the Board has been allowed to recover
these charges on year to year basis and these need to be reviewed by the Commission.
The Commission will invite public objections in the matter to know the views
of the public and take a decision in the matter before issue of the next tariff
order.
The Commission decides to continue the present charges including
rentals and deposits which are being collected by the Board as per the “Sales
Regulations for Supply of Energy to Consumers”, at the existing rates.
8.15 MONTHLY MINIMUM CHARGES TO PUBLIC LIGHTING CONSUMERS
Some Municipal Committees/Councils have brought out that under the
proposed two part tariff system the Board has proposed to abolish monthly minimum
charges for all categories except Public Lighting category. It has also been
brought out that as per the Board’s proposal monthly minimum charges would be
applicable to Public Lighting consumers even under the two part tariff comprising
of fixed charges and energy charges. It has further been brought out that presently
monthly minimum charges are calculated by assuming 8 hours running of lamps/lighting
points round the year and some street light points remain defective for different
periods, as such monthly minimum charges on the basis of average running of
8 hours period are on higher side. It has been submitted that it should be reduced
to 6 hours per day. It has further been submitted that if monthly minimum charges
are to be retained then there is no need for fixed charges in the street light
tariff.
Presently all Public Lighting consumers are governed by single part
tariff leviable on energy consumption of the consumers. However, monthly minimum
charges clause provides that annual revenue is to be calculated by assuming
8 hours per day running of sanctioned load or actual load whichever is higher
and the shortfall in revenue, if any, is chargeable to the consumers. The Board
has proposed two part tariff for this category alongwith other categories but
has also proposed to continue the levy of monthly minimum charges besides fixed
charges to Public Lighting category consumers.
In response the Board has stated that under the two part tariff, monthly
minimum charges clause would not be operative. It has also been informed that
the Board has proposed to discontinue monthly minimum charges for all categories.
The Board has not given any comments on the suggestion for reducing monthly
minimum charges on the basis of average running of 8 hours per day to 6 hours
per day.
The Commission notes that as two part tariff is not being adopted for
any category for the time being, the Public Lighting category shall also continue
to be governed by single part tariff. This would imply that fixed charges would
not be applicable but monthly minimum charges would be applicable. The Commission
observes that street lights are switched on during evening hours till next morning
and their operating hours vary from 9 ½ hours in summer to 13 ½ hours in winter.
The Commission also observes that replacement of defective street light points
is the basic responsibility of the local bodies. The Commission further observes
that monthly minimum charges are being levied on the Public Lighting consumers
on the basis of 8 hours running of load on annual basis for the last more than
30 years. The Commission further notes that monthly minimum charges are applicable
for all categories of consumers on monthly basis and Public Lighting consumers
have already been given concession for calculating the same on annual basis.
The Commission, therefore, decides to continue with the existing
system.
8.16 POWER CUTS/OTHER POWER REGULATORY MEASURES
PSEB has filed Petition No.5 of 2005 under Section 23 of Electricity
Act, 2003 for authorizing the Board to impose power cuts, peak load hour restrictions
and taking other power regulatory measures during the year 2005-06. It has been
submitted that during the year 2005-06 there shall be shortage in the availability
of power vis-à-vis unrestricted demand (in MW) and energy (in MU) during most
months of the year. It has further been intimated that while working out the
availability of power, the estimated power/energy from all sources i.e. own
power houses including share from BBMB, share from central sector power projects,
purchase from various agencies, banking from neighbouring states and unscheduled
over drawal(s) have been taken into account. It has been estimated by the PSEB
that there shall be shortage of energy and power during the year as such the
Board would be constrained to impose power cuts and take other regulatory measures
as under:
(i) to impose evening peak load hour restrictions
on industrial consumers (normally Large Supply consumers);
(ii) to impose power cuts on industrial sector
by way of weekly off days, restrictions on use of quantum of energy etc.;
(iii) to impose power cuts on Agriculture
sector, Non-Residential Supply and Domestic Supply consumers (rural and urban
sectors);
(iv) to impose power cuts on other categories
of consumers such as Bulk Supply etc. or to take other regulatory measures as
required.
Vide order dated March 09, 2005, the Commission ordered
that public notice inviting objections from the public be published in this
regard. It was also decided that public hearings in this respect would be held
alongwith hearings fixed in respect of ARR and Tariff Application for the year
2005-06. The Commission further ordered that in the meantime authorization already
issued by the Commission may continue for another three months i.e. upto
June 30, 2005. In compliance with the above order public notice was published
in various news papers on March 10, 2005 and March
13, 2005. The objections from the following were received within due date:
| Objection No. |
Name of the Party |
Reference No. and date
|
| 1. |
M/S Shakti Air Products, Chitra Talkies
Road, Amritsar |
No. Nil dated 16.3.2005 |
| 2. |
Shri Joginder Kumar, President, The
Ludhiana Electroplaters Association, Gambhir Market, Gill Road,
Ludhiana-141003. |
No.LDH/LEA/535/2005 dated 15.3.2005
|
| 3. |
Shri Angad Singh, Col.(Retd.)
General Secretary, The Consumer Protection and Grievances Redressal Forum
(Regd.), 1504, Phase 3-B-2, S.A.S.Nagar, Mohali |
No.CPGR/8746 dated 21.3.2005
|
| 5. |
Shri Jaswant Singh Virdi, General
Secretary, Cycle Trade Union (Regd.), Gill Road, Miller Ganj, Deshprem
Complex, Gobindpura, Ludhiana-141003 |
No.CTU/PSERC/PSEB/PC-PL/2005 dated
21.3.2005 |
| 6. |
Shri A.Puri, General Manager(Projects),
PACL Punjab Alkalies & Chemicals Ltd., SCO.125-127, Sector 17-B, Post
Box 152, Chandigarh-160017. |
No.PACL/PROJ/POWER/2005/3288 dated
24.3.2005 |
| 7. |
Shri S.P.Oswal, Past Chairman
Punjab State Council, Confederation of Indian Industry, Northern Region,
Sector 31-A, Chandigarh-160030. |
No. Nil dated 28.3.2005 |
All these objectors have objected to the proposal of the Board for
imposing power cuts and suggested that PSEB should develop new power projects,
improve its maintenance quality and farmers be asked to use only ISI marked
pumps so that wastage of energy is avoided. It has also been suggested that
power cuts on subsidizing categories should be applied judiciously so that Board’s
revenue from the highest revenue paying consumers is least effected. It has
further been suggested that the additional power requirements of the subsidized
categories should be met by arranging power from other sources and unscheduled
and unapproved cuts should not be imposed on industry as these impair economy
of the Board and the industry very badly.
Bharti Kisan Union has also filed a Petition wherein interalia it has
been brought out that quality of power being supplied to rural sector is very
bad as against quality of power being supplied to urban areas. The Union
has pleaded that there should be minimum discrimination between urban consumers
and rural consumers as far as quality of power is concerned. This petition is
pending with the Commission.
The Commission notes that due to mis-match between availability of
power from all sources and ever rising demand for electricity in the State,
the Board is deficit in power and is unable to supply uninterrupted power to
its consumers. To meet the demand of the consumers/general public, the Board
has to impose peak load hour restrictions on industry, put heavy restrictions
on supply of power to AP sector and impose power cuts/regulate the energy consumption
of other categories of consumers. The Commission also notes that Bharti Kisan
Union have been pleading for better quality of supply. The Commission had decided
to allow 10% rebate in tariff rates to rural domestic consumers in its Tariff
Order for the year 2004-05 due to poor quality of power supply to rural consumers.
The Commission observes that representatives of rural sector have requested
for better quality of supply to the rural consumers and not focused on lower
tariff. The Commission also observes that members of the Advisory Committee
in their meeting held on April 01, 2005 had also expressed the
view point that the Board should not discriminate with rural consumers. The
Commission appreciates the difficulties of the Board in supplying power to consumers
of all categories in urban and rural areas equitably. However, such vast disparities
in quality of power supply to different classes of consumers or between urban
and rural consumers are against the principles of justice and equality and therefore
difficult to accept.
The Commission, therefore, decides to authorize the Board to impose restrictions/power
cuts and other regulatory measures to bridge the gap between demand and supply
of power. Such measures will, however, be taken only to the minimum extent to
ensure least disturbance, dislocation and inconvenience to the consumers and
general public while keeping in view the requirement of the power system. The
Board will also ensure that purchase of power for this purpose is only for the
minimum quantum and at minimum cost. The Board should also ensure to make arrangements
to inform the consumers well in advance of the scheduled power cuts. If the
contingency so arises, the Board may impose unscheduled power cuts also. The
Commission further decides that the Board should take adequate steps to minimise
discrimination amongst consumers of different categories especially rural and
urban domestic consumers as far as possible while imposing power cuts. The Commission
also directs the Board to submit action plan for gradual reduction and ultimate
elimination of disparity in quality of power supply alongwith its next ARR for
the year 2006-07. Petition No.5 of 2005 is disposed of accordingly.
|